Farnsworth & Chambers Co., Inc. v. The United States

383 F.2d 407, 180 Ct. Cl. 992, 1967 U.S. Ct. Cl. LEXIS 107
CourtUnited States Court of Claims
DecidedJuly 20, 1967
Docket276-60
StatusPublished

This text of 383 F.2d 407 (Farnsworth & Chambers Co., Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farnsworth & Chambers Co., Inc. v. The United States, 383 F.2d 407, 180 Ct. Cl. 992, 1967 U.S. Ct. Cl. LEXIS 107 (cc 1967).

Opinion

OPINION

PER CURIAM:

This ease was referred to Trial Commissioner Paul H. McMurray with directions to make findings of fact and recommendation for conclusions of law. The commissioner has done so in a report and opinion filed on January 12, 1967. Exceptions to the commissioner’s findings and recommended conclusion of law were filed by the parties and the case has been submitted to the court on oral argument of counsel and the briefs of the parties. Since the court agrees with the *408 commissioner’s findings, opinion and recommended conclusion of law, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. Plaintiff is, therefore, entitled to recover and judgment is entered for plaintiff in the sum of $89,638.43.

OPINION OF COMMISSIONER *

McMURRAY, Commissioner:

This case involves a claim for an equitable adjustment concerning damages resulting from a changed condition 1 encountered by plaintiff in attempting to perform a construction contract entered into with the Corps of Engineers, United States Army. An adjustment in the contract price was denied by the Corps of Engineers Claims and Appeals Board, primarily, it appears, because the Board did not accept plaintiff’s report that there was a large opening in the bed of the river (a crevice, cavern, channel, trench or hole).

On June 24, 1964 the commissioner filed his report. The court handed down an opinion on June 11, 1965, 346 F.2d 577,171 Ct.Cl. 30, which found that plaintiff is entitled to recover and entered judgment to that effect, stating “[t]he amount of recovery will be determined, in accordance with this opinion, under Rule 47(c).” Stein Bros. Mfg. Co. v. United States, 337 F.2d 861, 162 Ct.Cl. 802 (1963).

The opinion of the court also stated that determination of the amount due plaintiff:

* * * should not assess against the defendant those extra costs, if any, of dewatering the cofferdam, which are fairly attributable to causes other than the changed conditions — such as leaks in cofferdam walls or an inadequate or incomplete grouting program (in-eluding grouting which plaintiff expected to perform). Nor should the defendant be charged again for the leakage through the timber crib for which it has already paid.

A formal trial was convened for the purpose of taking proof with a view to determining the amount of damages to which plaintiff might be entitled under the Changed Conditions article of the contract. During the trial plaintiff offered three witnesses, (1) a cost engineer, (2) a licensed Civil Engineer and general contractor and (3) a vice-president of plaintiff corporation experienced in general construction. These witnesses testified with respect to the subject of damages and explained in considerable detail the manner in which records were kept concerning the type of work performed, the number of hours or days worked in connection with the changed condition encountered, the type of material and equipment used and the costs involved.

Employees and representatives of defendant were present during the period when strenuous efforts were being made by plaintiff to handle the problem involved and were greatly concerned about getting the job done. Representatives of both plaintiff and defendant maintained a daily record of the labor, material and equipment used to combat the changed condition. Each party maintained notes and they were able to resolve any discrepancies found and reach an agreement before plaintiff’s monthly reports of claimed costs were filed. Defendant also made a thorough audit of all items of plaintiff’s claim from actual books and records.

All who were concerned with the operation were aware that records were being made which could be used, if necessary, to support a claim for dam *409 ages or an equitable adjustment of the contract price. 2 Testimony at the trial showed that representatives of defendant had access to the records maintained by plaintiff and, on occasion, made revisions and offered suggestions with respect to keeping those records.

Defendant did not offer any witnesses at the trial concerning damages. Counsel for defendant cross-examined plaintiff’s witnesses and indicated a desire to have the pertinent facts reflected in the record made at the trial.

At the conclusion of the trial on July 14, 1966, proof was closed and, on the same date, counsel were directed to submit memorandum reports to the commissioner on or before August 15, 1966. Each party submitted a report on August 15, 1966. Those reports are a part of the record in the case concerning the issue of damages.

In view of the court’s restriction on recovery of grouting which plaintiff expected to perform, a review of plaintiff’s grouting plans is in order. Plaintiff submitted the original grouting program to defendant on March 10, 1954 which provided for a program of drilling 3-inch grouting holes 5 feet apart on centers to depths averaging 45 feet within and around the periphery of the cofferdam cells. This planned grout curtain was to be placed prior to the beginning of any dewatering operations. It extended 1,-065 feet laterally and included 213 3-ineh holes, totaling 9,483 vertical feet of drilling.

A second set of drawings of intended grouting was submitted by plaintiff on April 4, 1954. This second plan was similar to the first. Neither of these grouting programs was put into execution.

On the basis of advice from plaintiff’s consulting geologist the grouting program was reduced to one with holes on 20-foot centers, with provision for filling in on closer centers as the need arose. The geologist made no recommendations with respect to the final depths for grouting, leaving that to the contractor. The drilling and grouting operations were to be carried on simultaneously.

Defendant’s foundation engineer, Charles Rochell, testified that there was little difference between the original plan and the one which began on 20-foot centers with intermediate holes as needed.

On July 23, 1954 when only 39 holes of the originally-planned 213 holes had been drilled to the anticipated depth and grouted, plaintiff attempted to dewater the cofferdam pool, but abandoned the effort when it was unsuccessful. Some holes which had been drilled were left open. The material placed in the grout curtain as of July 23, 1954 was 4,685 cubic feet, less than 10 percent of the estimated quantity in the dewatering plan of March 10, 1954.

Defendant’s resident engineer wrote plaintiff on August 2, 1954 expressing his dissatisfaction with the results of plaintiff’s efforts in the grouting program and the “utter inadequacy” in reducing the water level in the inside cofferdam pool more than 2% feet with a pumping capacity of 30,000 gallons per minute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Farnsworth & Chambers Co., Inc. v. The United States
346 F.2d 577 (Court of Claims, 1965)
Thomas Earle & Sons, Inc. v. United States
100 Ct. Cl. 494 (Court of Claims, 1944)
MacDougald Construction Co. v. United States
122 Ct. Cl. 210 (Court of Claims, 1952)
Stein Bros. Mfg. Co. v. United States
337 F.2d 861 (Court of Claims, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
383 F.2d 407, 180 Ct. Cl. 992, 1967 U.S. Ct. Cl. LEXIS 107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farnsworth-chambers-co-inc-v-the-united-states-cc-1967.