Farmland Preservation Ass'n v. Adams

491 F. Supp. 601, 11 Envtl. L. Rep. (Envtl. Law Inst.) 20, 1979 U.S. Dist. LEXIS 11617
CourtDistrict Court, N.D. Iowa
DecidedJune 19, 1979
DocketC 78-99
StatusPublished
Cited by2 cases

This text of 491 F. Supp. 601 (Farmland Preservation Ass'n v. Adams) is published on Counsel Stack Legal Research, covering District Court, N.D. Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Farmland Preservation Ass'n v. Adams, 491 F. Supp. 601, 11 Envtl. L. Rep. (Envtl. Law Inst.) 20, 1979 U.S. Dist. LEXIS 11617 (N.D. Iowa 1979).

Opinion

ORDER

McMANUS, Chief Judge.

This matter is before the court on all parties’ resisted cross-motions for summary judgment, filed March 19, 1979 by plaintiffs, April 9, 1979 by defendants, and April 10, 1979 by intervenor-defendants. Plaintiffs’ motion denied; defendants’ and intervenor-defendants’ motions granted.

Introduction

In this action, plaintiffs seek declaratory, injunctive and mandamus relief, claiming that a final environmental impact statement (EIS) submitted in connection with the proposed construction of a 47.6 mile segment of Interstate Highway 380 (1-380) between Cedar Rapids and Waterloo, Iowa, does not meet and therefore violates the requirements of the National Environmental Policy Act (NEPA), 42 U.S.C. § 4321 et seq. By agreement of the parties and order of the court the matter was submitted for decision upon the cross-motions, stipulations of facts, and a briefing schedule. All affidavits, exhibits, briefs and other documents having been submitted, the case is ready for decision. No genuine issue of material fact exists; the sole issue for decision being the legal adequacy of the EIS in light of NEPA. The underlying factual history follows.

*603 Facts

This case has its ultimate beginnings in 1956 when the Iowa State Highway Commission — now the Iowa Department of Transportation (IDOT) 1 — began efforts to obtain approval of additional interstate highway mileage, under the 1956 Federal-Aid Highway Act. 2 In 1968, the United States Congress increased the limit of total mileage for the national interstate highway system to 42,500 miles. As a result of the increased limit of mileage for the national interstate system, the State of Iowa received approval for an additional 71 miles of interstate highway to be constructed in Iowa. A portion of this approved additional mileage was to commence at 1-80 near Iowa City, pass through Cedar Rapids and proceed to the intersection of U. S. Highways 218 and 520 in Waterloo. 3 The segment of interstate highway at issue in this case forms a part of this portion and constitutes a 47.6 mile connection between Blairs Ferry Road in Cedar Rapids with U. S. Highways 218 and 520 in Waterloo.

The United States Secretary of Transportation, through the Federal Highway Administration (FHWA), has the responsibility for approval of state highway departments’ requests for routes on the interstate highway system, 23 U.S.C. § 103(e), and for approval of plans and specifications for each proposed interstate highway project, 23 U.S.C. § 109(b). The proposed segment of 1-380 at issue here is eligible for 90% federal funding as part of the national interstate highway system. Federal funding approval for highway projects, however, requires three stages of consideration. The first stage is submission of the location of the proposed highway corridor, which is considered in a corridor approval hearing held by the State. The second stage is consideration of the design of the proposed highway, which is the subject of a design hearing. The final stage is the submission of the project by the state to the FHWA for “projects, specifications and estimates” approval.

On March 17, 1971, the FHWA approved the draft EIS for the 47.6 mile segment of 1-380 at issue here. 4 Informational hear *604 ings concerning the 1-380 project were held in Vinton on November 29,1971; in Waterloo on November 30, 1971; in Independence on December 1, 1971; and in Cedar Rapids on December 2, 1971.

Corridor hearings for this proposed segment were held in Cedar Rapids and Waterloo on May 24, 1972, and May 25, 1972, respectively. On December 20, 1972, the IDOT voted to build this segment along the “Raymond” alternate as described in the EIS. 5 The final EIS for this segment (Plaintiffs’ Exhibit 3 and Defendants’ Exhibit 2) was issued in March, 1975 and approved by the FHWA on June 17, 1975. The FHWA gave corridor approval on June 22, 1975.

Design hearings for this proposed segment were held on January 12 and May 10, 1978, in Center Point; March 30, 1978, in Urbana; on May 11, 1978, in LaPorte City; and on June 29, 1978, in Gilbertville. The FHWA gave design approval for most of this segment during the period from June through September, 1978.

As of February, 1979, defendants had acquired at least 70 parcels of land in the right of way for this segment of 1-380, 6 and were preparing appraisals for many more. They intend to have completed appraisals for 284 parcels by April, 1979 and to purchase properties within 90 days of the completion of each appraisal. Defendants do not plan to begin grading or other construction activities on the majority of the right of way for this segment until April, 1980. This segment of 1-380 is planned to be open to traffic in the fall of 1981.

Since plaintiffs’ contentions also raise issues concerning the adequacy of the EIS with respect to the possible relationship between the proposed 1-380 segment at issue here with Arterial Highway 518, the factual record relating to such issues is stated at this juncture.

In Iowa, the state’s “Freeway” system, which was subsequently renamed the “Arterial Highway” system, is intended to supplement the national interstate highway system. 7 Somewhat contemporaneously with its efforts to obtain approval of additional interstate mileage to be constructed in Iowa, the IDOT adopted in 1965 as part of its proposed Arterial Highway (Freeway) system a plan to construct Arterial Highway 518 as a four-lane divided road, similar in part to interstate highway standards, through east central Iowa on a north-south axis beginning at Keokuk (passing through or near Iowa City, Cedar Rapids, and, Waterloo) and extending to 1-35 near Garner.

Construction of a portion of this Arterial Highway 518, to run south from 1-80 near Iowa City to the vicinity of state highway *605 92 in Washington County, 8 is expected to begin in the summer of 1979. Arterial Highway 518 from 1-80 south to state highway 22 will be a four-lane divided highway with access control. South of highway 22 to its junction with state highway 92, it will be a two-lane highway without full access control.

The IDOT has no specific plans for any further improvement of Arterial Highway 518 south of state highway 92 in Washington County at this time except for a five-mile segment (proceeding north of Keokuk to U. S. Highway 61), which will be a four-lane divided highway but without access control.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
491 F. Supp. 601, 11 Envtl. L. Rep. (Envtl. Law Inst.) 20, 1979 U.S. Dist. LEXIS 11617, Counsel Stack Legal Research, https://law.counselstack.com/opinion/farmland-preservation-assn-v-adams-iand-1979.