Far Tower Sites, LLC v. Knox County

126 S.W.3d 52, 2003 Tenn. App. LEXIS 583
CourtCourt of Appeals of Tennessee
DecidedAugust 20, 2003
StatusPublished
Cited by12 cases

This text of 126 S.W.3d 52 (Far Tower Sites, LLC v. Knox County) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Far Tower Sites, LLC v. Knox County, 126 S.W.3d 52, 2003 Tenn. App. LEXIS 583 (Tenn. Ct. App. 2003).

Opinion

OPINION

Dial Call, Inc. (“Dial Call”) entered into a sublease with Far Tower Sites, LLC (“Far Tower”), by the terms of which Dial Call sublet to Far Tower a 100 foot by 100 foot hilltop parcel of property in Knox County so Far Tower could construct a cellular telecommunications tower. Dial Call had previously obtained — and periodically renewed — a building permit from Knox County for the same purpose. After the sublease was executed, Far Tower secured a new building permit in its own name and was assured by the Knox County employee responsible for the issuance of such permits that Far Tower was “good to go, go build it.” After expending monies and doing both on-site and off-site work in connection with the proposed tower, Far Tower ceased its construction efforts when Knox County issued a stop work order. The order was predicated upon Far Tower’s failure to obtain a Certificate of Appropriateness (“COA”) — a legal prerequisite to the issuance of a building permit— from the Tennessee Technology Corridor Development Authority (“the Authority”) under a private act of the General Assembly named the Tennessee Technology Corridor Development Authority Act (“the Tech Act”). Far Tower’s subsequent efforts to obtain a COA were ultimately unsuccessful and, as a consequence, it abandoned the project. Proceeding under a number of theories, Far Tower sued Knox County and the Authority for damages based upon an alleged taking of its property. Following a bench trial, the court below dismissed Far Tower’s complaint and entered judgment in favor of the County and the Authority. Far Tower appeals, urging us to (1) reverse the trial court, (2) award it damages of $173,965.50 plus interest from the date of “taking,” and (3) remand for a hearing on Far Tower’s claim for attorney’s fees. We affirm the trial court’s judgment.

I. Facts

There does not appear to be a sharp dispute between the two sides as to the facts underlying this litigation. This being the case, our recitation of those facts will borrow liberally from the statement of facts found in Far Tower’s brief. 2 In or *54 der to put the issues before us in proper context, we have elected to extensively recite those facts.

On May 10, 1995, Dial Call leased a parcel of real property located near Carmichael Road in Knox County (“the Tower Site”) from James C. Gammon for the purpose of constructing a cellular telecommunications tower (“the Tower”)-. The Tower Site, being 100 feet by 100 feet, was a wooded area at the top of a hill. The site was zoned “agricultural” and the erection of a cellular tower on the Tower Site as planned by Dial Call was expressly permitted by the Knox County Zoning Ordinance.

The rent specified in the lease between Gammon and Dial Call was $500 per month for the initial five-year term. The lease recited Dial Call’s option to renew its lease for four additional five-year periods, with the rent for the option terms being increased by specified percentages. Because a tower site involves a substantial investment, it was Dial Call’s expectation that it would exercise all of the four options to renew.

Dial Call applied to the Knox County Codes Office for the issuance of a permit (“the original Permit”) for the construction of a cellular tower on the Tower Site. On June 23, 1995, the original Permit was issued. No representative of the Knox County Codes Office ever advised a representative of Dial Call that, prior to the issuance of a permit, Dial Call first had to obtain a COA from the Authority. Dial Call did not otherwise know that a COA was a prerequisite to the issuance of a permit.

The Authority is a public, governmental body acting as an agency and instrumentality of Knox County. It was created by the “Tennessee Technology Development Authority Act,” Chapter 148, Private Acts of 1983. The Tech Act applies to a large area of property located in West Knox County, known as the Tennessee Technology Corridor (“the Corridor”).

Within six months of the issuance of the original Permit, Dial Call built an access road across Mr. Gammon’s property from Carmichael Road to the tree line where the Tower Site was located and did erosion control work. Some work occurred at the Tower Site at least every six months. Dial Call never allowed the original Permit to expire, renewing it from time to time at the office that had initially issued it. Whenever the original Permit was renewed, Dial Call dealt with Mr. Bill Pierce in the Knox County Codes Office. Mr. Pierce never advised Dial Call that it had to obtain a COA from the Authority in order to renew the original Permit.

On March 31, 1997, Dial Call and Far Tower entered into the sublease agreement, whereby Dial Call subleased the Tower Site to Far Tower. The length of the sublease and the options to renew contained therein were identical to those specified in the original lease between Mr. Gammon and Dial Call.

Under the terms of the Dial Call/Gammon lease, the consent of Mr. Gammon to a sublease was required. As a condition for granting his consent, Mr. Gammon insisted upon, and Dial Call agreed to, a modification of the original lease so as to provide for a new rental amount of $1,000 per month, subject to specified increases for each of the option terms.

The consideration for the sublease was Far Tower’s agreement to construct a tower, at its sole cost, no later than January 1, 1998, on which Dial Call would be permitted to install, at no cost, its wireless communications equipment. Far Tower would not be required to pay rent to Dial Call; the latter would continue, however, to pay the ground rent to Mr. Gammon on the *55 original lease. The sublease further provided that, in the event the Tower was not substantially completed by January 1, 1998, Far Tower would be deemed to be in default, in which event, Dial Call could terminate the sublease and receive the sum of $5,000 from Far Tower as damages.

As previously indicated, the initial term of the sublease was five years, with four options to renew, each for five years. It was Far Tower’s expectation that each of the options would be exercised because of the company’s significant investment in the Tower and because it was confident of its ability to attract customers to locate on the Tower, thereby allowing it to reap substantial income.

In entering into the sublease agreement with Dial Call, Far Tower relied upon the fact that the original Permit had been issued. It would not have entered into the sublease had it known that there was a problem with the original Permit.

In 1997, Mr. Pierce was a Plans Examiner in the Administration Department of the Knox County Codes Office. His responsibilities included the reviewing of plans for various structures, including cellular towers. Mr. Pierce testified that he would review the plans and other documents submitted to Knox County in order to determine if the documents reflected compliance with the applicable regulations, including the Knox County Zoning Ordinance. If his review showed that the submitted plans were in compliance, he would issue a permit.

Mr. Pierce’s immediate supervisor in 1997 was Roy Braden, Supervisor of Codes Administration. Mr. Braden’s immediate supervisor was Bruce Wuethrich, who was, at that time, according to Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
126 S.W.3d 52, 2003 Tenn. App. LEXIS 583, Counsel Stack Legal Research, https://law.counselstack.com/opinion/far-tower-sites-llc-v-knox-county-tennctapp-2003.