Falls Sand and Gravel Co. v. Western Concrete, Inc.

270 F. Supp. 495, 1967 U.S. Dist. LEXIS 8989
CourtDistrict Court, D. Montana
DecidedJune 6, 1967
DocketCiv. 2433
StatusPublished
Cited by32 cases

This text of 270 F. Supp. 495 (Falls Sand and Gravel Co. v. Western Concrete, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Montana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Falls Sand and Gravel Co. v. Western Concrete, Inc., 270 F. Supp. 495, 1967 U.S. Dist. LEXIS 8989 (D. Mont. 1967).

Opinion

ORDER AND MEMORANDUM OPINION

JAMESON, Chief Judge.

Plaintiff seeks damages from the joint venture of George A. Fuller Company and Del E. Webb Corporation (Fuller-Webb), which contracted with the United States to construct missile facilities, and Western Concrete, Inc., which furnished concrete for the project pursuant to an agreement with Fuller-Webb. Plaintiff supplied Western Concrete with sand, aggregate and other materials.

*498 This action was commenced in state court on September 9,1963, and removed to this court by reason of diversity of citizenship. Plaintiff filed its amended complaint on September 2, 1966. On September 7, 1966, defendants filed their joint motion for summary judgment pursuant to Rule 56, F.R.Civ.P., requesting that plaintiff’s amended complaint be dismissed, or in the alternative, that each of the four counts be dismissed against the applicable defendant. 1 The last brief was filed May 5,1967.

The first count of the amended complaint alleges that Fuller-Webb entered into its contract with the United States on February 28, 1961, that Western contracted with Fuller-Webb to furnish the concrete on April 14, 1961, and that Falls contracted with Western to supply sand and aggregate on or about May 1, 1961. Prior to entering into its contract with Western, Falls negotiated with Fuller-Webb and Western with regard to the aggregates to be supplied for the project, and in this connection, on March 29,1961, Fuller-Webb furnished Falls with a production schedule and amounts of various types of concrete to be used in the project.

According to the amended complaint, from these amounts and schedule, the volume of aggregates needed could be ascertained and the times when aggregates would have to be available could be determined. Relying upon these amounts and production schedule, plaintiff computed its production costs for sand and aggregates, and determined the unit prices at which it would sell its products to Western. Falls thereafter contracted to sell Western “all of the aggregates Western may need in furnishing all of the concrete” and agreed that “the ‘aggregates’ to be furnished hereunder by Falls shall be available to Western on a twenty-four hour a day, seven days a week basis.”

It is further alleged that Fuller-Webb, in furnishing the production schedule and amounts negligently represented to plaintiff that they were accurate, which subsequently proved to be untrue, and that Fuller-Webb and Western failed to follow the projected schedule and amounts. The deviation from the schedule and from any uniform demand resulted in plaintiff’s spasmodic operations and attendant increased costs, all of which damaged plaintiff in the amount of $102,785.59.

The second count repleads the preliminary allegations of the first count and alleges that on March 29, 1961, in addition to the production schedule and amounts, Fuller-Webb furnished plaintiff with a “mix design” which showed the percentage of sand needed in the total aggregate. Relying upon the schedule and mix design, Falls computed its unit price for concrete sand at $1.20 per ton. Fuller-Webb negligently represented that the mix design was accurate, but in fact did not follow it both as to the total amount of concrete sand demanded and as to the percentage of concrete sand per cubic yard of concrete. The resulting demand for excess sand damaged . plaintiff in the amount of $63,644.91.

Count three alleges that the agreement between Falls and Western provides that, “In the event that at any time it becomes necessary to heat the aggregates, a price adjustment will be negotiated between the parties to reflect the reasonable cost of such heating.” Negotiations were conducted with Fuller-Webb and Western under this clause, and the defendants represented to Falls that the aggregates would have to be heated or dried so that their moisture content would not exceed two percent. Relying upon this figure, plaintiff computed its charges for heating or drying and negotiated a price adjustment with Western at a certain price per ton. However, Fuller-Webb and Western thereafter required that the ag *499 gregates be heated or dried so that the moisture content would be no more than one-half of one percent. Since Western would not accept aggregates with greater moisture content than .5%, Falls incurred extra expense in further drying them to its damage of $37,122:15.

Count four substantially realleges the first count with regard to the production schedule, amounts, and plaintiff’s reliance thereon, but specifically alleges that the quantity of Intrusion Prepakt required by defendants did not correspond to the amount calculated using the schedule and amounts furnished by Fuller-Webb. As a result, plaintiff was required to produce in excess of its projected demand which damaged plaintiff in the amount of $7,838.92.

Following the prayer of the amended complaint it is stated that, “If Plaintiff recovers under the First Count, its claim under the Second Count would be reduced by 27.8(§ per ton and its claim in the Third Count would be reduced by 10^ per ton. The Fourth Count is an alternative to the First Count.”

As noted supra (note 1), the court also has under consideration an action instituted by plaintiff against Fuller-Webb and its sureties under the Miller Act. Counsel have stipulated that the court may consider in this case statements submitted by plaintiff to Western between June 15, 1961, and August 30, 1962, covering materials supplied by plaintiff during that period. None of these statements make any reference to the claims asserted in this action. 2

Defendants have moved for summary judgment on the grounds of (1) election of remedies, (2) waiver of the misrepresentation by affirmance of the contract, and (3) the statute of limitations.

Summary judgment of course is proper only where there is no genuine issue of fact or where viewing the evidence and the inferences which may be drawn therefrom in the light most favorable to the adverse party, the movant is clearly entitled to prevail as a matter of law. All doubts as to the existence of a genuine issue as to any material fact must be resolved against the moving party. An issue of fact may arise from countering inferences which are permissible from evidence accepted as true. The court may not weigh evidence or resolve issues in determining a motion for summary judgment. 3

On the other hand, Rule 56(e), F.R.Civ.P., as amended in 1963, provides that in opposition to a motion for summary judgment an adverse party “may not rest upon the mere allegations or denials of his pleading” but must by affidavit or otherwise “set forth specific facts showing that there is a genuine issue for trial.” 4

With these guiding principles in mind, we turn to a consideration of defendants’ motion. The first, second and fourth counts of plaintiff’s amended complaint are interrelated and relate primarily to the actions of Fuller-Webb which allegedly resulted in damages to plaintiff and are based upon the theory of negligent misrepresentation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morrow v. Bank of America, N.A.
2014 MT 117 (Montana Supreme Court, 2014)
Corporate Air v. Edwards Jet Center
2008 MT 283 (Montana Supreme Court, 2008)
Williams v. DeVinney
856 P.2d 546 (Montana Supreme Court, 1993)
Shupak v. New York Life Insurance
780 F. Supp. 1328 (D. Montana, 1991)
Bottrell v. American Bank
773 P.2d 694 (Montana Supreme Court, 1989)
Bushnell v. Cook
718 P.2d 665 (Montana Supreme Court, 1986)
McGregor v. Mommer
714 P.2d 536 (Montana Supreme Court, 1986)
White v. Lobdell
678 P.2d 637 (Montana Supreme Court, 1984)
Gregory v. City of Forsyth
609 P.2d 248 (Montana Supreme Court, 1980)
Hill v. Squibb & Sons, ER
592 P.2d 1383 (Montana Supreme Court, 1979)
Harrington v. Holiday Rambler Corp.
575 P.2d 578 (Montana Supreme Court, 1978)
Anderson v. Applebury
567 P.2d 951 (Montana Supreme Court, 1977)
State Ex Rel. Dimler v. Dist. Ct., Eleventh JD
550 P.2d 917 (Montana Supreme Court, 1976)
Gaston v. Hartzell
549 P.2d 632 (New Mexico Court of Appeals, 1976)
Betancourt v. Wilson
409 F. Supp. 598 (D. Puerto Rico, 1975)
Stray Calf v. Scott Land & Livestock Co.
391 F. Supp. 433 (D. Montana, 1975)
Arizona Title Insurance & Trust Co. v. O'Malley Lumber Co.
484 P.2d 639 (Court of Appeals of Arizona, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
270 F. Supp. 495, 1967 U.S. Dist. LEXIS 8989, Counsel Stack Legal Research, https://law.counselstack.com/opinion/falls-sand-and-gravel-co-v-western-concrete-inc-mtd-1967.