Puetz v. Carlson

364 P.2d 742, 139 Mont. 373, 1961 Mont. LEXIS 58
CourtMontana Supreme Court
DecidedSeptember 13, 1961
Docket10104
StatusPublished
Cited by9 cases

This text of 364 P.2d 742 (Puetz v. Carlson) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Puetz v. Carlson, 364 P.2d 742, 139 Mont. 373, 1961 Mont. LEXIS 58 (Mo. 1961).

Opinion

MR. JUSTICE CASTLES

delivered the Opinion of the Court.

Plaintiffs as co-partners brought this action against defendants to recover for work and labor alleged to have been performed and for materials alleged to have been furnished and delivered to defendants. Verdict and judgment were in favor of plaintiffs. Defendants’ motion for a new trial was denied and they have appealed from the judgment and have attempted to appeal from the order denying a new trial though appeals from such orders have been abolished. Section 93-8017.

The complaint alleges that defendants became indebted to plaintiffs for such labor and materials which were alleged to have been performed and furnished “upon the special instance and request of the defendants” in the amounts specified in the complaint aggregating $4,408.21.

The complaint alleges payments upon the account aggregating $812 leaving $3,596.21 due and unpaid.

A general demurrer was overruled and defendants filed an answer. The defendants denied any indebtedness upon an *375 open account and alleged that an agreement was made between the parties whereby plaintiffs were to build a trailer court for defendants for the lump sum of $6,309 and that the obligations of the parties were governed by that contract and not by an open account. They admitted the payments alleged in the complaint but deny that they were applied on the account as alleged but pursuant to their agreement.

The other material allegations of the complaint were denied. By way of affirmative defense defendants alleged that they were the owners of certain described real estate near Billings and that they had agreed to build and construct upon the property a trailer village and to operate thereon a trailer court. It is further alleged that the plaintiffs were doing business as the Billings Blacktop Company and contacted the defendants for the purpose of submitting a bid; that they did submit a bid dated the 23rd day of March, 1956, and that the bid was accepted by the defendants. It was further alleged that the work as set forth in the bid could be completed within ten days to two weeks after actual construction had commenced. Finally, it was alleged that plaintiffs commenced the construction of the trailer court but failed, refused and neglected to complete the contract according to its terms and are not entitled to recover.

The answer also contained a counter-claim. It made the same allegations as set forth in the affirmative defense and then alleged that as the result of the failure of the plaintiffs to complete the contract the defendants were obligated to complete the construction of the trailer village by employing the Midland Materials Company to complete the work for a total sum of $6,100, and in this respect claimed damages for failure of the plaintiffs to complete the contract according to its terms which should be set off against any claim asserted by the plaintiffs.

The answer also contained a cross complaint. It made the same allegations as set forth in the affirmative defense and *376 further alleged that three months was a reasonable time within which to complete such work, and that they were advised and informed such work could be completed within such time; that plaintiffs knew such premises were to be used as a trailer village, and that by reason of the fact such work ivas not completed they sustained a loss of business in the sum of $6,250, and in addition sustained a loss in depreciation of the premises by reason of the faulty Avorkmanship of the plaintiffs. The reply denied generally the allegations contained in the pleadings of the defendants.

The evidence discloses that defendants were the owners of about three acres of Jand near the City of Billings; that they Avere interested in constructing a trailer park; that plaintiffs contacted defendants AAdth the idea of installing asphalt paving on the contemplated park; that the park was to contain two semi-circular driveways from Avhieh trailer lots Avere to be constructed at an angle on both the outside and inside of the circumference on Avhieh house trailers or mobile homes could be placed; that each trailer lot Avas to be provided with necessary utilities; that the driving area Avas to be constructed of hard surfacing blacktop placed on a gravel cushion rolled with a three to five ton roller similar to road and highway construction generally; that grass was to be planted between the lots; that along the sides of the driveway two by four’s were to be placed to form straight edges to serve as a divider between the blacktopped area and the portion planted to grass; and that after the sewer, water and electric lines were in place defendants requested a written bid on the blacktop. Plaintiffs submitted a bid. One of the defendants objected to the form of the bid and a second bid was thereupon made.

The only conversation regarding payment Avas one in which defendant Mrs. Carlson informed plaintiffs that the Avork would be paid for when completed. Before commencing the work plaintiff Brittain informed Mrs. Carlson that plaintiffs would not commence the work unless the defendants paid estimates *377 for the work as the same was being completed. Defendants agreed to do this and thereafter made three payments for portions of the work as it was completed. The work of blacktopping was started in July 1956. Prior to that plaintiffs did some grade work with a caterpillar and scoop. During that summer defendants were filling in the top soil in the area wherein grass was to be planted. In order to keep the two by four’s in place and to counteract the weight of the gravel on one side of the two by four’s, it was necessary that the top soil be placed to the top of the two by four’s. Only a part of the ground had been thus prepared for the blacktop; that part was completed in September 1956. There was evidence that defendants advised plaintiffs that they desired no further work to be performed that year. There ivas a conflict in the evidence on this point but the conflict was resolved in plaintiff’s favor by the jury after the issue was submitted to it under instruction numbered 9.

When plaintiffs offered in evidence their bid which specified the amount of work to be done, defendants objected on the ground that it constituted a variance from the allegations of the complaint. The objection was overruled. Several of the specifications of error are predicated upon that contention.

The main issue presented by this appeal is whether there was a fatal variance when the complaint was based upon the theory of quantum meruit and an express contract was proven at the trial. This involves the consideration of two separate but interrelated questions. First: Will an action in assumpsit lie in this case? Under familiar rules of substantive law, when an action is brought in assumpsit recovery is upon an implied promise, not upon the express contract. Second: Even assuming that an action in assumpsit will lie, was the failure to allege the express contract a material variance; i. e.; one which misled the defendant to his prejudice, within the meaning of section 93-3901, R.C.M.1947? Both of these questions will be handled together in the following discussion.

*378 Defendants rely upon the case of Johns v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Keneally v. Orgain
606 P.2d 127 (Montana Supreme Court, 1980)
Baldwin v. Stuber
597 P.2d 1135 (Montana Supreme Court, 1979)
State Ex Rel. State Highway Commission v. Cooper
521 P.2d 190 (Montana Supreme Court, 1974)
DeFord v. Wansink
452 P.2d 73 (Montana Supreme Court, 1969)
Falls Sand and Gravel Co. v. Western Concrete, Inc.
270 F. Supp. 495 (D. Montana, 1967)
Clark v. Rex Worrall & Canyon Hotels, Inc.
406 P.2d 822 (Montana Supreme Court, 1965)
Bennett Leasing Company v. Ellison
387 P.2d 246 (Utah Supreme Court, 1963)
Fraser v. Williams
367 P.2d 769 (Montana Supreme Court, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
364 P.2d 742, 139 Mont. 373, 1961 Mont. LEXIS 58, Counsel Stack Legal Research, https://law.counselstack.com/opinion/puetz-v-carlson-mont-1961.