Fagerholm v. Nielson

106 A. 333, 93 Conn. 380, 1919 Conn. LEXIS 27
CourtSupreme Court of Connecticut
DecidedApril 16, 1919
StatusPublished
Cited by15 cases

This text of 106 A. 333 (Fagerholm v. Nielson) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fagerholm v. Nielson, 106 A. 333, 93 Conn. 380, 1919 Conn. LEXIS 27 (Colo. 1919).

Opinion

Gager, J.

The first two reasons of appeal are based on the refusal of the court to charge as requested by the defendant. The action is for a balance due upon a building contract, and for extras, and the plaintiff’s right to recover upon the contract depends *385 upon substantial performance, and the right upon the extras depends upon whether they were ordered.

The first of the defendant’s requests relates merely to the essentials of a discharge of the contract by agreement, and treats of termination by agreement and substitution of a new contract. The record does not raise any such questions and there was no error in not charging as requested. But this request to charge also incorporates a reference to performance: “The jury must find for the defendant, in case said defendant proves that plaintiff failed to perform said contract according to its terms, unless such failure was caused by any of the three discharges enumerated above,” referring to discharge by agreement, by impossibility of performance, and by breach. This, standing by itself, is not an accurate statement with reference to building contracts. The necessities of such cases have led to a modification of the statement, to prevent injustice, as set out in Pinches v. Swedish Evangelical Lutheran Church, 55 Conn. 183, 187, 10 Atl. 264.

The second request to charge relates to impossibility of performance, and to a recovery on quantum meruit. As to the first of these points, the record does not show that impossibility of performance was claimed. The contract did not provide for its completion at any definite time, hence it was to be completed in a reasonable time; and the real question was as to the defendant’s imperative directions to the plaintiff to proceed before the walls were fit to be papered, and the woodwork varnished, on his definite promise to pay for work that might have to be done over in consequence. No claim of the plaintiff is based on impossibility of complying with the terms of the contract. The claim was, that owing to the condition of the walls compliance with the hurry-up-order of the defendant necessarily resulted in the peeling off of some paper and the con *386 sequent repapering. As to quantum, meruit, the entire request is based upon the theory that the plaintiff’s action is upon the technical quantum meruit, and quite overlooks the real meaning of the Pinches case, which recognizes the action as still on the contract, though deductions may be made from the contract price when there has not been entire conformity with the contract, provided the deviation was not wilful. Daly & Sons v. New Haven Hotel Co., 91 Conn. 280, 99 Atl. 853; Jones & Hotchkiss Co. v. Davenport, 74 Conn. 418, 420, 50 Atl. 1028; Chariott v. McMullen, 84 Conn. 702, 81 Atl. 65. The contract is the basis of recovery. The request is too long to be quoted. It is sufficient to say that it is involved, argumentative upon the law, and contains no clear definite request adapted to the case under the pleadings and claims of the parties. There was no error on the second request to charge. The real difference between the parties was in reference to the falling of paper from the walls after it was put on, and upon this the court correctly charged: “Now, if you find that the plaintiff faithfully performed his work, and that this paper came off not through his fault, but through the fault of the defendant Nielson by not having the Avails properly dried, either by himself or his agents, and by directing the work of the paper hanger and the decorator to go on when the walls were not in condition to receive the work, and that, OAving to the acts of the defendant Nielson in not having the walls dried, and permitting the frost to get into the walls; and if you find, further, that the paper came off by reason of that, then, as a matter of law, gentlemen, you cannot charge the plaintiff with that fault of the defendant.”

In Anew of our conclusions above stated, the reason of appeal (3) which alleges that the court did not charge “in every particular as requested by the de *387 fendant,” needs no consideration further than to say that the court is never bound to charge “in every particular” as a party may request. If the charge is proper and adequate, the whole duty of the court is performed. Crotty v. Danbury, 79 Conn. 379, 385, 65 Atl. 147; Radwick v. Goldstein, 90 Conn. 701, 706, 98 Atl. 583. Error in a refusal to charge occurs only when the request is pertinent and correct and the court has not fairly covered the particular point raised; but the court may always choose its own form of expression.

Another reason of appeal (4) predicates error in the entire charge in failing to state the law explicitly and in leaving the principles of law undefined, and not sufficiently explicit. No specific error is pointed out. This is a sort of blanket objection which this court will not consider. Harper Machinery Co. v. Ryan-Unmack Co., 85 Conn. 359, 363, 82 Atl. 1027. It is claimed for error (5) that the charge was argumentative against the defendant because the principles of law favoring the plaintiff were unduly emphasized, and those favoring the defendant were minimized. Here, as in the fourth reason of appeal, the defendant has neglected to specify what language is over-emphatic, and in what respects the law is minimized. There is no sufficient allegation of error for this court to consider.

The defendant also appeals from the denial of a motion to set aside the verdict as against the weight of evidence and as unsupported thereby. An examination of the record shows very clearly that there was evidence before the jury on which they might fairly come to the conclusion they did. The rule in this respect has been so often and so consistently stated by the court that it should be elementary law for those who undertake the trial of cases. We only refer to *388 two of the later cases. Robinson v. Backes, 91 Conn. 457, 99 Atl. 1057; Bergh v. Spivakowski, 86 Conn. 98, 84 Atl. 329.

The ninth and tenth reasons of appeal are that the court erred in holding and charging that under the pleadings the plaintiff could offer evidence as to the frozen condition of the walls, and the orders of the defendant with, reference thereto, as stated above. The pleadings, omitting the third defense of payment as to which no question is made, are, in substance, performance of the contract by the plaintiff, and denial of performance by the defendant. The pleadings themselves make no mention of frozen walls or defective work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Automobile Insurance v. Model Family Laundries, Inc.
52 A.2d 137 (Supreme Court of Connecticut, 1947)
Quackenbush v. Vallario
159 A. 893 (Supreme Court of Connecticut, 1932)
Sizer v. City of Waterbury
154 A. 639 (Supreme Court of Connecticut, 1931)
Kelley v. Hance
142 A. 683 (Supreme Court of Connecticut, 1928)
Draus v. International Silver Co.
135 A. 437 (Supreme Court of Connecticut, 1926)
Beitler v. Rudkin
133 A. 214 (Supreme Court of Connecticut, 1926)
Pollak v. Danbury Manufacturing Co.
131 A. 426 (Supreme Court of Connecticut, 1925)
Bridgeport Hydraulic Co. v. City of Bridgeport
130 A. 164 (Supreme Court of Connecticut, 1925)
Barlow Brothers v. Lunny
128 A. 115 (Supreme Court of Connecticut, 1925)
State v. O'Brien
126 A. 690 (Supreme Court of Connecticut, 1924)
Lukosevicia v. Bartow
122 A. 709 (Supreme Court of Connecticut, 1923)
Salemme v. Mulloy
121 A. 870 (Supreme Court of Connecticut, 1923)
Hine v. McNerney
116 A. 610 (Supreme Court of Connecticut, 1922)
Riley v. O'Connell
116 A. 89 (Supreme Court of Connecticut, 1922)
Young v. Shetucket Coal & Wood Co.
115 A. 672 (Supreme Court of Connecticut, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
106 A. 333, 93 Conn. 380, 1919 Conn. LEXIS 27, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fagerholm-v-nielson-conn-1919.