F. Zacherl, Inc. v. Flaherty Mechanical Contractors, LLC

131 A.3d 1030, 2016 Pa. Commw. LEXIS 22, 2016 WL 56242
CourtCommonwealth Court of Pennsylvania
DecidedJanuary 6, 2016
Docket1196 C.D. 2014
StatusPublished
Cited by3 cases

This text of 131 A.3d 1030 (F. Zacherl, Inc. v. Flaherty Mechanical Contractors, LLC) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
F. Zacherl, Inc. v. Flaherty Mechanical Contractors, LLC, 131 A.3d 1030, 2016 Pa. Commw. LEXIS 22, 2016 WL 56242 (Pa. Ct. App. 2016).

Opinions

OPINION BY

Judge BROBSON.

Appellant West Allegheny School District (the District) appeals from an order of the Court of Common Pleas of Allegheny County (trial court), dated June 26, 2014, granting Appellee F. Zacherl, Inc.’s (Zacherl) motion to mold the verdict to add interest, a penalty, and attorney’s fees, and denying the District’s motion for post-trial relief. For the reasons discussed below, we affirm in part, and vacate in part, and remand the matter to the trial court for it to determine whether Zacherl is entitled to attorney’s fees.

At issue in this matter are claims for payment, a penalty, and attorney’s fees by Zacherl, arising from a construction contract for additions and alterations to West Allegheny High School (the Project). International Fidelity Insurance Company (the Surety) issued both payment and performance bonds for the Project. The District selected Flaherty Mechanical Contractors, LLC (Flaherty) as a prime contractor for the Project, pursuant-to the Separations Act, Act of May 1, 1913, P.L. 155, as amended, 53 P.S. § 1003. The prime contract between the District and Flaherty provided that Flaherty would be responsible for the installation of heating, ventilation, and air conditioning equipment. Flaherty subcontracted the necessary sheet metal work to Zacherl. Pursuant to its contract with the District, Flaherty was responsible for payments to any subcontractors it engaged for portions of its prime contract, including payments to Zacherl. The Surety’s payment bond ensured that payments made by the District to Flaherty reached contractors as required by Section 756 of the Public School Code of 1949 (Public School [1033]*1033Code), Act of March 10, 1949, P.L. 30, 24 P.S. § 7-756.2

Throughout the course of the work on the Project, the District made various timely payments to Flaherty for work performed, but Flaherty failed to make timely payments to its subcontractors, including Zacherl. On several occasions, Zacherl and other subcontractors requested that the District assist them in getting payments from Flaherty, which the District successfully did. In August 2009, Zacherl again sought assistance from the District regarding non-payment by Flaherty, but this time the District was not able to resolve the non-payment matter. Zacherl issued a notice of claim to the Surety and a notice of possible work stoppage to Flaherty. The District, aware that the payment problems were not being corrected, notified Flaherty that payment applications would not be processed without proof of payment to the subcontractors. Ultimately, as- a result of the non-payment issues and Flaherty’s inability to complete satisfactorily the contracted work, the District terminated Flaherty’s prime contract on October 26, 2009. The next day, Flaherty terminated its contract with Zacherl.

Following the termination of the contracts, the parties notified the Surety and sought enforcement of the payment and performance bonds. The Surety issued a “stop payment” order to the District, demanding that no further funds be released under the Flaherty contract without the written consent and direction of the Surety. Shortly thereafter, the Surety notified the District that the District had a duty to mitigate damages. In order to allow work to continue, the Surety stated that it would review expeditiously any requests for funds.

In order not to delay further completion of the Project with the search for a re-plaeément sheet metal contractor, the District requested that Zacherl return to the Project to complete the sheet metal work that it originally agreed to perform under its subcontract with Flaherty. In response, Zacherl sent a letter, dated November 16, 2009, setting forth the subcontract amount, amount billed to date, amount paid to date, amount due as of that date, amount remaining to bill, and the total unpaid amount. According to that letter, Zacherl calculated that it was owed $288,458.82, for work performed under its contract with Flaherty. By way of a verbal agreement, Zacherl agreed to complete the work on the Project, provided that the District paid it $147,591.90, which represented an amount equal to Za-cherl’s outstanding June and July invoices. On November 17, 2009, the District issued payment to Zacherl in the, amount of $147,591.90. Despite the fact that Zacherl completed the work on the Project, the District made no further payments to Za-cherl. '

Zacherl filed a civil action in the trial court against Flaherty,3 the District, and the Surety, asserting breach of contract counts against' Flaherty and the District, unjust enrichment counts against Flaherty and the District, counts of anticipatory breach of contract against Flaherty, the District, and the Surety, and a count for breach of payment bond against Flaherty [1034]*1034and the Surety, Zacherl sought damages in the amount of $116,263.35 • for work it performed under its contract with Flaherty; $59,842.22 for additional work performed after October 26, 2009, pursuant to the verbal agreement between Zacherl and the District, for which it invoiced the District and did not receive payment; and $53,404.27 for work performed on the Project after October 26, 2009, but for which it had not yet billed the District. Zacherl also sought interest, costs, a penalty, and attorney’s fees.

The partiés submitted motions for summary judgment, and the trial court granted summary judgment in favor of Zacherl. The trial court ordered the Surety to pay Zacherl ' $116,263.35 for the work performed under Zacheri’s contract with Flaherty. The trial court ordered the District to pay Zacherl $113,246.39 for all work that Zacherl performed on the Project subsequent to the District’s termination of the'prime contract with Flaherty. The trial court also scheduled a hearing to address Zacherl’s claim for a penalty, attorney’s fees, and interest.

Following the hearing, the trial court concluded that the District acted in bad faith, and the trial court awarded Zacherl an additional $41,130.31 in attorney’s fees and interest, pursuant to what is commonly referred to as the Prompt Pay Act, 62 Pa.C.S. §§ 3931-3939. The District filed a notice of appeal.4

On appeal to this Court, we reversed the trial court’s order-to the extent that it granted summary judgment in favor of Zacherl and against the District and remanded the’'matter to the trial court for further proceedings. Specifically, we held that

the trial court erred in entering summary judgment based upon breach' of contract, where the evidence presented fails to address any of the terms of the verbal agreement-between Zacherl and the District, other than that Zacherl agreed to return to the Project to, complete the sheet metal work after it received a payment for two earlier invoices for which it had not received payment from Flaherty. In order to demonstrate a breach of contract, a plaintiff must establish: “(1) the existence of a.-contract between the plaintiff and deten- - dant, including its essential terms; (2) a breach of duty imposed by the contract; and (3) damages resulting from that breach of duty.” Boyd v. Rockwood Area Sch. Dist., 907 A.2d 1157, 1165 (Pa.Cmwlth.2006), appeal denied, ... [591 Pa. 717] 919 A.2d 959 ([Pa.] 2007).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
131 A.3d 1030, 2016 Pa. Commw. LEXIS 22, 2016 WL 56242, Counsel Stack Legal Research, https://law.counselstack.com/opinion/f-zacherl-inc-v-flaherty-mechanical-contractors-llc-pacommwct-2016.