F. M. Ross v. T. C. Bateson Construction Company

270 F.2d 796, 1959 U.S. App. LEXIS 5264, 38 Lab. Cas. (CCH) 65,820
Court of Appeals for the Fifth Circuit·Decided October 9, 1959·No. 17678_1·Published·Cited by 4 cases

Opinions

WISDOM, Circuit Judge.

This appeal presents the question of whether the appellant’s cause of action is barred by a former suit. The lower court held that the prior suit barred this action and granted the appellee’s motion for a directed verdict. We reverse and remand.

The T. C. Bateson Construction Company, appellee-defendant, contracted to construct four warehouses for the United States Government at Anniston Ordnance Depot, Anniston, Alabama. F. M. Ross, appellant-plaintiff, a subcontractor, agreed to excavate, clear, and grub land, and to excavate footings and backfilling for the general contractor, Bateson. The subcontract stipulated that time was of essence. The parties contemplated that Ross’ work would be completed in four months. Ross commenced work in August, 1952. He completed approximately eighty-five percent of the work within four or five months. Ross’ work was of such a nature that he had to wait on Bateson’s performance. Because of delays on the part of Bateson the final excavating and filling was not completed for fourteen or fifteen months. Ross suffered severe financial loss because of this delay, to the extent that in May 1953 it was necessary for his surety, Seaboard Surety Company, to take over his business and finish the job. Ross remained as trustee until the work was completed, October 1954.

The government’s decision to change the location of one of the warehouses was partly the cause of the delay. This change necessitated additional work on the part of Ross, because the dirt of the new location was difficult to excavate. The government acknowledged that the contract should be renegotiated. Ross and Bateson traveled to Mobile, Alabama, where a conference was held with the project engineer for the government. The parties agreed that Ross was entitled to an adjustment in the contract price amounting to an increase of approximately $45,000. Bateson was to submit this figure on the next estimate to the government. Bateson did not submit the increase to the government until after the completion of the job, and the $45,000 was not paid until a judgment was obtained against Bateson.

After the completion of the construction job, Yancey Bros., Inc., a material-man, filed a suit in the United States District Court for the Northern District of Alabama against Bateson under the Miller Act, 40 U.S.C.A. § 270a et seq. Several other creditors intervened and Ross and his surety were made third party respondents. The attorney for Seaboard Surety also represented Ross. After answering, he filed a counterclaim asking for Ross’ earnings under the subcontract. The other creditors settled their claims, and it was agreed that the cause of action raised by the counterclaim would be tried as an original Miller Act case. This was case number 817.

A few days before the date set for trial, Ross employed a new attorney. The new attorney prepared an amendment to the counterclaim asking for damages caused by the delay in performance and the delay in the payment of the $45,000. The district judge discussed the matter in chambers with counsel, discussed the continuance that would be necessary if [798] the amendment were allowed, pointed out that case 817 was under the Miller Act, and refused to allow the amendment.1

Ross’ attorney then filed the present action, case 889, as a separate suit in the same court. The present suit sets forth the same cause of action that Ross tried to assert by the amendment that was not allowed in case 817.

Case 817 was tried on the counterclaim for earnings under the subcontract. The jury awarded approximately $27,000 to Ross and Seaboard Surety on the counterclaim.2

The district judge held a pre-trial hearing for case 889. The issues were drawn and the case was set for a hearing on the merits. When the case was continued and the hearing date was reset it came up before another district judge. He too held a pre-trial hearing, but no formal order was prepared. At the trial, the district court granted Bateson’s motion for a directed verdict. Ross appeals from this judgment.

Ross assigns fifteen errors.3 We shall confine our consideration to the first two as they present the primary question in this case: Is the judgment in case 817 a bar to the present action ?

Ross contends that case 817 is not a bar because: (1) Ross was not the real party in interest in ease 817, since Seaboard Surety received all of the money that was recovered by the judgment in that case; (2) the issues are not the same in the two cases, because the counterclaim in case 817 did not ask for damages; (3) even if Bateson’s liability for delaying payment and delaying performance should have been litigated in ease 817, it does not bar the present action, since Ross tried to assert these damages by amendment in case 817, but the amendment was not allowed. Bateson’s main contentions are three-fold: (1) The judgment for Ross in case 817 bars the present suit; (2) Ross is precluded from recovering damages because of his failure to comply with a provision of the subcontract requiring written notice of any damages suffered within ten days from the beginning of the damages; (3) Ross is also precluded by another provision of the subcontract requiring a full accounting of damages within ten days from the date that the extent of the damages is known.

Bateson argues that case 817 is a bar to this suit because: (1) Suing and recovering on the subcontract in case 817 constituted an election of remedies that is binding on Ross; (2) allowing recovery in this suit for damages would violate the rule against splitting a cause [799] of action; (3) Ross’ action for damages was a compulsory counterclaim in case 817 and as it was not presented in that case, it is lost.

Free access — add to your briefcase to read the full text and ask questions with AI

F. M. Ross v. T. C. Bateson Construction Company, 270 F.2d 796, 1959 U.S. App. LEXIS 5264, 38 Lab. Cas. (CCH) 65,820 (5th Cir. 1959).

270 F.2d 796 (F. M. Ross v. T. C. Bateson Construction Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lee v. Rapid City Area School District, No. 51-4
526 N.W.2d 738 (South Dakota Supreme Court, 1995)
Craig A. Dell v. William A. Heard, Jr.
532 F.2d 1330 (Tenth Circuit, 1976)
F. M. Ross v. T. C. Bateson Construction Company
270 F.2d 796 (Fifth Circuit, 1959)