ExxonMobil Pipeline Co. v. Harrison Interests, Ltd.

93 S.W.3d 188, 2002 WL 1438627
CourtCourt of Appeals of Texas
DecidedAugust 29, 2002
Docket14-00-01392-CV, 14-01-01209-CV
StatusPublished
Cited by14 cases

This text of 93 S.W.3d 188 (ExxonMobil Pipeline Co. v. Harrison Interests, Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ExxonMobil Pipeline Co. v. Harrison Interests, Ltd., 93 S.W.3d 188, 2002 WL 1438627 (Tex. Ct. App. 2002).

Opinion

OPINION

LESLIE BROCK YATES, Justice.

In these consolidated cases, appellant ExxonMobil Pipeline Company (“Exxon-Mobil”) appeals from a dismissal of its condemnation proceeding for lack of jurisdiction and a final judgment for the landowner, appellee Harrison Interests, Ltd. (“Harrison”), awarding damages resulting from ExxonMobil's possession of the property it sought to condemn. We reverse the dismissal of the condemnation proceeding and remand for further proceedings, and we reverse and render final judgment on the damages award.

FACTUAL AND PROCEDURAL BACKGROUND

ExxonMobil is a common carrier vested with the power of eminent domain. In March of 1995, ExxonMobil determined that there was a public necessity to construct a common carrier pipeline from the Katy Gas Plant in Waller County, Texas, through Fort Bend County, Texas, to a location near Damon Junction in Brazoria County, Texas. In connection with that project, ExxonMobil also determined that there was a public necessity to acquire a permanent right-of-way and easement across a 473-acre tract owned by Harrison in northern Fort Bend County. The easement was to be fifty feet wide and 8,000 feet long, or 9.19 acres.

ExxonMobil attempted to negotiate with Harrison to acquire a permanent easement and a temporary construction easement. The negotiations were unsuccessful, however, and on June 20, 1995, ExxonMobil made Harrison a final offer of $45,950.00 for the easements. Enclosed with ExxonMobil’s final offer letter was a form easement and right-of-way agreement detailing the rights and interests it sought to acquire. Harrison was given ten days to accept the offer. Exx-onMobil’s letter informed Harrison that in the event Harrison did not accept the final offer, ExxonMobil would initiate eminent domain proceedings. Athough Harrison received the letter, he did not contact ExxonMobil within the ten-day period or at any time thereafter.

Having received no response to its final offer letter, on August 2, 1995, ExxonMo-bil filed its Statement and Petition in Condemnation seeking to take the easement. After a special commissioners’ hearing at which Harrison did not appear, ExxonMo-bil deposited the amount of compensation determined by the commissioners, $7,858.00, into the registry of the court, took possession of the easement, and installed the pipeline.

Prior to trial on the issue of just compensation, ExxonMobil moved for partial summary judgment on its right to condemn, asserting that no disputed facts were before the trial court. Harrison responded to the motion and filed a cross motion for partial summary judgment, arguing that the trial court had no jurisdiction because ExxonMobil did not conduct good faith negotiations with Harrison prior to the condemnation proceeding. Harrison contended that, among other things, ExxonMobil faded to negotiate in good faith by requiring Harrison to grant it rights which ExxonMobil was not entitled to obtain in a condemnation proceeding, including (1) the unrestricted right to assign the easement; and (2) the obligation of Harrison to warrant and defend title to the easement.

*191 Following a hearing on the cross motions for partial summary judgment, the trial court found that ExxonMobil had negotiated in good faith and ruled that Exx-onMobil had the power to condemn the property sought in its petition. Subsequently, however, the First Court of Appeals decided a condemnation case against the condemnor in a factually similar case. Harrison then moved to dismiss Exxon’s condemnation proceeding for want of jurisdiction on the basis of the new authority. On August 4, 2000, the trial court granted Harrison’s motion.

After Exxon’s condemnation case was dismissed, Harrison sought a trial on damages resulting from ExxonMobil’s possession of the property, and attorney’s and expert fees as allowed by the Texas Property Code. Following the trial, the trial court signed a final judgment on December 21, 2000 awarding Harrison $28,809.80 in professional fees and expenses, $110,000.00 in attorney’s fees through trial and appeal, $151,922.64 in damages through October 20, 2000, $102,534.92 in future damages through October 19, 2003, $75,961.32 in prejudgment interest accruing at the rate of $41.62 per day from October 18, 2000 until judgment, and post-judgment interest. ExxonMobil was also ordered to pay all costs.

ANALYSIS

In this consolidated appeal, Exxon appeals the dismissal of its condemnation case for want of jurisdiction and the final judgment in favor of Harrison. Because we find that the appeal of the dismissal for want of jurisdiction on the issue of the statutory good faith negotiation requirement is dispositive of the appeal of the final judgment, we will begin there.

The Good Faith Negotiation Requirement

ExxonMobil contends that it negotiated in good faith prior to filing its condemnation case because, after unsuccessful negotiations with Harrison for the easement, it made Harrison a final offer for an amount well in excess of the easement’s appraised value, but received no response. Harrison argues that ExxonMobil did not negotiate in good faith because it sought to acquire two property rights it could not obtain by condemnation, specifically (1) the unrestricted right to assign the easement, and (2) the obligation of Harrison to warrant and defend title to the easement. 1

In order to avoid the time and expense of a condemnation proceeding, a condemnor is required to negotiate in good faith with a landowner for the property rights the condemnor is attempting to acquire before filing a condemnation proceeding. Mercier v. MidTexas Pipeline Co., 28 S.W.3d 712, 720 (Tex.App.-Corpus Christi 2000, pet. denied); Schlottman v. Wharton County, 259 S.W.2d 325, 330 (Tex.Civ.App.-Fort Worth 1953, writ *192 dism’d). The requirement of good faith negotiations, also known as the “unable to agree” requirement, is found in section 21.012 of the Texas Property Code, which provides as follows:

(a) If ... a corporation with eminent domain authority ... wants to acquire real property for public use but is unable to agree with the owner of the property on the amount of damages, the condemning entity may begin a condemnation proceeding by filing a petition in the proper court.
(b) The petition must:
[[Image here]]
(4) state that the entity and the property owner are unable to agree on the damages.

Tex. PROp.Code Ann. § 21.012 (Vernon 1984) (emphasis added). The “unable to agree” condition refers to a bona fide attempt to agree on damages and includes a bona fide offer by the condemnor to pay the estimated true value of the land. Hubenak v. San Jacinto Gas Transmission Co., 65 S.W.3d 791, 797 (Tex.App.-Houston [1st Dist.] 2002, pet. filed); State v. Schmidt,

Related

Cite This Page — Counsel Stack

Bluebook (online)
93 S.W.3d 188, 2002 WL 1438627, Counsel Stack Legal Research, https://law.counselstack.com/opinion/exxonmobil-pipeline-co-v-harrison-interests-ltd-texapp-2002.