Exxon Mobil Corp. v. Saudi Basic Industries Corp.

941 F. Supp. 2d 513, 2005 WL 6939358, 2005 U.S. Dist. LEXIS 22166
CourtDistrict Court, D. New Jersey
DecidedSeptember 30, 2005
DocketCivil Action No. 04-4900 (WHW)
StatusPublished
Cited by3 cases

This text of 941 F. Supp. 2d 513 (Exxon Mobil Corp. v. Saudi Basic Industries Corp.) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Exxon Mobil Corp. v. Saudi Basic Industries Corp., 941 F. Supp. 2d 513, 2005 WL 6939358, 2005 U.S. Dist. LEXIS 22166 (D.N.J. 2005).

Opinion

OPINION

WALLS, District Judge.

Saudi Basic Industries Corporation (“SABIC”) moves to compel Exxon Mobil Corporation (“ExxonMobil”) to arbitrate this dispute and seeks a stay of litigation in this Court until such arbitration is complete. As a corollary, SABIC appeals the entry of a pretrial scheduling order by the Magistrate Judge assigned to the case. For the reasons set forth below, the motion to compel arbitration and stay the litigation is denied and the Magistrate Judge’s pretrial scheduling order is modified.

FACTS AND PROCEDURAL BACKGROUND

Plaintiff ExxonMobil filed a complaint, individually and on behalf of Al-Jubail Petrochemical Co. (“KEMYA”), against defendant SABIC on October 7, 2004. KEMYA is a 50/50 joint venture between SABIC and Exxon Chemical Arabia, Inc. (“ECAI”), an indirect subsidiary of Exxon-Mobil. ExxonMobil’s complaint alleges: (1) breach of contract; (2) breach of covenant of good faith and fair dealing; (3) fraud in the inducement; (4) negligent misrepresentation; (5) unjust enrichment; and (6) promissory estoppel, each in conjunction with SABIC’s alleged violations of the March 10, 2000 stipulation agreement made between SABIC and ExxonMobil before this Court (the “Stipulation”). The Stipulation provides that ExxonMobil drop the fourth count of its amended counterclaim against SABIC in Civil Action No. 98-4897 (the “NJ-I” action) and that SA-BIC and its affiliates (other than KEMYA) refrain from using certain technologies (the “SCM-T Information”) until ownership rights in the technologies are established. The fourth count of the amended counterclaim alleged that SABIC had breached its fiduciary duties to KEMYA by assisting other SABIC affiliates in their use of SCM-T Information.1

Although nearly identical, there are two arbitration provisions at issue in this case. The first provision is found in the 1980 Joint Venture Agreement (“JVA”) between SABIC and ECAI; the second in the 1980 Service Agreement (“SA”) between KEM-YA and Exxon Chemical Company (“ECC”), an unincorporated subsidiary of ExxonMobil. The JVA reads in pertinent part:

[516]*516 Article 17
Settlement of Dispute:
17.1 Subject to Article 16 of this Joint Venture Agreement if at any time any question, dispute, difference or controversy shall arise between the Partners relating to the design, construction, start-up, maintenance and subsequent operation of the Petrochemical Plant (including the provision of technical information and services) or as a result of or in connection with the provisions of this Joint Venture Agreement and the applicable annexes either Partner within (60) days following a notice to the other partners of the existence of' a dispute may request that such matter be made the subject of a non-binding recommendation by 3 arbitrators appointed in accordance with the Rules of Conciliation and Arbitration of the Kingdom. The arbitration shall take place in Saudi Arabia and shall be conducted in English and Arabic and provision shall be made for simultaneous translation.
17.2 Each Partner undertakes to refrain from instituting any proceedings under Article 12.1 until the forgoing procedure has been completed and a further 90 days have elapsed thereafter, without prejudice to all other remaining rights of the partners under the provisions of this Joint Venture Agreement.2

DISCUSSION

SABIC’s principal argument is that the arbitration provisions in question are governed by the Federal Arbitration Act (“FAA”). 9 U.S.C. § 1 et seq. If SABIC is correct and the provisions are otherwise enforceable, this Court is without discretion in the matter and must compel arbitration and stay the litigation, 9 U.S.C. §§ 3-4. ExxonMobil counters that the provisions are non-binding and not subject to the FAA. ExxonMobil also argues that the provisions are unenforceable for a variety of reasons, including absence of agreement, waiver, and estoppel. The Court need not decide whether the arbitration agreements are otherwise enforceable because it now holds that the non-binding arbitration provisions in this case fall outside the scope of the FAA.

I. Applicability of the FAA

Federal law is unsettled with regard to the application of the FAA to non-binding arbitration provisions. See, e.g., Wolsey, Ltd. v. Foodmaker, Inc., 144 F.3d 1205, 1207-09 (9th Cir.1998) (applying the FAA to a mandatory, non-binding arbitration provision). But cf. Bombardier Corp. v. National R.R. Passenger Corp., 333 F.3d 250, 251-52 (D.C.Cir.2003) (discussing district court’s refusal to compel alternative dispute resolution in a case with $200 million in claims where the panel was only able to issue binding awards up to $5 million). The Third Circuit has twice considered the issue, generally adopting the approach outlined by Judge Jack Weinstein in AMF, Inc. v. Brunswick Corp., 621 F.Supp. 456 (E.D.N.Y.1985). There, the Judge noted that “[ajrbitration is a term that eludes easy definition,” “[t]he Federal Arbitration Act ... made agreements to arbitrate enforceable without defining what they were,” and “[a]t no time have the courts insisted on a rigid or formalistic approach to the definition of arbitration.” Id. at 459-60. Judge Weinstein [517]*517believed that “[t]he issue posed is whether ‘a controversy’ would be ‘settled’ by the process set forth in the agreement,” “vieioed in the light of reasonable commercial expectations.” Id. at 459, 461 (emphasis added).

In the first Third Circuit case adopting this approach, Harrison v. Nissan Motor Corp., 111 F.3d 343, 349 (3d Cir.1997), the court held that non-binding arbitration under the Pennsylvania Lemon Law did not fall under the FAA because a claimant could pursue litigation after forty days if the arbitrator had not reached a final decision. The definition of “arbitration” was narrowed:

the essence of arbitration ... is that, when the parties agree to submit then-disputes to it, they have agreed to arbitrate these disputes through to completion, i.e. to an award made by a third-party arbitrator. Arbitration does not occur until the process is completed and the arbitrator makes a decision. Hence, if one party seeks an order compelling arbitration and it is so granted, the parties must then arbitrate their dispute to an arbitrator’s decision, and cannot seek recourse to the courts before that time.

Id. at 350.

In the second decision, Dluhos v. Strasberg, 321 F.3d 365, 370 (3d Cir.2003), the circuit held that the FAA did not apply to a contractual regime providing for nonbinding arbitration, when not preventing a party from filing suit before, during or after the arbitration proceedings. This case also adopted the Weinstein “reasonable commercial expectations” standard as well as the Harrison

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
941 F. Supp. 2d 513, 2005 WL 6939358, 2005 U.S. Dist. LEXIS 22166, Counsel Stack Legal Research, https://law.counselstack.com/opinion/exxon-mobil-corp-v-saudi-basic-industries-corp-njd-2005.