Bombardier Corp. v. National Railroad Passenger Corp.

298 F. Supp. 2d 1, 2002 U.S. Dist. LEXIS 26544, 2002 WL 32333170
CourtDistrict Court, District of Columbia
DecidedSeptember 30, 2002
DocketCIV. 01-2335(RJL)
StatusPublished
Cited by5 cases

This text of 298 F. Supp. 2d 1 (Bombardier Corp. v. National Railroad Passenger Corp.) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bombardier Corp. v. National Railroad Passenger Corp., 298 F. Supp. 2d 1, 2002 U.S. Dist. LEXIS 26544, 2002 WL 32333170 (D.D.C. 2002).

Opinion

MEMORANDUM ORDER

LEON, District Judge.

On May 1, 1996, Bombardier Corporation (“Bombardier”), GEC Alstom (“Alstom”), and National Railroad Passenger Corporation (“NRRPC,” “Amtrak”) entered into three fixed price contracts (collectively referred to as “Contract”) for the design and construction of high-speed passenger trainsets, locomotives, rail equipment, and facilities to be operated by Amtrak in the Northeast corridor. 1 These *2 trainsets comprise the Acela Express trains, now in use between Washington, D.C., and Boston, Massachusetts.

The design and construction processes have been riddled with problems from the start. Both Bombardier and Amtrak agree that “performance under the Contracts has been plagued by delays.” 2 According to Amtrak, delivery on the fifteen trainsets was, in aggregate, 6,900 days late, with the first trainset, scheduled to be delivered in November 1999, arriving 351 days late. 3 Bombardier argues that Amtrak is to blame for the delay in putting the Acela trains into operation because Amtrak repeatedly changed design specifications, delayed in approving design specifications, insisted on defective or impracticable design modifications and unnecessary testing requirements, and failed to complete track modernizations and electrification necessary to accommodate the high-speed trainsets. Amtrak, in turn, argues that any delay is attributable to Bombardier as subcontractors that Bombardier selected were late in delivering brakes and other train components to Bombardier. Further, Amtrak claims that track electrification did not contribute to manufacturing delays. Aside from delay, Amtrak maintains that the trainsets Bombardier delivered do not meet the Contract’s specifications. Specifically, Amtrak contends that there are cracks in the steel used to construct the carbody frames, that the trains have not qualified for the speeds designated in the Contract, and other design defects exist that hamper the trains’ “optimal performance.” 4

On November 8, 2001, Bombardier Corporation (“Bombardier”) brought suit against the National Railroad Passenger Corporation (“NRRPC,” “Amtrak”) seeking at least $200,000,000 in damages. Before the Court can reach the merits of Bombardier’s claims against Amtrak, however, it must first determine whether these claims are appropriately before the Court at this time. The Contract executed by Bombardier, Alstom, and Amtrak contained a dispute resolution provision for claims “arising from or related to the Contract.” According to Amtrak, Bombardier is barred, as a matter of law, from seeking relief here because it did not first submit its claims, presently before this Court, to the dispute resolution processes provided for by the Contract. Therefore, Amtrak asks that Bombardier’s Complaint be dismissed.

Because the Court finds that dispute resolution was not a condition precedent to litigation, Amtrak’s Motion to Dismiss is DENIED.

The Contract

According to Article 32 of the Contract between Amtrak and Bombardier and Alstom, “any Claim relating to this Contract” is subject to the dispute resolution provisions of Article 32. Article 29 of the Contract defines a “claim” to be:

a “demand or assertion by one of the parties seeking, as a matter of right: (i) an adjustment or interpretation of Contract terms, (ii) payment of money, (iii) an extension of time, (iv) other relief with respect to the terms of the Contract, or (v) a resolution of all other disputes and matters in question be *3 tween Amtrak and Contractor arising out of or relating to the Contract.” 5

Claims, which must be made by written notice, 6 are initially referred to a Contracting Officer Representative (“COR”) or Contracting Officer’s Technical Representative (“COTR”) for review. 7 Only after the COR or COTR has made a decision regarding the claim may a party seek a final decision from a Contracting Officer (“CO”). 8 If the party disagrees with the Contracting Officer’s final decision, the party may then pursue its claim before the Dispute Resolution Board (DRB), in accordance with the terms and provisions of Article 32.

Article 32, entitled “Resolution of Claims and Disputes,” outlines the procedures parties must follow when submitting Claims to the Dispute Resolution Board. In particular, it provides that “any Claim relating to this Contract which is not disposed of by agreement of the parties shall be referred to and decided by the Contracting Officer.” While this provision uses mandatory language, the DRB has jurisdiction over only two types of Claims: disputes regarding money damages, and rulings on whether particular services or work required by a Change Order is within the scope of Bombardier’s and Amtrak’s Contract. 9 Article 32 also stipulates that decisions of the DRB are binding only if disputes involve $5 million or less; if the dispute involves more than $5 million, the DRB’s decision is not binding unless the parties agree to it. Moreover, Article 32 provides that if the parties are “unable to resolve their dispute through negotiation or the DRB,” the parties may then pursue their Claim here, in the United States District Court for the District of Columbia. 10 Finally, the DRB provisions require the parties, “[p]ending a final court decision of a dispute,” to proceed with their performance under the Contract. 11

Dispute Resolution is Not a Condition Precedent to Litigation

Amtrak argues that Bombardier’s claims now before this Court fall squarely within the Contract’s dispute resolution provisions. First, Bombardier’s claims are “Claims,” as defined by the Contract, because they are either demands for the “payment of money,” or “seeking ... a resolution of all other disputes and matters in question between Amtrak and Contractor [Bombardier] arising out of or relating to the Contract,” per Article 29. Second, Amtrak maintains that these Claims fall within the dispute resolution processes of Article 32 because demands for payment of money, or for resolution of disputes and matters in question between Amtrak and Bombardier, necessarily relate to the Contract. Amtrak argues that the language of Article 32, and all other provisions of the Contract relating to dispute resolution proceedings, is plain and unambiguous, and leads to only one conclusion: that submission of Claims relating to the Contract to the dispute resolution process is mandatory, and that Bombardier’s failure to submit the claims now before this Court to a COR, then to a CO and finally to a DRB, bars it from seeking relief here.

Bombardier, however, maintains that submission of Claims to the Contract’s dispute resolution process outlined in Article *4 82 is not a condition precedent to litigation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
298 F. Supp. 2d 1, 2002 U.S. Dist. LEXIS 26544, 2002 WL 32333170, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bombardier-corp-v-national-railroad-passenger-corp-dcd-2002.