Essex Crane Rental Corp. v. Striland Construction Co.

753 S.W.2d 751, 1988 WL 81454
CourtCourt of Appeals of Texas
DecidedJune 14, 1988
Docket05-87-00313-CV
StatusPublished
Cited by66 cases

This text of 753 S.W.2d 751 (Essex Crane Rental Corp. v. Striland Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Essex Crane Rental Corp. v. Striland Construction Co., 753 S.W.2d 751, 1988 WL 81454 (Tex. Ct. App. 1988).

Opinion

BAKER, Justice.

Essex Crane Rental Corporation appeals from a judgment in which a jury awarded damages and attorney’s fees to Striland Construction Company for breach of an equipment lease. We disagree with Essex’ contentions that neither the pleadings nor the evidence supported the submission of the special issues concerning Essex’ breach of the lease or the jury’s finding of a breach. However, we do agree with Essex that the trial court erred in disregarding the jury’s award of attorney’s fees to it. Striland brings two cross-points of error which this court is without jurisdiction to consider. Accordingly, we modify the judgment to reinstate the jury’s award of attorney’s fees to Essex and affirm the judgment as modified.

The material facts of this case are not in dispute. Striland, working as a concrete subcontractor on a project at the University of Dallas, leased a Manitowoc 4000 W Lift Crane from Essex in 1988. The agreement provided for a four-month minimum rental period with rental payments of $6,500 per month. At the expiration of the four-month rental period in February of 1984, Striland paid for its use of the crane in full and asked Essex to remove the crane from the job site. In response, Essex informed Striland that it intended to store the crane at the job site for approximately two weeks. However, the crane was not removed from the job site until early June of 1984.

The evidence showed that during the three-month interim storage period Striland used the crane on at least four occasions but no more than ten. As a result, Essex claims that it is due the full monthly rental payment of $6,500 per month for the period of March 3,1984, to June 1,1984. Striland contends, however, that Essex is entitled only to rent for the actual time the crane was used and offered to pay Essex two weeks’ rent for its use _of the crane. Demanding full payment, Essex refused the offer and by letter dated June 27, 1984, notified J.W. Bateson Company, the general contractor, and Traveler’s Insurance, the surety, of its claim. Subsequently, Essex filed a lien on the project for its claim.

Earl Davis, Bateson’s representative, testified that on the date of the Essex notice letter, Bateson did not owe any additional money to Striland because Striland had already been paid more than it was due under its contract. However, Bateson determined that it would be cheaper to pay Striland its additional costs for completing the project rather than to complete the project itself. Accordingly, it paid six additional pay requests to Striland, but after receiving notification of Essex’ claim and lien, it refused to pay Striland’s last three pay requests totaling $10,715.69. Davis further stated that had the lien not been filed, it was very possible that Striland would have been paid for its final pay requests as Bateson had routinely done in the past.

Striland sued for breach of the equipment lease seeking the $10,715.69 withheld by Bateson after Essex filed its lien. Essex counterclaimed for $20,366.66 in rent based on Striland’s use of the crane while it was stored at the project site. The jury found that Essex had breached the lease agreement by failing to inform Striland of the length of storage time, by failing to remove the crane from the job site, and by seeking rent for the entire term of the storage period. Furthermore, the jury found that due to Essex’ breach, Striland was unable to recover its final three payment requests from the general contractor, resulting in $10,715.69 in damages. The jury refused to find that Essex had breach *754 ed the lease by filing a lien and, further, awarded Essex an offset of $1,083.33, representing the daily rental rate for five days’ use of the crane. In addition, the jury awarded both parties attorney’s fees for trial and appeal. The trial court entered judgment in accordance with the jury’s findings but disregarded the award of attorney’s fees to Essex, apparently finding its initial claim for $20,366.66 excessive and in bad faith. Further, the court refused to invalidate the mechanic’s and materialman’s lien filed by Essex.

In points of error four, ten, and sixteen, Essex complains that the trial court erred in submitting the special issues inquiring whether Essex breached the lease agreement because the issues were not supported by pleadings. We disagree. Essex did not specially except to Striland’s petition. JÜ)sent special exceptions, a petition will be construed liberally in favor of the pleader. Roark v. Allen, 633 S.W.2d 804, 809 (Tex.1982). This Court will look to the pleader’s intentions and uphold the pleadings even in the absence of a specific allegation of an element to the cause of action. In addition, every fact that can reasonably be supported by the specific allegations contained in the pleading will be inferred. Roark v. Allen, 633 S.W.2d at 809; Gulf, Colorado & Santa Fe Railway Co. v. Bliss, 368 S.W.2d 594, 599 (Tex.1963). A petition that gives fair and adequate notice of the facts upon which the pleader bases his claim is sufficient because it provides the opposing party with enough information to enable him to prepare a defense. Murray v. O & A Express, Inc., 630 S.W.2d 633, 636 (Tex.1982); Castleberry v. Goolsby Building Corp., 617 S.W.2d 665, 666 (Tex.1981).

Striland’s petition alleged breach of contract in the following manner:

2. Essex Crane’s failure to advise Stri-land that it intended to store the crane on the Project constituted a breach of the Lease, which clearly contemplated that Essex Crane would advise Striland if it was necessary to store the cráne on the Project. In further breach of the Lease, Essex Crane also failed to advise Striland of the extended length of time it intended to store the crane on the Project. (Emphasis in original)
3. By reason of the aforementioned breach of the Lease, by Essex Crane, the Defendant is precluded from recovering rent for the months the crane remained on the Project following Striland's written notice of termination. Essex Crane’s filing of a lien on the project is in further breach of the Lease, and this lien filing damaged Striland in the amount of $10,-715.69, representing funds not paid to Striland by the Project contractor.

Furthermore, Paragraph Fourteen of Striland’s pleadings requesting a declaratory judgment states:

3. The months for which Essex has charged Striland additional rent resulted from Essex Crane’s failure to remove its crane from the Project within a reasonable period of time after Striland provided written notice of termination. As a result, Striland is entitled to a Declaratory Judgment establishing that the amount claimed due by Essex Crane is not a just debt and that the lien filed by Essex Crane is therefore invalid and directing Essex Crane to execute and record a release of such lien.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allman v. Butcher
314 S.W.3d 671 (Court of Appeals of Texas, 2010)
Wallace v. Perry (In Re Perry)
423 B.R. 215 (S.D. Texas, 2010)
in the Interest of I. D. T., a Child
Court of Appeals of Texas, 2008
in the Interest of N. L. G., a Minor Child
Court of Appeals of Texas, 2006
Dessie Hunt Simmons v. State
Court of Appeals of Texas, 2006
Kurtz, Julia L. v. Kurtz, Ronald D.
Court of Appeals of Texas, 2004
Steve Sadoskas v. Gail Gleimer Sadoskas
Court of Appeals of Texas, 2003
Standard Constructors, Inc. v. Chevron Chemical Co.
101 S.W.3d 619 (Court of Appeals of Texas, 2003)
Wayne v. A.V.A. Vending, Inc.
52 S.W.3d 412 (Court of Appeals of Texas, 2001)
Wayne, James v. A.V.A. Vending, Inc.
Court of Appeals of Texas, 2001

Cite This Page — Counsel Stack

Bluebook (online)
753 S.W.2d 751, 1988 WL 81454, Counsel Stack Legal Research, https://law.counselstack.com/opinion/essex-crane-rental-corp-v-striland-construction-co-texapp-1988.