Ergon-West Virginia, Inc. v. Dynegy Marketing & Trade

706 F.3d 419, 2013 WL 237567
CourtCourt of Appeals for the Fifth Circuit
DecidedJanuary 22, 2013
Docket11-60492
StatusPublished
Cited by23 cases

This text of 706 F.3d 419 (Ergon-West Virginia, Inc. v. Dynegy Marketing & Trade) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ergon-West Virginia, Inc. v. Dynegy Marketing & Trade, 706 F.3d 419, 2013 WL 237567 (5th Cir. 2013).

Opinions

EDITH BROWN CLEMENT, Circuit Judge:

Appellant-Cross Appellee Dynegy Marketing and Trade (“Dynegy”) and Cross [422]*422Appellant Ergon Refining appeal the district court’s holding that Dynegy had no contractual duty to Ergon Refining to attempt to secure replacement gas after declaring force majeure in response to hurricane damage, but did have such a duty to Ergon-West Virginia (“Ergon-WV”) under a separate contract. For the reasons provided below, we hold that neither contract required Dynegy to attempt to secure replacement gas during the force majeure period. We AFFIRM the district court’s ruling on the Ergon Refining contract and REVERSE and RENDER with respect to the Ergon-WV contract.

FACTUAL AND PROCEDURAL BACKGROUND

This is a contract dispute between a natural gas clearinghouse, Dynegy, and two separate entities that manage refinery plants, Ergon Refining and Ergon-WV. The two Ergon entities1 have contracted with Dynegy to provide their natural gas supply since 19932 and 1997, respectively. When Hurricanes Katrina and Rita hit in 2005 and caused extensive damage to the gas industry’s infrastructure, Dynegy’s own internally designated suppliers declared force majeure. Dynegy followed suit, reducing its supply of gas to both Ergon entities. This forced Ergon Refining and Ergon-WV to buy gas on the open market at increased cost during the force majeure event. To recoup these costs, they sued Dynegy in Mississippi state court, alleging that their respective contracts’ force majeure provisions required Dynegy to attempt to secure replacement gas, which Dynegy admits that it did not do.3 Instead, Dynegy contends that it had no such contractual duty to either Ergon company.

After the two Ergon companies’ suits were removed to federal court and consolidated, the district court held a bench trial. Following trial, the district court determined that the Ergon Refining contract was ambiguous and that extrinsic evidence showed that the contract did not obligate Dynegy to attempt to secure replacement gas. But the court concluded that the Ergon-WV contract unambiguously required Dynegy to make this attempt. The court’s analysis hinged on the language of the force majeure provisions in each contract.

Interpreting the Ergon Refining contract, the district court ruled for Dynegy. The language in this contract required the party invoking force majeure to demonstrate that it had “remedied with all reasonable dispatch” the force majeure event.4 [423]*423The court concluded that this provision was ambiguous for two main reasons. First, it determined that one of the recitals of the contract, which specifies, “WHEREAS, Seller has certain volumes of gas which are available for sale,” implies that the parties intended that the seller would supply gas from designated sources. Second, the district court noted that the initial contract expressly referred to designated source points, which the parties later removed through a series of amendments. Taken together, these facts suggested to the court that there was “at least a latent ambiguity” in the contract as to whether Dynegy had a duty to seek replacement gas.

Because the district court concluded that the contract was ambiguous, it admitted parol evidence of trade usage in the form of unrebutted testimony given at trial by Dyaeg/s expert witness, whom it found “highly credible.” The district court explained that the witness testified that it is a “universal practice” in the gas industry for a downstream supplier to declare force majeure when its upstream supplier has done so and that the downstream supplier is not expected or obligated to search for replacement gas. Moreover, the court noted that the witness testified that “there were sound economic reasons for this approach,” and, particularly that it stabilized prices during a force majeure event by quelling demand. The court, based on this testimony, found that Dynegy had remedied with all reasonable dispatch the supply reduction caused by the hurricanes and held that Dynegy was excused from performing during the force majeure period.

Turning to the Ergon-WV contract, the district court ruled for Ergon-WV. Although this contract did not contain an “all reasonable dispatch” clause in its force majeure provision, it required that for some, if not all, force majeure events, the party invoking force majeure demonstrate that the event was one that it was unable to overcome with due diligence. The provision allowed a party to invoke force majeure if it was “rendered unable, by reason of an event of force majeure, to perform, wholly or in part” and listed events that qualify. Following its list of enumerated force majeure events, which included “hurricanes” and “partial or entire failure of wells or sources of supply of gas,” the provision concluded “and any other causes, whether of the kind herein enumerated or otherwise, not within the control of the party claiming suspension and which by the exercise of due diligence such party is unable to prevent or overcome.” (Emphasis added.) The court concluded that the language of the Ergon-WV force majeure provision was “far more straightforward” than the Ergon Refining provision, and thus that the Ergon-WV contract was unambiguous. According to the court, the Ergon-WV contract unambiguously “required [Dynegy] to find replacement gas or use due diligence to overcome the event.” Because Dynegy conceded that it was physically capable of transporting gas to Ergon-WV’s plant and that it could have purchased gas on the open market, the district court found that Dynegy could have provided replacement gas using due diligence, and so it was not entitled to invoke force majeure. The court, therefore, awarded Ergon-WV the difference between the cover price and the contract price plus pre-judgment interest.

Ergon Refining and Dynegy cross-appeal the district court’s construction of the two contracts’ force majeure provisions. Dynegy also contends on appeal that the district court erred by not requiring Er[424]*424gon-WV to prove the amount of its damages.

STANDARD OF REVIEW

“The standard of review for bench trials is well-established: ‘findings of fact are reviewed for clear error; legal issues de novo.’” Gebreyesus v. F.C. Schaffer & Assocs., Inc., 204 F.3d 639, 642 (5th Cir. 2000) (quoting FDIC v. McFarland, 33 F.3d 532, 536 (5th Cir.1994)). Under the contracts’ choice-of-law-provisions, all issues of contract construction are governed by Texas law.

In Texas, the existence of ambiguity in a contract is a question of law, so the Court reviews whether the Ergon contracts were ambiguous de novo. In re D. Wilson Constr. Co., 196 S.W.3d 774, 781 (Tex.2006); see Gebreyesus, 204 F.3d at 642. “A contract is ambiguous only if it is subject to two or more reasonable interpretations after applying the pertinent rules of construction.” In re D. Wilson Constr. Co., 196 S.W.3d at 781 (citation and internal quotation marks omitted). A contract is unambiguous “[i]f the written instrument is so worded that it can be given a certain or definite legal meaning or interpretation.” Coker v. Coker, 650 S.W.2d 391, 393 (Tex.1983).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

R & R BOATS, INC. v. GOL, LLC
E.D. Louisiana, 2025
MIECO v. Targa Gas Marketing
Fifth Circuit, 2025
Marathon Oil v. Mercuria Energy America
2025 Tex. Bus. 39 (Texas Business Court, 2025)
Seacor Marine LLC v. GOL, LLC
E.D. Louisiana, 2025
Mieco, L.L.C. v. Pioneer
Fifth Circuit, 2024
Franlink v. BACE Services
50 F.4th 432 (Fifth Circuit, 2022)
Conn Credit I, L.P. v. TF Loanco III, L.L.C.
903 F.3d 493 (Fifth Circuit, 2018)
Lyda Swinerton Builders, Inc. v. Okla. Sur. Co.
903 F.3d 435 (Fifth Circuit, 2018)
Carla Frew v. Thomas Suehs
Fifth Circuit, 2017
LLOG Exploration Company, LLC v. Signet Maritime C
673 F. App'x 422 (Fifth Circuit, 2016)
International Marine, L.L.C. v. FDT, L.L.C.
619 F. App'x 342 (Fifth Circuit, 2015)
United States v. Markus Stanley
595 F. App'x 314 (Fifth Circuit, 2014)
ARV Offshore Company, Limited v. Con-Dive, L.L.C.
514 F. App'x 524 (Fifth Circuit, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
706 F.3d 419, 2013 WL 237567, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ergon-west-virginia-inc-v-dynegy-marketing-trade-ca5-2013.