Equitable Life Assurance Society of the United States v. Basnight

67 S.E.2d 390, 234 N.C. 347, 1951 N.C. LEXIS 487
CourtSupreme Court of North Carolina
DecidedOctober 31, 1951
Docket305
StatusPublished
Cited by41 cases

This text of 67 S.E.2d 390 (Equitable Life Assurance Society of the United States v. Basnight) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Equitable Life Assurance Society of the United States v. Basnight, 67 S.E.2d 390, 234 N.C. 347, 1951 N.C. LEXIS 487 (N.C. 1951).

Opinion

Ekvin, J.

This question arises at the outset: Where a lien claimant files notice of a contractor’s lien against a building and the lot on which it stands in the office of the clerk of the Superior Court on 15 March, 1949, for work done and materials furnished by him in the construction of the building under contract with the owners of the lot between 14 August and 27 November, 1948, does the lien relate back to the time when the lien claimant began the performance of the work and the furnishing of the materials, and take precedence by reason of such relation back over an intervening recorded deed of trust made by the owners of the lot on 17 February, 1949?

The trial judge answered this query in the affirmative when he adjudged that the lien of the contractor Dunn has priority as against the deed of trust under which Equitable and Albion Dunn, Trustee, claim. We affirm his ruling on the authority of these decisions: King v. Elliott, 197 N.C. 93, 147 S.E. 701; Harris v. Cheshire, 189 N.C. 219, 126 S.E. 593; Porter v. Case, 187 N.C. 629, 122 S.E. 483; McAdams v. Trust Co., 167 N.C. 494, 83 S.E. 623; Dunavant v. Railroad, 122 N.C. 999, 29 S.E. 837; Pipe & Foundry Co. v. Howland, 111 N.C. 615, 16 S.E. 857, 20 L.R.A. 743; Burr v. Maultsby, 99 N.C. 263, 6 S.E. 108, 6 Am. S. R. 517; and Chadbourn v. Williams, 71 N.C. 444.

In so doing, we do not ignore the contentions of Equitable and Albion Dunn, Trustee, on this phase of the case. They advance these successive and interdependent arguments with much earnestness and industry: (1) The doctrine that a contractor’s lien for work done or materials furnished relates back to the time when the claimant commenced the performance of the work or the furnishing of the materials has no foundation in law save that embodied in a statute originally enacted as section 2 of chapter 206 of the Public Laws of 1869-70 and subsequently codified as section 1782 of the Code of 1883, which was couched in these words: *351 ■“The lien for work on crops or farms or materials given by this act stall be preferred to every otter lien or encumbrance wtict attached upon the property subsequent to the time at which the work was commenced, or the materials were furnished.” (2) This foundation of the relation back •doctrine was removed as to all liens arising under the laws now incorporated in chapter 44 of the General Statutes except liens for work on crops in 1905 when the codifiers of the Revisal changed the statute, i.e., section 2 of chapter 206 of the Public Laws of 1869-70 and section 1782 of the ■Code of 1883, to its present form, to wit: “The lien for work on crops given by this chapter shall be preferred to every other lien or encumbrance which attached to the crops subsequent to the time at which the work was commenced.” G.S. 44-41; O.S. 2472; Rev. 2034. (3) As a -consequence, the relation back doctrine has no application to the lien of the contractor Dunn, and the deed of trust under which Equitable and Albion Dunn, Trustee, claim has priority because it was made and recorded before the notice of Dunn’s lien was filed.

These arguments are untenable for reasons even more cogent than the significant fact that their acceptance would constitute a repudiation of all germane decisions handed down since the adoption of the Revisal of 1905.

Two of the present statutes giving liens to contractors for labor performed or materials furnished, namely G.S. 44-1 and G.S. 44-2, had their genesis in chapter 206 of the Public Laws of 1869-70. Section 2 was not put in that chapter to establish the relation back doctrine, and did not do so. It simply selected three specific liens, i.e., liens “for work on crops or farms or materials,” out of all the liens given to contractors by sections 1 and 3 of the chapter, and conferred upon such three specific liens preference over all other liens and encumbrances (including other liens given to contractors) “which attached upon the property subsequent to the time at which the work was commenced or the materials were furnished.” These considerations show that the relation back doctrine was not begotten by section 2 of chapter 206 of the Public Laws of 1869-70, and is not nurtured by its present day counterpart. G.S. 44-41.

The doctrine is inherent in the very statutes which give the contractor the lien upon the property improved by his labor or materials, and allow him six months after the completion of the labor or the final furnishing of the materials in which to claim it; for it is plain that unless the contractor’s lien when filed relates back to the time at which the contractor commenced the performance of the work or the furnishing of the materials, the object of the statutes can be defeated at the will of the owner of the property, by his selling or encumbering his estate. Burr v. Maultsby, supra; Chadbourn v. Williams, supra. To hold that the doctrine, of relation back is not inherent in these statutes would be to “keep the word of promise to our ear, and break it to our hope.”

*352 This brings us to the second and final question presented by the appeal: Does a contractor’s prior lien become unavailable as against subsequent encumbrancers by the contractor’s failure to make the subsequent encum-brancers parties to his action to enforce the lien brought against the owners within the statutory period?

Dunn, the builder, bottoms his claim to a contractor’s lien against the real property in controversy on this statutory provision: “Every building-built, rebuilt, repaired or improved, together with the necessary lots on which such building is situated . . ., shall be subject to a lien for the payment of all debts contracted for work done on the same, or material furnished.” G.S. 44-1.

A contractor’s lien on real property-is inchoate until perfected by compliance with legal requirements, and is lost if the steps required for its perfection are not taken in the manner and within the time prescribed bylaw. 36 Am. Jur., Mechanics’ Liens, Section 124; 57 C.J.S., Mechanics’ Liens, Section 119.

To perfect his lien on real property, the contractor must comply with these statutory requirements:

1. He must file a notice or claim of lien in the office of the clerk of the Superior Court of the county where the labor has been performed or the materials furnished within six months after the completion of the labor or the final furnishing of the materials specifying in detail the labor performed or the materials furnished and the time thereof. G.S. 44-38 and 44-39; Beaman v. Hotel Corp., and Roofing Co. v. Beaman, 202 N.C. 418, 163 S.E. 117; Supply Co., v. McCurry, 199 N.C. 799, 156 S.E. 91.

2. He must bring an action in the Superior Court to enforce the lien within six months from the date of the filing of the notice or claim of lien. G.S. 44-43 and 44-48 (4); Norfleet v. Cotton Factory, 172 N.C. 833, 89 S.E. 785.

These things being true, the present position of Equitable and Albion Dunn, Trustee, i.e.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Covenant Clearinghouse LLC v. D.R. Horton, Inc.
North Carolina Business Court, 2026
Pait v. Southeastern General Hospital
724 S.E.2d 618 (Court of Appeals of North Carolina, 2012)
Wachovia Bank National Ass'n v. Superior Construction Corp.
718 S.E.2d 160 (Court of Appeals of North Carolina, 2011)
Lawyers Title Ins. Corp. v. ZOGREO, LLC
702 S.E.2d 222 (Court of Appeals of North Carolina, 2010)
Dunn v. Cook
693 S.E.2d 752 (Court of Appeals of North Carolina, 2010)
Wachovia Bank, N.A. v. Superior Constr. Corp.
2010 NCBC 9 (North Carolina Business Court, 2010)
Apgar v. Crawford
692 S.E.2d 194 (Court of Appeals of North Carolina, 2010)
Park East Sales v. Clark-Langley, Inc.
651 S.E.2d 235 (Court of Appeals of North Carolina, 2007)
Sutton v. Messer
620 S.E.2d 19 (Court of Appeals of North Carolina, 2005)
Johnson v. Lucas
608 S.E.2d 336 (Court of Appeals of North Carolina, 2005)
Metropolitan Life Insurance Co. v. Rowell
444 S.E.2d 231 (Court of Appeals of North Carolina, 1994)
RDC, Inc. v. Brookleigh Builders, Inc. Ex Rel. Burns
305 S.E.2d 722 (Supreme Court of North Carolina, 1983)
RDC, Inc. v. Brookleigh Builders, Inc. ex rel. Burns
299 S.E.2d 448 (Court of Appeals of North Carolina, 1983)
Begley v. Employment Security Commission
274 S.E.2d 370 (Court of Appeals of North Carolina, 1981)
Thomas v. Thomas
260 S.E.2d 163 (Court of Appeals of North Carolina, 1979)
Swenson v. Thibaut
250 S.E.2d 279 (Court of Appeals of North Carolina, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
67 S.E.2d 390, 234 N.C. 347, 1951 N.C. LEXIS 487, Counsel Stack Legal Research, https://law.counselstack.com/opinion/equitable-life-assurance-society-of-the-united-states-v-basnight-nc-1951.