Equinor Energy LP v. Lindale Pipeline, LLC

Court of Appeals of Texas·Decided November 21, 2023·No. 01-21-00712-CV·Published

Opinion

Opinion issued November 21, 2023

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-21-00712-CV ——————————— EQUINOR ENERGY LP, Appellant V. LINDALE PIPELINE, LLC, Appellee

On Appeal from the 157th District Court Harris County, Texas Trial Court Case No. 2019-44547

MEMORANDUM OPINION

When Equinor Energy, LP’s predecessor, Brigham Oil & Gas, LP, began

developing oil and gas wells in the “Rough Rider” portion of North Dakota’s

Bakken Shale, the water needed for its operations was brought in by trucks and stored in tanks. In 2011, Brigham entered into a contract with Lindale Pipeline,

LLC for the construction and operation of a freshwater pipeline, which the parties

understood would be a more efficient and cost-effective way for Lindale to supply

water to Brigham and third parties. Through merger, sale, and assignment,

Brigham became “Statoil,” which later changed its name to Equinor. Around 2014,

with a downturn in the oil and gas industry and the arrival of an even more cost-

effective method of providing water for development and operation of wells,

Equinor began buying water from other suppliers instead of buying water that

Lindale could have delivered using the freshwater pipeline.

Lindale sued Equinor for breach of contract, and Equinor countersued for

breach of contract. A jury determined that both parties had breached the contract in

different ways. The jury found Lindale’s damages were $27,144,404.50, and

Equinor’s damages were $3,583,863.26. The trial court rendered judgment on the

verdict, awarding Lindale $23,560,541.20 plus pre- and post-judgment interest.

Equinor appealed.

On appeal, Equinor first argues that the trial court erred by finding that a

contested portion of the parties’ contract was ambiguous and submitting its

interpretation to the jury. Next, Equinor contends that there was no evidence to

support the jury’s finding of the amount of Lindale’s damages. Finally, Equinor

2 asserts that the jury charge incorrectly permitted the jury to rely on an

unreasonable interpretation of the contested portion of the contract.

We affirm.

Background

I. Behan and Anderson work in Texas providing water for oil and gas operations.

Dale Behan owned and operated International Western Company d/b/a

Western Company of Texas (“Western”) to provide water by pipeline to oil and

gas wells for drilling, completion, and production. His stepson, Chris Anderson,

worked with him. From 2000 to about 2008 or 2009, Western worked primarily in

the Barnett Shale area in Texas.

II. Western expands from Texas to North Dakota.

Anderson testified that in 2008 or 2009, Mitchell Brown, a lead fracking

supervisor who had worked with Anderson and Behan in the Barnett Shale,

contacted Behan and Anderson regarding work in North Dakota. At that time,

Brown was working for Brigham as a drilling and completion supervisor using

hydraulic fracturing on oil and gas wells. Brown sought assistance from Behan and

Anderson with provision of water for Brigham’s wells. Behan and Anderson

moved Western’s work to North Dakota.1

1 In North Dakota, they operated under a Master Sales/Service Contract. This contract included the following disclaimer: “Nothing in this Contract shall be 3 Western identified a water source, obtained permits, and began supplying

water to Brigham by trucks. Despite the lack of obligation, Western became the

sole provider of water for Brigham’s operations in the Rough Rider area. As Behan

and Anderson learned about the inefficiencies of overland transfer of water in

North Dakota’s climate, they conceived an idea to build an underground water

pipeline, as they had done in Texas while working in the Barnett Shale.

III. Behan and Anderson have a big idea.

In 2010, Behan and Anderson approached Brigham’s Russell Rankin with

their idea, which was novel or “revolutionary” for the time and location. Behan

then met with Rankin and others at Brigham’s office in Austin, Texas, and they

learned that Brigham planned to install a gathering system for its Rough Rider

project. Rankin told Behan that Brigham planned to truck in water for its

operations, and Behan suggested that Brigham modify its right-of-way agreements

to allow the construction of an underground freshwater pipeline beneath the pipes

needed for the oil-and-gas gathering system.

Both Behan and Brigham wanted to own the freshwater pipeline. Behan

testified that in exchange for pipeline ownership, Brigham promised Behan that it

would buy “all the water necessary to frac every well in the Rough Rider project.”

construed to obligate Operator [Brigham] to order work, equipment or materials from Provider [Western], or to obligate Provider [Western] to accept work from or furnish equipment or materials to Operator [Brigham].” 4 Behan said that, at the time, Brigham “anticipated over the next ten years, they

would frac between 450 and 500 wells.” Behan testified that Rankin said Behan’s

company would make over $50 million if Behan made the deal with Brigham.

Behan recalled that Rankin said: “Dale . . . instead of building your own pipeline,

if you will do this deal with us, you will have the best 401(k) of any individual in

the total United States.” Behan testified that he was persuaded to make the deal

with Brigham, so they hired attorneys and negotiated the details over a period of

eight months.

IV. The parties sign the Pipeline Agreement.

On June 10, 2011, Behan and Lance Langford, Brigham’s executive vice-

president, signed the Pipeline Agreement. Behan, his wife Linda, and Anderson

formed Lindale Pipeline, LLC to conduct the operations under the Pipeline

Agreement, rather than operating as Western. The Pipeline Agreement included the

following provisions relevant to this appeal:2

2 The Pipeline Agreement also included the following terms:

5. Indemnity

....

G. Consequential Damages

Notwithstanding the provisions of Section 5 (A) through (D) above, neither Party shall indemnify or hold the other liable for its consequential, indirect, or special damages. This shall include without limitation, loss of profit, loss 5 of or inability to use property and equipment or business interruption, howsoever same may be caused.

11. Term and Termination

This Agreement shall be effective as of February 1, 2011 and will remain in effect for ten (10) years. In the event of a material change of the economic conditions related to the operation of the Pipeline, this Agreement may be terminated by either Party upon thirty (30) days written notice to the other Party. This Agreement may be terminated by mutual written consent of both Parties at any time. Notwithstanding the above, if Lindale breaches any material provision hereunder, Brigham shall have the right to immediately terminate the Agreement.

13. Miscellaneous
A. Waiver

Free access — add to your briefcase to read the full text and ask questions with AI

Equinor Energy LP v. Lindale Pipeline, LLC, (Tex. Ct. App. 2023).

Equinor Energy LP v. Lindale Pipeline, LLC (Equinor Energy LP v. Lindale Pipeline, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
Ford Motor Co. v. Ridgway
135 S.W.3d 598 (Texas Supreme Court, 2004)
Baylor University v. Sonnichsen
221 S.W.3d 632 (Texas Supreme Court, 2007)
Equistar Chemicals, L.P. v. Dresser-Rand Co.
240 S.W.3d 864 (Texas Supreme Court, 2007)
Miga v. Jensen
96 S.W.3d 207 (Texas Supreme Court, 2002)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
Stewart v. Basey
245 S.W.2d 484 (Texas Supreme Court, 1952)
State Department of Highways & Public Transportation v. Payne
838 S.W.2d 235 (Texas Supreme Court, 1992)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Barry v. Jackson
309 S.W.3d 135 (Court of Appeals of Texas, 2010)
B & W SUPPLY, INC. v. Beckman
305 S.W.3d 10 (Court of Appeals of Texas, 2009)
Kroger Texas Ltd. Partnership v. Suberu
216 S.W.3d 788 (Texas Supreme Court, 2006)
Graham Central Station, Inc. v. Jesus Peña
442 S.W.3d 261 (Texas Supreme Court, 2014)
Wackenhut Corporation v. Jesse James Gutierrez
453 S.W.3d 917 (Texas Supreme Court, 2015)
Luling Oil & Gas Co. v. Humble Oil & Refining Co.
191 S.W.2d 716 (Texas Supreme Court, 1945)