Environmental Safety Consultants, Inc.

Armed Services Board of Contract Appeals·Decided July 25, 2014·No. ASBCA No. 58343·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Environmental Safety Consultants, Inc. ) ASBCA No. 58343 ) Under Contract No. N62470-95-B-2399 )

APPEARANCE FOR THE APPELLANT: Mr. Peter C. Nwogu President

APPEARANCES FOR THE GOVERNMENT: Ronald J. Borro, Esq. Navy Chief Trial Attorney Ellen M. Evans, Esq. Senior Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE FREEMAN ON THE GOVERNMENT'S MOTION TO DISMISS FOR LACK OF JURISDICTION

Environmental Safety Consultants, Inc., (ESCI) appeals the deemed denial of its termination settlement claim under the captioned contract (hereinafter "Contract 2399"). The Board, sua sponte, noted the possible lack of jurisdiction over a substantial amount of the claim and requested the parties to brief the issue. The government's brief concludes that: "the board lacks authority over the entire case," and that "the appeal should be dismissed for lack of jurisdiction." We construe this conclusion as in substance a motion to dismiss.

ESCI opposes the motion on the grounds of (i) equitable tolling of the statute of limitations and (ii) that the claim for increased costs over and above the contract price did not accrue until 12 June 2012 when the government withdrew its appeal to the Federal Circuit from the Board's 28 September 2011 decision converting the termination for default to a termination for convenience. We grant the government's motion in part.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. This appeal arises out of our decision of 28 September 2011 converting the government's termination for default of Contract 2399 to a termination for convenience of the government. See Environmental Safety Consultants, Inc., ASBCA No. 51722, 11-2 BCA if 34,848. Familiarity with that decision is assumed. 2. Contract 2399 was a firm-fixed-price construction contract. At award on 13 November 1995, the firm-fixed-price was $561,764.25 (R4, tab 1at15). 1 On 7 April 1997, ESCI submitted to the contracting officer a comprehensive proposal for an increase of$205,463.60 in the contract price for the costs of additional work and delays allegedly caused by the government (R4, tab 12 at 9).

3. In bilateral Modification No. P00006, effective 24 June 1997, the parties modified the contract deleting five items of specified work and adding nine items of additional work. The additional work items included among others:

j. Subcontract all remaining work, including supervision, quality control, and punchlist items.

k. Provide additional overhead costs incurred due to subcontracting.

m. Provide additional labor and time for entering, leaving, and working in the Q-Area.

n. Provide extended overhead for the Government delays under this contract.

(R4, tab 2 at 11-12)

4. Modification No. P00006 concluded with a summary of the agreed price adjustment and contract completion date for the additions and deletions of work and a general release as follows:

2. TOTAL AMOUNT OF ADDITIONAL WORK $199,301.00 TOTAL AMOUNT OF CREDITS $199, 192.00

The total contract price is increased by $109 .00 from $561,764.25 to $561,873.25.

The contract completion date is extended by 308 calendar days from August 26, 1996, to June 30, 1997.

The foregoing is agreed to as constituting full and equitable adjustment and compensation (both time and

1 All Rule 4 citations refer to the Rule 4 filed in ASBCA No. 51722.

2 money) attributable to the facts of [sic] circumstances giving rise to the change directed hereby, including but not limited to, any changes, differing site conditions, suspensions, delays, rescheduling, accelerations, impact, or other causes as may be associated therewith.

(R4, tab 2 at 2)

5. Modification No. P00006 was signed by Peter Nwogu on behalf ofESCI without reservations on 23 June 1997 (R4, tab 2 at 1). Also on 23 June 1997, Peter Nwogu signed ESCI's Invoice No. 7 which among other things stated that the total contract value was $561,873.25 (the amount agreed to in Modification No. P00006) (R4, tab 14 ).

6. No work was performed on the contract after 16 June 1997. Environmental Safety Consultants, 11-2 BCA ~ 34,848 at 171,430, finding 19. On 12 June 1998, the contract was completely terminated for default for failure to make progress to ensure completion of the work and failure to perform the work within the specified time (R4, tab 2 at 13). There were no contract modifications increasing the contract price after Modification No. P00006. At termination, the contract price was the price agreed to by the parties in Modification No. P00006 ($561,873.25). Over the course of the contract, the government paid ESCI a total amount of $303,990.00 in progress payments (R4, tab 13 at 1, tab 14 at 1).

7. Pursuant to paragraph (c) of the FAR 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984) clause of the contract, and as a result of our decision sustaining the appeal from the default termination, "the rights and obligations of the parties will be the same as if the termination had been issued for the convenience of the Government" (R4, tab I at 69).

8. The 52.249-2, TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR 1984}-ALTERNATE I clause in Contract 2399 stated in pertinent part:

( d) After termination the Contractor shall submit a final termination settlement proposal to the Contracting Officer in the form and with the certification prescribed by the Contracting Officer ....

(e) Subject to paragraph (d) above, the Contractor and the Contracting Officer may agree upon the whole or any part of the amount to be paid because of the termination .... However, the agreed amount, whether

3 under this paragraph (e) or paragraph (t) below, exclusive of costs shown in subparagraph (t)(3) below, [ZJ may not exceed the total contract price as reduced by ( 1) the amount of payments previously made and (2) the contract price of work not terminated ....

( t) If the Contractor and Contracting Officer fail to agree on the whole amount to be paid the Contractor because of the termination of work, the Contracting Officer shall pay the Contractor the amounts determined as follows, but without duplication of any amounts agreed upon under paragraph (e) above:

( 1) For contract work performed before the effective date of termination, the total (without duplication of any item) of-

(i) The cost of this work;

(ii) The cost of settling and paying termination settlement proposals under terminated subcontracts that are properly chargeable to the terminated portion of the contract if not included in subdivision (i) above; and

(iii) A sum, as profit on (i) above, determined by the Contracting Officer under 49 .202 of the Federal Acquisition Regulation, in effect on the date of this contract, to be fair and reasonable, however, if it appears that the Contractor would have sustained a loss on the entire contract had it been completed, the Contracting Officer shall allow no profit under this subdivision (iii) and shall reduce the settlement to reflect the indicated rate of loss.

(2) The reasonable costs of settlement of the work terminated, including-

2 There is no subparagraph ( t)(3) in the Alternate I clause, but the same provisions that are in subparagraph (t)(3) of the basic clause are in subparagraph (t)(2) of the Alternate I clause.

4 (i) Accounting, legal, clerical, and other expenses reasonably necessary for the preparation of termination settlement proposals and supporting data;

(ii) The termination and settlement of subcontracts (excluding the amounts of such settlements); and

(iii) Storage, transportation, and other costs incurred, reasonably necessary for the preservation, protection or disposition of the termination inventory.

9.

Free access — add to your briefcase to read the full text and ask questions with AI

Environmental Safety Consultants, Inc., (asbca 2014).

Environmental Safety Consultants, Inc. (Environmental Safety Consultants, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Arctic Slope Native Association, Ltd. v. Sebelius
699 F.3d 1289 (Federal Circuit, 2012)