Environmental Safety Consultants, Inc.

Armed Services Board of Contract Appeals·Decided August 13, 2014·No. ASBCA No. 58343·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Environmental Safety Consultants, Inc. ) ASBCA No. 58343 ) Under Contract No. N62470-95-B-2399 )

APPEARANCE FOR THE APPELLANT: Mr. Peter C. Nwogu President

APPEARANCES FOR THE GOVERNMENT: Ronald J. Borro, Esq. Navy Chief Trial Attorney Ellen M. Evans, Esq. Senior Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE FREEMAN ON APPELLANT'S MOTION FOR PARTIAL SUMMARY JUDGMENT

Environmental Safety Consultants, Inc. (ESCI) moves for partial summary judgment on its appeal of the contracting officer's deemed denial of its termination for convenience settlement claim under the captioned contract. ESCI contends that there is no genuine issue of material fact that it is entitled to immediate payment of (i) $68,230.50 for "work that was completed and accepted at contract price," and (ii) $199,950.00 for "settled constructive changes, extensive delays and overheads" (mot. at 1-2). The government opposes on the grounds that there is no legal authority under the termination for convenience clause for recovery of "selected prices in the last invoice and the last modification issued before the termination" (opp'n at 1). We agree with the government and deny the motion.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. This appeal arises out of our decision converting the government's termination of the captioned contract (hereinafter "Contract 2399") for default to a termination for the government's convenience. Environmental Safety Consultants, Inc., ASBCA No. 51722, 11-2 BCA i! 34,848. 1 We have also addressed, more recently, a jurisdictional issue with respect to the total amount ofESCI's termination settlement claim. Environmental Safety Consultants, Inc., ASBCA No. 58343, slip op. (25 July 2014). Familiarity with these decisions is assumed.

1 All Rule 4 citations refer to the Rule 4 filed in ASBCA No. 51722. 2. Pursuant to paragraph (c) of the FAR 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984) clause of the contract, and as a result of our decision sustaining the appeal from the default termination, "the rights and obligations of the parties will be the same as ifthe termination had been issued for the convenience of the Government" (R4, tab 1 at 69).

3. The FAR 52.249-2, TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR 1984)-ALTERNATE I clause in Contract 2399 states in pertinent part:

(d) After termination, the Contractor shall submit a final termination settlement proposal to the Contracting Officer in the form and with the certification prescribed by the Contracting Officer ....

(e) Subject to paragraph (d) above, the Contractor and the Contracting Officer may agree upon the whole or any part of the amount to be paid because of the termination .... However, the agreed amount, whether under this paragraph (e) or paragraph (t) below, exclusive of costs shown in subparagraph (t)(3) below, may not exceed the total contract price as reduced by ( 1) the amount of payments previously made and (2) the contract price of work not terminated ....

(t) If the Contractor and Contracting Officer fail to agree on the amount to be paid the Contractor because of the termination of work, the Contracting Officer shall pay the Contractor the amounts determined as follows, but without duplication of any amounts agreed upon under paragraph (e) above:

( 1) For work performed before the effective date of termination, the total (without duplication of any items) of-

(i) The cost of this work;

(ii) The cost of settling and paying termination settlement proposals under terminated subcontracts that are properly chargeable to the terminated portion of the contract, if not included in subdivision ( i) above; and

2 (iii) A sum, as profit on (i) above, determined by the Contracting Officer under 49.202 of the Federal Acquisition Regulation, in effect on the date of this contract, to be fair and reasonable; however, if it appears that the Contractor would have sustained a loss on the entire contract had it been completed, the Contracting Officer shall allow no profit under this subdivision (iii) and shall reduce the settlement to reflect the indicated rate of loss.

4. On 5 July 2012, ESCI submitted its termination settlement proposal to the contracting officer for a "net proposed settlement" of$1,183,366.59. On 14 September 2012, it submitted that proposal to the contracting officer as a certified claim under the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101-7109 (app. supp. R4, vol. I, tab 3 at 1-4, tab 5 at 1-2). The contracting officer refused to either negotiate a settlement or issue a final decision on the termination settlement claim (answer ii 8). On 29 September 2012, ESCI appealed the deemed denial of the claim. The appeal was docketed as ASBCA No. 58343.

5. ESCI's motion for partial summary judgment on its termination settlement claim has two parts. First, it claims that:

[T]here are no genuine issues of material fact as to whether appellant is entitled to payment of the amount of $68,230.50. This amount represents the compensation for completed, verified and accepted work at contract price before government's termination on June 12, 1998. This amount for payment is presented in Table 1.0 - Compensation for completed, verified and accepted by the Government on June 24, 1997 ....

(Mot. at 1)

6. Table 1 is a listing of the progress payment estimates in Invoice No. 7 for some, but not all, of the items of work, required to perform Bid Item OOOlA (mot. at 20-23; R4, tab 14 at 3-16). 2 Bid Item OOOlA was a $358,754 lump sum fixed-price

2 Invoice No. 7 for a total progress payment of $138,506.50 was returned to ESCI unpaid by the contracting officer in June 1997 on the ground that it contained an "invalid" certification. ESCI did not thereafter submit a timely CDA claim for payment of the invoice. See Environmental Safety Consultants, Inc., ASBCA No. 58847, 14-1BCAii35,510, and ASBCA No. 54615, 07-1 BCA ii 33,483 at 165,984. 3 item for ''the entire work, complete in accordance with the drawings and specifications, but excluding work described in Bid Items OOOlB, OOOlC, OOOlD, OOOlE and OOOlF." As of the date the contract was terminated (12 June 1998), Bid Item OOOlA had not been completed. The work items in Table 1 ofESCI's motion were part of the Bid Item OOOlA work, but none of those items were separately priced in the contract Schedule. (R4, tab 1 at 16, 29-30)

7. The progress payment estimates for the work items in Invoice No. 7 and in Table 1 ofESCI's motion are not based on the actual incurred costs of performing the work item. They are based on portions of the Bid Item price assigned to the work item by the contractor after award of the contract pursuant to paragraph (b) of the FAR 52.232-5, PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (APR 1989) clause of the contract. (R4, tab 1 at 68, 70) Paragraph (b) states in pertinent part:

The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished .... The Contractor shall furnish a breakdown of the total contract price showing the amount included therein for each principal category of the work, which shall substantiate the payment amount requested in order to provide a basis for determining progress payments.

(R4, tab 1 at 70)

8. Progress payments under paragraph (b) are not final payments accepting the work for which they are paid.

Free access — add to your briefcase to read the full text and ask questions with AI

Environmental Safety Consultants, Inc., (asbca 2014).

Environmental Safety Consultants, Inc. (Environmental Safety Consultants, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

§ 7101-7109
41 U.S.C. § 7101-7109
§ 7101
41 U.S.C. § 7101