Environmental Safety Consultants, Inc.

CourtArmed Services Board of Contract Appeals
DecidedMarch 2, 2015
DocketASBCA No. 58343
StatusPublished

This text of Environmental Safety Consultants, Inc. (Environmental Safety Consultants, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Safety Consultants, Inc., (asbca 2015).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Environmental Safety Consultants, Inc. ) ASBCA No. 58343 ) Under Contract No. N62470-95-B-2399 )

APPEARANCE FOR THE APPELLANT: Mr. Peter C. Nwogu President

APPEARANCES FOR THE GOVERNMENT: Ronald J. Borro, Esq. Navy Chief Trial Attorney Ellen M. Evans, Esq. Senior Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE FREEMAN

Environmental Safety Consultants, Inc. (ESCI), appeals the deemed denial of its settlement proposal/claim for the government's convenience termination of the captioned contract (hereinafter "Contract 2399"). The government contends that ESCI' s claim is not based on its actual incurred costs but on prices, and that it has not proven its actual incurred costs as required by the termination clause of the contract. ESCI responds in pertinent part 1 that (i) the convenience termination did not convert the firm-fixed-price contract into a cost-reimbursement contract, and (ii) the contract changes and costs that were incurred for each of the six Bid Items were negotiated and settled and are not subject to further actual cost determination. We find no merit in appellant's argument. We find that the incurred costs of the terminated work with a reasonable profit thereon are less than the progress payments made by the government, and that the settlement expenses have not been proven in any amount. Accordingly, we deny the appeal.

1 We say in pertinent part because most of ESCI' s brief is devoted to its claims for contract time and price adjustments and for breach of contract damages that were not submitted to the contracting officer for decision within six years of accrual as required by the Contract Disputes Act of 1978 (CDA), 41 U.S.C. § 7103(a)(l) and (4)(A), or otherwise were settled by mutual agreement in bilateral Modification No. P00006 to the contract. See Environmental Safety Consultants, Inc., ASBCA No. 58343, 14-1 BCA if 35,681, and finding 3 below. FINDINGS OF FACT

A. Submission of the Termination for Convenience Settlement Claim to the Contracting Officer

1. Contract 2399 was awarded to ESCI on 13 November 1995. The contract required ESCI to remove old and install new underground and above ground fuel storage tanks at the Naval Weapons Station (NWS), Yorktown, Virginia. The total contract price at award was $561,764.25. The specified contract completion date was 16 August 1996. The contract schedule consisted of six priced "Bid Items." Bid Item OOOIA was a firm-fixed-price item in the amount of $358,754 for "the entire work, complete in accordance with the drawings and specifications, but excluding work described in Bid Items OOOIB, OOOIC, OOOID, OOOIE and OOOIF." The Bid Items excluded from the work under Bid Item 000 IA were unit priced items per gallon for removal and disposal of specified quantities of fuel (OOOIB), sludge material (OOOIC), and water contaminated petroleum (OOOID), and per cubic yard for specified quantities of petroleum contaminated soil (OOOIE and OOOIF). (R4, tab I at 15, 16, 29)2

2. ESCI began work on the site on 2 April 1996 and performed the work with its own personnel until I 0 October 1996. At that time ESCI had missed the specified completion date and to avoid a termination for default, it agreed to subcontract the entire completion of the work to a competent subcontractor. From November 1996 to 16 June 1997, Rickmond Environmental, Inc., performed the contract work as a subcontractor to ESCI. Rickmond stopped performance after 16 June 1997 because ESCI failed to pay Rickmond invoices in the amount of $114,239.60. See Environmental Safety Consultants, Inc., ASBCA No. 51722, 11-2 BCA i! 34,848 at 171,429-30, findings 12-19.

3. On 24 June 1997, ESCI and the government, in bilateral Modification No. P00006, agreed to the following changes to the contract:

1. The contractor shall provide all materials, labor, and equipment to accomplish the following:

PC0-01:

a. Delete Bid Item OOOlB, fuel removal.

b. Provide 36,210 gallons of fuel removed.

c. Delete Bid Item OOOlE, contaminated soil removal

2 All Rule 4 citations refer to the Rule 4 filed in ASBCA No. 51722. 2 <500 ppm.

d. Delete Bid Item 0001 F, contaminated soil removal >500 ppm.

e. Provide 1,000 CY of contaminated soil removal.

f. Remove a 120-gallon UST and demolish the existing washrack at Building 1828.

g. Delete the removal of Tank No. 714.1, as shown on NAVFAC Drawing #4307235.

h. Delete the installation of Tank No. 709.6, as shown on NA VFAC Drawing #4307235.

1. Provide the in-place closure of three (3) US Ts, Tank Nos. 719, 1828, and 2006.

J. Subcontract all remaining work, including supervision, quality control, and punchlist items.

k. Provide additional overhead costs incurred due to subcontracting.

I. Remove an 8,000-gallon UST, Tank No. 457.2, as shown on NA VF AC Drawing #4307231.

m. Provide additional labor and time for entering, leaving, and working in the Q-Area.

n. Provide extended overhead for the Government delays under this contract.

2. TOTAL AMOUNT OF ADDITIONAL WORK $199,301.00

TOTAL AMOUNT OF CREDITS $199,192.00

The total contract price is increased by $109.00 from $561,764.25 to $561,873.25.

3 The contract completion date is extended 308 calendar days from August 26, 1996, to June 30, 1997.

The foregoing is agreed to as constituting full and equitable adjustment and compensation (both time and money) attributable to the facts of [sic] circumstances giving rise to the change directed hereby, including, but not limited to, any changes, differing site conditions, suspensions, delays, rescheduling, accelerations, impact, or other causes as may be associated therewith.

(R4, tab 2 at 11-12)

4. No work on the contract was performed after 16 June 1997. After 12 months of fruitless negotiation with ESCI to restart and complete the work, the government on 12 June 1998 terminated Contract 2399 "completely" for default (R4, tab 2 at 13). At termination, none of the Bid Items on the Contract Schedule had been completed and accepted for final payment by the government (R4, tab 14 at 17). On 26 August 1998, ESCI appealed the default termination to this Board. That appeal was docketed as ASBCA No. 51722. On 28 September 2011, the Board sustained the appeal. Pursuant to paragraph (c) of the FAR 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984) clause of the contract, this decision converted the default termination to a termination for convenience of the government. See Environmental Safety Consultants, 11-2 BCA ~ 34,848 at 171,433. Familiarity with that decision is presumed.

5. The FAR 52.249-2, TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR 1984)-ALTERNATE I (APR 1984) clause of Contract 2399 stated in pertinent part:

( d) After termination, the Contractor shall submit a final termination settlement proposal to the Contracting Officer in the form and with the certification prescribed by the Contracting Officer ....

(e) Subject to paragraph (d) above, the Contractor and the Contracting Officer may agree upon the whole or any part of the amount to be paid because of the termination. The amount may include a reasonable allowance for profit on work done. However, the agreed amount, whether under this paragraph (e) or paragraph ( t) below, exclusive of costs shown in subparagraph (f)(3) below, may not exceed the total contract price as reduced by ( 1) the amount of payments previously made and (2) the

4 contract price of work not terminated. The contract shall be amended, and the Contractor paid the agreed amount.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
Environmental Safety Consultants, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-safety-consultants-inc-asbca-2015.