Environmental Protection Information Center v. Pacific Lumber Co.

301 F. Supp. 2d 1102, 58 ERC (BNA) 1523, 2004 U.S. Dist. LEXIS 803, 2004 WL 180413
CourtDistrict Court, N.D. California
DecidedJanuary 23, 2004
DocketC 01-2821 MHP
StatusPublished
Cited by2 cases

This text of 301 F. Supp. 2d 1102 (Environmental Protection Information Center v. Pacific Lumber Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Protection Information Center v. Pacific Lumber Co., 301 F. Supp. 2d 1102, 58 ERC (BNA) 1523, 2004 U.S. Dist. LEXIS 803, 2004 WL 180413 (N.D. Cal. 2004).

Opinion

Order Motion to Dismiss

PATEL, Chief Judge.

On July 24, 2001, plaintiff Environmental Protection Information Center (“EPIC”), a non-profit environmental organization, brought a citizen-suit action under section 505(a) of the Clean Water Act (“CWA”), 33 U.S.C. § 1365(a), against Pacific Lumber Company and Scotia Pacific Lumber Company (collectively “PALCO”), the Environmental Protection Agency (“EPA”), and Christine Todd Whitman as EPA Administrator. 1 EPIC’s complaint alleges that PALCO violated the CWA, the Porter-Cologne Act, and California’s Unfair Competition Law, Cal. Bus & Prof. Code § 17200 et seq., when it discharged pollutants without a CWA permit. For these alleged violations, EPIC seeks declaratory and injunctive relief, civil remedies, and restitution.

On August 16, 2001, the court denied EPIC’s motion for a temporary restraining order. PALCO and' EPA subsequently filed separate motions to dismiss the action, and EPIC, in response,- filed an amended complaint on September 24, 2001, adding a third claim challenging the non-point source provision of the relevant regulation. On June 6, 2003, the court denied EPA’s motion to dismiss and denied PAL-CO’s motion to dismiss in part, concluding that EPIC could pursue a claim under the Administrative Procedures Act (“APA”) in this court and that EPIC’s claim was not time-barred. On October 13, 2003, the court denied EPIC’s motion for summary judgment on its third claim for relief, granting PALCO’s and EPA’s cross-motions and construing the relevant EPA regulation in a manner consistent with germane federal law.

Now before the court is PALCO’s motion to dismiss EPIC’s remaining claims under Federal Rule of Civil Procedure 12(b)(6). The court has considered the parties’ arguments fully, and for the reasons set forth below, the court rules as follows.

BACKGROUND 2

In its opinion of October 14, 2003, the court set forth in significant detail the *1104 factual and procedural histories of this action. To give context and shape to the court’s consideration of PALCO’s motion to dismiss, the court repeats much of this background here.

I. Underlying Facts

At the. heart of this litigation is Bear Creek, a brook situated several miles upstream of Scotia, California. A tributary of the Eel River, Bear Creek creates a watershed that covers 5500 acres of land throughout Humboldt County, California. Pacific Lumber Company and its wholly owned subsidiary, defendant Scotia Pacific Lumber Company, own some ninety-five percent of the land in the Bear Creek watershed, much of which PALCO uses for logging. 3

According to EPIC, substantial logging activity in the watershed area — primarily that performed by PALCO — has spurred a dramatic increase in the amount of sediment deposited into Bear Creek. Before significant logging began, EPIC claims, Bear Creek’s sediment deposit peaked at approximately 8,000 tons per year; after logging practices commenced, sediment deposit climbed to 27,000 tons per year. This sediment increase, EPIC alleges, has a specific source: PALCO’s timber harvesting and construction of unpaved roads. According to EPIC, PALCO’s logging activity creates a deleterious environmental process. First, EPIC notes, timber harvesting removes vegetation from the ground surface, making soil more susceptible to erosion and landslides; construction of unpaved roads then exposes more soil, which, in turn, further destabilizes slopes. The effect of timber harvesting and road construction, EPIC contends, is to expose far more destabilized soil than is environmentally sustainable. When it rains, EPIC explains, the rain water carries the exposed silts and sediments — as well as other pollutants, like pesticides and diesel fuel — into culverts, ditches, erosion gullies, and other alleged channels. From these various water channels, silts, sediments, and pollutants flow directly into Bear Creek.

According to an April 1998 study conducted by PALCO consultants, sediments and pollutants pile into Bear Creek and its tributaries at no fewer than 179 specific watershed points. Among other channels, pollutant-laden water flows through 156 hillside culverts and 5.5 miles of roadside ditches, all of which drain directly into stream-crossing culverts. The consequences of this system, EPIC contends, are predictable and environmentally adverse: Beneficial uses of Bear Creek are substantially diminished; e.g., fish are significantly less able — if able at all- — -to use the creek as a nesting and rearing habitat. Worse still, EPIC adds, PALCO’s present and future timber harvest plans promise the construction of additional roads and the digging of additional culverts, all of which could increase the amount of sediment, silt, and other pollutants deposited into Bear Creek. PALCO neither holds nor has applied for any relevant permits for these sites, sites EPIC contends should be regulated as “point sources” under the CWA.

II. Statutory and Regulatory Background

With the goal of “restorfing] and main-tainting] the chemical, physical, and biological integrity of the Nation’s waters,” Congress enacted the CWA in 1972. 33 U.S.C. § 1251(a) (originally codified as the Federal Water Pollution Control Act, 62 Stat. 1155); see Association to Protect Hammersley v. Taylor Res., Inc., 299 F.3d *1105 1007, 1016 (9th Cir.2002) (noting that, in 1972, “Congress passed the Clean Water Act amendments, 33 U.S.C. §§ 1251-1387, to respond to environmental degradation of the nation’s waters”); Pronsolino v. Nastri, 291 F.3d 1123, 1126 (9th Cir.2002) (observing that prior federal water pollution regulation “had proven ineffective”). Built on a “fundamental premise” that the unauthorized “discharge of any pollutant by any person shall be unlawful,” Natural Resources Defense Council (“NRDC”) v. EPA 822 F.2d 104, 109 (D.C.Cir.1987) (citing 33 U.S.C. § 1311(a)), the CWA “establishes a comprehensive statutory system for controlling water pollution.” Association to Protect Hammersley, 299 F.3d at 1009 (citation and internal quotation marks omitted). This broad statutory scheme includes, inter alia, a National Pollutant Discharge Elimination System (“NPDES”) for regulation of pollutant discharges into the waters of the United States. See 33 U.S.C. §§ 1311(a), 1342(a). Under the NPDES, permits may be issued by EPA or by States that have been authorized by EPA to act as NPDES permitting authorities. See 33 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conservation Law Foundation v. Hannaford Bros. Co.
327 F. Supp. 2d 325 (D. Vermont, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
301 F. Supp. 2d 1102, 58 ERC (BNA) 1523, 2004 U.S. Dist. LEXIS 803, 2004 WL 180413, Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-protection-information-center-v-pacific-lumber-co-cand-2004.