Driscoll v. Adams

181 F.3d 1285, 29 Envtl. L. Rep. (Envtl. Law Inst.) 21387, 48 ERC (BNA) 2093, 1999 U.S. App. LEXIS 16931, 1999 WL 528208
Court of Appeals for the Eleventh Circuit·Decided July 23, 1999·No. 98-8532·Published·Cited by 28 cases

Opinion

CARNES, Circuit Judge:

Plaintiffs David and Barbara Driscoll and Ruel and Patricia Galbreath appeal the district court’s award of summary judgment to • defendant Ross Adams on their Clean Water Act claim, which arose out of Adams’ discharge of allegedly polluted stormwater into a stream running from his property to ponds on their properties. Adams argues that the district court was correct in concluding that he is not subject to liability under the Clean Water Act because the Act imposed an impossible condition by requiring him to obtain a discharge permit that was unavailable in the state of Georgia. He also maintains that his discharge falls outside the scope of the Act,because it was not a point source discharge of a pollutant into a navigable water as defined by the Act. We reject both of those arguments and reverse the district court’s grant of summary judgment for Adams.

I. FACTS AND PROCEDURAL HISTORY

At all times relevant to this case, Adams owned 76 acres of land in the North Georgia mountains. David and Barbara Dris-coll owned approximately five acres adjacent to Adams’ property, and Ruel and *1287 Patricia Galbreath owned about two acres adjacent to the Driscolls’ property. The Spiva Branch stream flows downhill from Adams’ property through a pond on the Driscolls’ property and then through another pond on the Galbreaths’ property, before merging with the Nottely River, which flows across the Georgia-Tennessee border and unites with the Tennessee River. The Driscolls and Galbreaths claim in their complaint, and the magistrate judge found, that stormwater washed mud, silt, sand, and other materials from Adams’ property into the Spiva Branch stream and thence into the plaintiffs’ two ponds while Adams was harvesting timber and developing his property.

Adams harvested timber on his property from March 1995 to November 1995. During the harvest, he cut and graded roads, installed storm pipes, and cut and removed timber. Adams then proceeded to develop the property, putting gravel on the roads, building culverts and check dams to channel the stormwater runoff, and dividing the property into residential lots for vacation homes. The harvest and development caused erosion of mud, sand, and other materials on his property. Adams concedes that he did little to stabilize his property or prevent erosion until the spring of 1996, after the erosion had already caused a considerable amount of damage to the plaintiffs’ properties. He says his delay in taking preventive measures was the result of inclement weather and winter cold.

Adams failed to seek the proper approval from any federal, state, or local government agency before starting to work on his property. After all of the timber harvest and much of the development were already completed, he filed for the required state permit in September 1996. He did not obtain a county development permit until February 1997, two months after the filing of the complaint in this lawsuit. As for federal law requirements, Adams never obtained a National Pollutant Discharge Elimination System (“NPDES”) permit, which is required for lawful pollutant discharge under the Clean Water Act. The parties agree that an NPDES general stormwater permit was not available because of a legal challenge to the permit. The plaintiffs contend, however, that other NPDES permits were available, including an individual stormwater permit and both general and individual point source discharge permits.

The plaintiffs filed this lawsuit in December 1996 against Adams for violations of the Clean Water Act, 33 U.S.C. §§ 1251-1376 (1994), pursuant to its citizen suit provision, 33 U.S.C. § 1365. They also included in their complaint pendent state law claims for nuisance, trespass, and negligence, among other things. They filed a motion for summary judgment, and Adams filed a motion to dismiss, which the district court treated as a cross motion for summary judgment. The court denied the plaintiffs’ motion and granted Adams’, stating that . the requirement of an “NPDES permit was an impossible condition ... [and][t]here were no approved federal standards for how much sand, silt and mud could be in the released water.” After disposing of the federal law claim, the court declined to retain supplemental jurisdiction over the state law claims and dismissed them without reaching the merits. The plaintiffs appealed.

We review de novo the district court’s award of summary judgment. See B.R.L. Equip. Rentals Ltd. v. Seabring Marine Indus., Inc., 168 F.3d 413, 415 (11th Cir.1999). We also review de novo the district court’s conclusions of law. See Brooks v. Miller, 158 F.3d 1230, 1236 (11th Cir.1998).

II. DISCUSSION

Adams raises essentially two issues on appeal. First, he argues that the Clean Water Act’s prohibition on pollutant discharge does not apply where the NPDES permit required to make the discharge lawful under the Act is not available. Second, he contends that his discharges in this case did not fall within the scope of prohib *1288 ited pollutant discharges- under the Act. We will address each contention in turn.

A. DOES THE CLEAN WATER ACT’S PROHIBITION ON “THE DISCHARGE OF ANY POLLUTANT BY ANY PERSON” APPLY WHERE THE NPDES PERMIT REQUIRED FOR LAWFUL DISCHARGE IS NOT AVAILABLE?

The Clean Water Act provides, “Except as in compliance with this section and sections 1312,1316, 1317,1328,1342, and 1344 of this title, the discharge of any pollutant by any person shall be unlawful.” 33 U.S.C. § 1311(a). Of the excepted sections, the only one potentially applicable in this case is § 1342, which establishes the National Pollutant Discharge Elimination System and authorizes the Administrator of the EPA to issue permits under this system that allow the permit holder to discharge limited quantities of pollutants under prescribed conditions. See 33 U.S.C. § 1342(a)(1). If the Administrator approves a state’s permit program, the state may assume control of NPDES permitting for that jurisdiction: See 33 U.S.C. § 1342(b).

Georgia has an approved state NPDES permit program. Pursuant to that program, the Georgia Environmental Protection Division (“EPD”) has attempted several times over the past few years to issue a general NPDES stormwater discharge permit. Unlike an individual permit, which would apply to an individual dischar-ger, the general permit would apply to an entire class of dischargers. To obtain coverage under a general permit, a would-be discharger could file a Notice of Intent form with the EPD.

Free access — add to your briefcase to read the full text and ask questions with AI

Driscoll v. Adams, 181 F.3d 1285, 29 Envtl. L. Rep. (Envtl. Law Inst.) 21387, 48 ERC (BNA) 2093, 1999 U.S. App. LEXIS 16931, 1999 WL 528208 (11th Cir. 1999).

181 F.3d 1285 (Driscoll v. Adams) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ben Porto & Son, LTC v. Montgomery Cnty.
Court of Special Appeals of Maryland, 2024
GUNN v. META PLATFORMS INC
M.D. Georgia, 2023
Black Warrior River-Keeper, Inc. v. Drummond Co.
387 F. Supp. 3d 1271 (N.D. Alabama, 2019)
Flint Riverkeeper, Inc. v. Southern Mills, Inc.
276 F. Supp. 3d 1359 (M.D. Georgia, 2017)
United States v. HVI Cat Canyon, Inc.
213 F. Supp. 3d 1249 (C.D. California, 2016)
John W. Mrosek v. City of Peachtree City
631 F. App'x 757 (Eleventh Circuit, 2015)
United States v. Ortiz
427 F.3d 1278 (Tenth Circuit, 2005)
Quebell P. Parker v. Scrap Metal Processors
386 F.3d 993 (Eleventh Circuit, 2004)
United States v. Emilio A. Perez
366 F.3d 1178 (Eleventh Circuit, 2004)
Environmental Protection Information Center v. Pacific Lumber Co.
301 F. Supp. 2d 1102 (N.D. California, 2004)
North Carolina Shellfish Growers Ass'n v. Holly Ridge Associates, LLC
278 F. Supp. 2d 654 (E.D. North Carolina, 2003)
Carabell v. United States Army Corps of Engineers
257 F. Supp. 2d 917 (E.D. Michigan, 2003)
Mississippi River Revival, Inc. v. City of Minneapolis
319 F.3d 1013 (Eighth Circuit, 2003)
United States v. Buday
138 F. Supp. 2d 1282 (D. Montana, 2001)
Headwaters, Inc. v. Talent Irrigation District
243 F.3d 526 (Ninth Circuit, 2001)