Environmental Dimensions, Inc. v. EnergySolutions Government Group, Inc.

District Court, D. New Mexico·Decided March 18, 2021·No. 1:16-cv-01056·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF NEW MEXICO ______________________

ENVIRONMENTAL DIMENSIONS, INC.,

Plaintiff, v. No. 1:16-cv-1056-KWR-JHR

ENERGYSOLUTIONS GOVERNMENT GROUP, INC. (n/k/a Atkins Energy Government Group, Inc.),

Defendant.

MEMORANDUM OPINION AND ORDER GRANTING IN PART AND DENYING IN PART DEFENDANT’S MOTION FOR ATTORNEYS’ FEES

THIS MATTER comes before the Court upon Defendant’s Motion for Attorneys’ Fees, filed December 23, 2020 (Doc. 214). Having considered the parties’ briefs and the applicable law, the Court finds that Defendant’s motion is well-taken in part, and will be granted with respect to its counterclaim for attorneys’ fees related to an open account/account stated, and denied with respect to fees related to “defending a ‘groundless’ claim under the New Mexico Unfair Practices Act” and for “for All of the Claims and Counterclaims in This Lawsuit.” Id. at 1, 10. BACKGROUND

The claims arise from a dispute involving a nuclear waste remediation project the parties worked on together at Los Alamos National Lab (“LANL”). The facts of the case are set out in detail in several Memorandum and Opinion Orders and need not be repeated in their entirety here. See Docs. 167, 168, 188, 196, 202, and 215. Briefly, Defendant, a subcontractor of Plaintiff’s, carried out work authorized by Plaintiff, after which Defendant submitted six invoices dating from March 10 - August 11, 2015 amounting to $1,041,531.74,1 for which it was not paid, although Plaintiff submitted invoices to Los Alamos National Security, LLC (LANS) for the same work and received payment. Plaintiff’s Claim under the New Mexico Unfair Trade Practices Act Defendant’s LANS Contract: Master Task Order 10

Defendant provides nuclear waste remediation and personnel support. In 2009, two years before contracting with Plaintiff, Defendant worked as prime contractor with LANS on a transuranic waste remediation project designated as Master Task Order 10. The project was completed on June 30, 2014. Plaintiff was not a party to that agreement. On February 14, 2014, an incident occurred at the Carlsbad Waste Isolation Pilot Plant facility when an improperly packaged waste drum, packaged by Defendant at LANL, underwent an exothermic reaction and burst, causing a radiological release (“WIPP incident”). The DOE Accident Investigation Board (AIB) investigated the incident and issued a report on April 15, 2015. The report pinpointed twelve contributing factors leading to the accident, including, among other things, LANS’ failure to

adhere to certain controls implemented by the relevant field office, LANL’s failure to develop appropriate packaging and treatment procedures, and failure of LANS, Defendant, and the Los Alamos field office to ensure a strong enough safety culture. The report stated that Defendant’s actions were possible contributing factors to the accident but stated that none of the contributing factors individually caused the accident.2 Master Task Order Agreement No. 2

1 Defendant’s invoices originally amounted to $1,057,354.63, however, invoice 41537, which Defendant invoiced for $281,011.44, was only approved for $265,188.55, thereby resulting in an outstanding balance of $1,041,531.74. Doc. 206 at 5, fn 4. 2 The Report provides “Contributing Causes: Events or conditions that collectively with other causes increased the likelihood or severity of an accident but that individually did not cause the accident.” (Doc. 111 Ex. 1 Page 4). Unrelated to Defendant’s Master Task Order 10 project, on July 12, 2011, in pursuit of qualification to bid on a LANL contract for small businesses, denominated as Master Task Order Agreement No. 2 (“MTOA2”), Plaintiff executed a Teaming Agreement with Defendant, specifying the duties and responsibilities of the parties should the bid be accepted. The Agreement included that, “[e]xcept as expressly provided … all rights and obligations of the parties under this

Agreement shall terminate on the earliest of the following: … e. Execution by both parties of the subcontract contemplated by this Agreement.” (Doc. 99 Ex. G). In February 2012, Plaintiff was qualified as a potential contractor, but no work was assigned at the time. The LANS’ MTOA2 agreement with Plaintiff provided that “Contractor [LANS] may, at any time, without notice to the sureties if any, by written Change Notice unilaterally direct additions, deletions or changes . . . to all or any part of the Work and Subcontractor agrees to perform such work as changed.” (SOF 7). After its successful qualification, Plaintiff subcontracted with Defendant and two other companies to carry out assigned work. Plaintiff executed the subcontract with Defendant in

August 2013. On April 16, 2014, LANS awarded Plaintiff work under MTOA2 Task Order 1, with a maximum potential allocation of $23,349,876.42. LANS retained the right to modify this amount. LANS incrementally released funds for the project to Plaintiff amounting to $4,839,421.76. Work began on the project in July 2014. Plaintiff’s employees, project manager Chris Edgmon (“Edgmon”) and COO/VP of business development John Rodell (“Rodell”)3 were tasked with coordinating the work. Edgmon was responsible for managing the project on a day-to-day basis by scheduling work, budgeting, and approving invoices submitted by the subcontractors, which in turn were submitted to Rodell

3 It is unclear what Rodell’s exact title is, but the record reflects that Edgmon deferred to him and he made final decisions regarding the project on a day-to-day basis. for review and approval. Bradshaw had little involvement in the day-to-day operations of the project, and most decisions were largely left to Edgmon and Rodell. Defendant took on a larger role than the other subcontractors in performance of the work, consequently billing for a larger share than the other subcontractors. It is undisputed that Defendant only carried out work authorized by Plaintiff; that Defendant submitted six invoices

dating from March 10 - August 11, 2015 amounting to $1,041,531.74, for which it was not paid; and that Plaintiff submitted invoices to LANS for the same work and received payment. On May 12, 2015, Bradshaw sent a letter of cure to Defendant stating Defendant was not in compliance with the terms of the Teaming Agreement and that “[i]n spite of repeated attempts by EDi to realign the staffing to meet the TA [Teaming Agreement] goals, EnergySolutions continued refusal has forced us to take action… [i]f this matter is not resolved by Friday May 15, 2015, any work [going forward] performed by EnergySolutions above and beyond 35% is done so solely at EnergySolutions’ risk.” (Doc. 111 Ex. 2). After Bradshaw’s letter, Plaintiff continued to assign work to Defendant, which it performed until LANS terminated the underlying Task Order by letter

on May 27, 2015, stating that “[t]he TRU waste program has reduced the scope and budget for SSR activities this fiscal year and for the next two fiscal years. As a result, the current and long term scope included in EDi’s Task Order 275074 will be removed in full with the exception of the warehousing leasing applicable to this removed scope of work.” (SOF 16).

Free access — add to your briefcase to read the full text and ask questions with AI

Environmental Dimensions, Inc. v. EnergySolutions Government Group, Inc., (D.N.M. 2021).

Environmental Dimensions, Inc. v. EnergySolutions Government Group, Inc. (Environmental Dimensions, Inc. v. EnergySolutions Government Group, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Exxon Mobil Corp. v. Saudi Basic Industries Corp.
544 U.S. 280 (Supreme Court, 2005)
Bear v. Patton
451 F.3d 639 (Tenth Circuit, 2006)
Tal v. Hogan
453 F.3d 1244 (Tenth Circuit, 2006)
Hiatt v. Keil
738 P.2d 121 (New Mexico Supreme Court, 1987)
Monsanto v. Monsanto
894 P.2d 1034 (New Mexico Court of Appeals, 1995)
G.E.W. Mechanical Contractors, Inc. v. Johnston Co.
858 P.2d 103 (New Mexico Court of Appeals, 1993)
Lujan v. Merhege
519 P.2d 122 (New Mexico Supreme Court, 1974)
Tabet Lumber Company v. Chalamidas
489 P.2d 885 (New Mexico Court of Appeals, 1971)
Trujillo v. Romero
481 P.2d 89 (New Mexico Supreme Court, 1971)
Wolf and Klar Cos. v. Garner
679 P.2d 258 (New Mexico Supreme Court, 1984)
Superior Concrete Pumping, Inc. v. David Montoya Construction, Inc.
773 P.2d 346 (New Mexico Supreme Court, 1989)
Genuine Parts Co. v. Garcia
582 P.2d 1270 (New Mexico Supreme Court, 1978)
Scott v. Mego International, Inc.
524 F. Supp. 74 (D. Minnesota, 1981)
Martinez v. Albuquerque Collection Services, Inc.
867 F. Supp. 1495 (D. New Mexico, 1994)
Craft v. Sunwest Bank of Albuquerque, N.A.
84 F. Supp. 2d 1226 (D. New Mexico, 1999)
Garcia v. Jeantette
2004 NMCA 004 (New Mexico Court of Appeals, 2003)
Cutter Flying Service, Inc. v. Straughan Chevrolet, Inc.
459 P.2d 350 (New Mexico Supreme Court, 1969)
J.R. Hale Contracting Co. v. Union Pacific Railroad
2008 NMCA 037 (New Mexico Court of Appeals, 2007)