Environmental Dimensions, Inc. v. EnergySolutions Government Group, Inc.

District Court, D. New Mexico·Decided December 31, 2020·No. 1:16-cv-01056·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF NEW MEXICO ______________________

ENVIRONMENTAL DIMENSIONS, INC.,

Plaintiff, v. No. 1:16-cv-1056-KWR-JHR

ENERGYSOLUTIONS GOVERNMENT GROUP, INC. (n/k/a Atkins Energy Government Group, Inc.),

Defendant.

MEMORANDUM OPINION AND ORDER GRANTING SUMMARY JUDGMENT ON DEFENDANT’S DAMAGES

THIS MATTER comes before the Court following the Court’s prior order (Doc. 205), filed on November 13, 2020, in light of the Court’s decision to treat Defendant’s brief on the resolution of damages as a motion for summary judgment. Doc. 203. Having reviewed the parties’ pleadings and the applicable law, the Court finds that Defendant’s motion is well-taken and, therefore, is GRANTED. BACKGROUND1

The claims arise from a dispute involving a nuclear waste remediation project the parties worked on together at Los Alamos National Lab (“LANL”). Plaintiff is in the business of providing environmental resources and radioactive waste management and containment support to the U.S. Department of Energy and other government agencies. The company is managed predominately by its Vice President, Michael Bradshaw (“Bradshaw”). Plaintiff engaged in a

1 The Court incorporates the following factual background from findings in its preceding MOO’s, which are taken largely from undisputed facts cited by Defendant and supported in the record. See Docs. 167, 168, 188 and 202. As the Court provides in this Memorandum and Opinion Order, Plaintiff also fails to cite to the record in disputing these facts. bidding process for qualification to contract with Los Alamos National Security, LLC (“LANS”) to perform transuranic waste remediation work at LANL. Defendant provides nuclear waste remediation and personnel support and worked with LANL previously on other projects. Prior to submitting its bid, Plaintiff executed a Teaming Agreement with Defendant on July 12, 2011, specifying the duties and responsibilities of the parties should the bid be accepted. The Agreement

includes that, “[i]n any event, EnergySolutions' share will be a minimum of 35% of the total contract labor value earned in performance of the life cycle of the anticipated contract issued by LANS.” The Agreement contains an additional provision that “[e]xcept as expressly provided … all rights and obligations of the parties under this Agreement shall terminate on the earliest of the following: … e. Execution by both parties of the subcontract contemplated by this Agreement.” (Doc. 99 Ex. G). When Plaintiff was subsequently awarded the contract, denominated as Master Task Order Agreement 2 (“MTOA2”), it subcontracted with Defendant and two other companies to carry out the work. Plaintiff executed the subcontract with Defendant in August 2013, which incorporated

the language of the Teaming Agreement guaranteeing Defendant a 35% minimum share of the labor. The subcontract further provided that “[p]ayments shall be issued to Subcontractor after receipt and approval of Subcontractor’s invoices by EDi and within 10 days of receipt of payment from the [LANS].” Through a series of modifications, Defendant was authorized to bill up to $3,500,000 for completed work. At no time did Defendant exceed this amount. Work began on the project in July 2014. Plaintiff’s employees, project manager Chris Edgmon (“Edgmon”) and COO/VP of business development John Rodell (“Rodell”)2 were tasked with coordinating the work on a day-to-day

2 It is unclear what Rodell’s exact title is, but the record reflects that Edgmon deferred to him and he made final decisions regarding the project on a day-to-day basis. basis. Edgmon was responsible for, among other things, scheduling work, budgeting, and approving invoices submitted by the subcontractors, which in turn were submitted to Rodell for review and approval. Bradshaw had little involvement in the day-to-day operations of the project, and most decisions were largely left to Edgmon and Rodell. Defendant took on a larger role than the other subcontractors in performance of the work,

consequently billing for a larger share than the minimum 35% expressed in the Teaming Agreement and the subcontract. It is undisputed that Defendant only carried out work authorized by Plaintiff; that Defendant submitted six invoices dating from March 10 - August 11, 2015 amounting to $1,057,354.63, for which it was not paid; and that Plaintiff submitted invoices to LANS for the same work and received payment. On May 12, 2015, Bradshaw sent a letter of cure to Defendant stating it was not in compliance with the terms of the Teaming Agreement and that “[i]n spite of repeated attempts by EDi to realign the staffing to meet the TA [Teaming Agreement] goals, EnergySolutions continued refusal has forced us to take action… [i]f this matter is not resolved by Friday May 15, 2015, any work [going forward] performed by EnergySolutions above

and beyond 35% is done so solely at EnergySolutions’ risk.” (Doc. 113 Ex. 2). After Bradshaw’s letter, Plaintiff continued to assign work to Defendant, which it performed until the underlying Task Order was terminated by LANS on May 27, 2015. Plaintiff originally sued Defendant raising, among other claims, breach of contract and violation of New Mexico’s Unfair Trade Practices Act. Plaintiff largely attributed LANS’ choice to terminate the project and perform more work internally as a punitive measure in response to Defendant’s alleged misconduct during the February 14, 2014 “WIPP incident,” when an improperly packaged waste drum packaged by Defendant at LANL, while working on another project3, underwent an exothermic reaction and burst, causing a radiological release. RELEVANT PROCEDURAL HISTORY On November 8, 2019, the Court denied Defendant’s Motion for Summary Judgment on its Counterclaims (November Order) for, inter alia, breach of contract, or in the alternative, breach

of covenant of good faith and fair dealing and unjust enrichment. Defendant seeks damages in the amount of $1,057,354.63; the total of payments withheld by Plaintiff for the work Defendant performed. See Memorandum Opinion and Order (Doc. 158). The Court did not reach the merits of the majority of Defendant’s claims, denying the motion instead because, although Defendant’s argument was “persuasive,” it sought payment for work performed after the issuance of Bradshaw’s May 12 letter, as opposed to work completed solely beforehand. This case was subsequently transferred to the undersigned. On February 11, 2020, the undersigned granted Defendant’s motion for summary judgment on Plaintiff’s claims for breach of contract and fraud, and on February 14, 2020, granted Defendant’s motion for partial summary judgment on Plaintiff’s

New Mexico Unfair Trade Practices claim, thereby disposing of Plaintiff’s remaining claims. On April 30, 2020, the Court granted Defendant’s Motion for Reconsideration (Doc. 188), thereby granting summary judgment on Defendant’s counterclaim for breach of contract and alternatively for unjust enrichment. The Court did not reach the merits of Defendant’s other counterclaims. On July 6, 2020, in accordance with Defendant’s status report request, the Court addressed the remaining counterclaims, ruling in Defendant’s favor but deferring with respect to its counterclaim for an open account/account stated. Doc. 196. Pursuant to Fed. R. Civ. P. 56 (f) (1), the Court

3 Defendant operated as the prime contractor on that project; Plaintiff was not involved in and was not a party to that project. provided Defendant’s notice that it may grant summary judgment in favor of Plaintiff on this counterclaim and provided the Defendant an opportunity to respond. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Environmental Dimensions, Inc. v. EnergySolutions Government Group, Inc., (D.N.M. 2020).

Environmental Dimensions, Inc. v. EnergySolutions Government Group, Inc. (Environmental Dimensions, Inc. v. EnergySolutions Government Group, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Shero v. City of Grove, Okl.
510 F.3d 1196 (Tenth Circuit, 2007)
Smothers v. Solvay Chemicals, Inc.
740 F.3d 530 (Tenth Circuit, 2014)