Environmental Defense Fund, Inc. v. Armstrong

356 F. Supp. 131, 5 ERC 1153, 3 Envtl. L. Rep. (Envtl. Law Inst.) 20294, 5 ERC (BNA) 1153, 1973 U.S. Dist. LEXIS 14462
CourtDistrict Court, N.D. California
DecidedMarch 16, 1973
DocketC-72-1057
StatusPublished
Cited by20 cases

This text of 356 F. Supp. 131 (Environmental Defense Fund, Inc. v. Armstrong) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Defense Fund, Inc. v. Armstrong, 356 F. Supp. 131, 5 ERC 1153, 3 Envtl. L. Rep. (Envtl. Law Inst.) 20294, 5 ERC (BNA) 1153, 1973 U.S. Dist. LEXIS 14462 (N.D. Cal. 1973).

Opinion

MEMORANDUM OF DECISION AND ORDER

RENFREW, District Judge.

This memorandum of decision and order constitutes this Court's final opinion as to the adequacy of the Environmental Impact Statement ("EIS") filed in connection with the New Melones Project. The project, under the direction of the United States Corps of Army Engineers, involves the construction of a 2.4 million a cre feet capacity earth and rock-filled dam known as the New Melones Dam. Plaintiffs and plaintiff-intervenors originally brought suit on June 8, 1972, seeking preliminarily to enjoin further work on the project on the ground that the EIS filed in connection with the project was inadequate in several respects. The motion for a preliminary injunction and the trial on the merits were consolidated, and the case was then tried to the Court on September 27-30 and October 9, 1972.

The Court issued its first opinion in this matter on November 14, 1972, Environmental Defense Fund v. Armstrong, 352 F.Supp. 50 (N.D.Cal.1972). Viewing the project to be discussed in the EIS as including both the construction and the actual operation of the dam, as urged by plaintiffs, the Court found that the EIS was fully adequate in its treatment of the construction phase of the project and that it was also adequate in its treatment of the operation of the dam, except for the discussion therein of the uses to which the 285,000 1 acre-foot conservation yield would be put. The Court found that the failure to designate, at least preliminarily, the alternative uses to which the conservation yield was to be put, and the environmental impact thereof, mandated a finding that the EIS was incomplete under the standards set out in the National Environmental Policy Act ("NEPA"), 42 U.S.C. § 4321, et seq., and the Council on Environmental Quality Guidelines, 36 F.R. 7724.

However, after hearing extensive arguments from both sides, both in chambers on October 5, 1972, and in open court on October 9, 1972, the Court concluded in its opinion and order that a balancing of the equities required that the initial work on the project (though no actual construction) not be preliminarily enjoined pending the necessary supplementation of the EIS, as long as the Court retained jurisdiction and thus the power to restrain the commencement of actual construction work on the project in the event the revised EIS did not meet the requirements of NEPA. The Court clearly determined that such initial work as would occur was activity involving the ordering of equipment, the assembling of work crews, and the like, none of which could have any impact on the environment, adverse or otherwise.

The factors which led the Court to this conclusion were not only the substantial costs to be endured by the tax *134 payers were the project delayed, estimated to be some 12 million dollars at a minimum, and the increased flood hazard posed by such delay, but also the more general interest of effectuating compliance with Congressional dictates. The Court finally decided that in light of the relatively minor defects in the statement, the issuance of a blanket injunction stopping all such initial work on the project, not simply actual on-site construction, would in no way speed the preparation of a sufficient EIS and was therefore inappropriate.

Nonetheless, the Court made it abundantly clear to all concerned that no work on the project which would in any way affect the environment or indeed the site itself could be undertaken prior to completion and submission of a revised EIS which was found by the Court to comply with the requirements of NEPA. It was thus clearly understood by those contracting and undertaking the initial non-construction activity that they did so at their own risk, and that should the project later be enjoined because the EIS was not adequately supplemented, they would bear the costs incurred thereby. 2

Accordingly, after extensive meetings in chambers with the parties on September 30 and October 5, 1972, the Court drew up a revised construction schedule and a schedule for implementation of the EIS. Environmental Defense Fund v. Armstrong, supra, at 61. Under those schedules, no work was to be undertaken at the construction site until March 5, 1973, which was after the final hearing on the revised EIS scheduled for February 28, 1973, which thus gave the Court ample opportunity to enjoin the actual construction of the project in the event the requirements of NEPA had not been met. In the interim, supplementary data on the proposed alternative uses of the conservation yield was to be submitted by the Bureau of Reclamation to the Corps of Army Engineers and a preliminary or draft revised EIS prepared. The draft statement was then to be submitted to the Council on Environmental Quality ("CEQ") and to the public, as required under NEPA and the CEQ Guidelines.

On November 28, 1972, the first of two scheduled court hearings on the revised EIS was held. At that hearing, the Court, having studied the draft EIS submitted to it on November 22, 1972, afforded counsel for the Environmental Defense Fund and the Sierra Club an opportunity to comment upon the revised statement, noting any deficiencies therein, and to present to the Court any reasons why the Court should alter either the construction or the supplementation schedules. At the hearing, counsel for plaintiffs offered no reason why, in light of the preliminary revised EIS, the Court's schedule should be altered, much less why the project itself should be preliminarily enjoined. Rather counsel reasserted its views that (1) there would be a total loss of the white water were the dam built, an environmental impact which the Court already had held to have been fully discussed in the first EIS, and (2) that once the Court found a deficiency in the EIS, it could not balance the equities but was required, as a matter of law, to enjoin the entire project. As the Court noted in its earlier opinion, Environmental Defense Fund v. Armstrong, supra, at 60:

“Nothing in the NEPA, its legislative history, or the cases indicates that the Court is to be thus restricted from exercising its equity powers to fashion a decree meeting the needs of the particular case before the Court.”

Following the November 28th hearing, the Court issued its first Supplemental Memorandum Opinion and Order, in which the Court explained that, having been presented with no reason to alter the schedule as initially announced, the parties were to adhere to that schedule.

*135 On November 28th, the Court of Appeals for the Ninth Circuit issued a temporary injunction enjoining the Federal defendants from certain action concerning the contract for construction of the dam until December 8, 1972. After several continuations, the Court of Appeals issued an opinion on January 18, 1973, continuing the injunctive relief pending disposition of the appeal. The Court of Appeals then scheduled briefing to conform to the supplementation schedule so as to have a final judgment on the adequacy of the EIS from this Court prior to the commencement of its deliberations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

California Trout v. Schaefer
58 F.3d 469 (Ninth Circuit, 1995)
United States v. California
509 F. Supp. 867 (E.D. California, 1981)
United States v. State of Cal.
509 F. Supp. 867 (E.D. California, 1981)
Miller v. United States
492 F. Supp. 956 (E.D. Arkansas, 1980)
Colony Federal Savings & Loan Ass'n v. Harris
482 F. Supp. 296 (W.D. Pennsylvania, 1980)
City of South Pasadena v. Volpe
418 F. Supp. 854 (C.D. California, 1976)
City of Romulus v. County of Wayne
392 F. Supp. 578 (E.D. Michigan, 1975)
Sierra Club v. Froehlke
392 F. Supp. 130 (E.D. Missouri, 1975)
Sierra Club v. Stamm
507 F.2d 788 (Tenth Circuit, 1974)
Sierra Club v. Morton
421 F. Supp. 638 (District of Columbia, 1974)
Environmental Defense Fund, Inc. v. Armstrong
487 F.2d 814 (Ninth Circuit, 1973)
State of Ohio Ex Rel. Brown v. Callaway
364 F. Supp. 296 (S.D. Ohio, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
356 F. Supp. 131, 5 ERC 1153, 3 Envtl. L. Rep. (Envtl. Law Inst.) 20294, 5 ERC (BNA) 1153, 1973 U.S. Dist. LEXIS 14462, Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-defense-fund-inc-v-armstrong-cand-1973.