California Trout v. Schaefer

58 F.3d 469, 1995 WL 374254
Court of Appeals for the Ninth Circuit·Decided June 26, 1995·No. No. 93-17160·Published·Cited by 14 cases

Opinion

DAVID R. THOMPSON, Circuit Judge:

California Trout (CalTrout), a nonprofit environmental organization, challenges the United States Army Corps of Engineers’ (the Corps) decision to approve an application by the Stockton East Water District (SEWD) for a permit under section 404 of the Clean Water Act, 33 U.S.C. § 1344. SEWD sought a permit to discharge fill material into wetlands under the jurisdiction of the United States in conjunction with SEWD’s construction of a larger project to divert water from the Stanislaus River in California’s Central Valley.

CalTrout contends the Corps violated the National Environmental Policy Act (NEPA), 42 U.S.C. § 4331, et seq., and the Clean Water Act, 33 U.S.C. § Í344, by, inter alia, excluding from the scope of its permit review the entire project’s environmental effects on fisheries downstream in the Stanislaus River. The district court granted the Corps’s and SEWD’s motions for summary judgment, and this appeal by CalTrout followed. We affirm.

FACTS

SEWD has constructed a 41-mile long project to divert water from the Stanislaus River in the northern portion of California’s Central Valley to SEWD’s water treatment plant east of Stockton, California.

The New Melones Reservoir, which is the source of the water to be diverted, is controlled by the Bureau of Reclamation, United States Department of Interior (the Bureau). As part of its oversight, and pursuant to congressional direction, the Bureau has conducted studies and prepared environmental impact statements (EIS) to ensure that the allocation of New Melones water is “at all times ... subordinate” to the quantities of water required “to satisfy all existing and future needs within [the Stanislaus River] basin,” and that “appropriate measures” are adopted to “insure the preservation and propagation of fish and wildlife.” Flood Control Act of 1962, Pub.L. No. 87-874, 76 Stat. 1180, 1191. These studies include an EIS issued in 1972, and a supplemental EIS issued in 1980.

In addition, several studies are currently examining the impact on Stanislaus River fisheries of water allocations from the New Melones Reservoir. The Bureau, along with the U.S. Fish and Wildlife Service (FWS) and the California Department of Fish and Game (DFG), is conducting a multi-year study of the instream flow requirements and other needs of the fisheries. In addition, the Bureau and DFG are jointly developing a long-term water use plan for the Stanislaus and Calaveras Rivers that will, in part, “[p]rovide increased instream flows for fishery and wildlife needs” in those rivers. The Bureau and DFG are preparing an EIS in conjunction with that study, as required by the Central Valley Project Improvement Act (GVPIA). See Pub.L. No. 102-575, § 3406(e)(2), 106 Stat. 4706, 4722 (1992) (requiring that the Bureau complete the EIS by September 30,1996 and in so doing “evaluate and determine existing and anticipated future basin needs in the Stanislaus River Basin,” including “fish and wildlife resources”).

In 1983, SEWD entered into an interim water supply contract with the Bureau. The Bureau agreed to provide SEWD with a maximum of 75,000 acre-feet of water annually, subject to availability after the Bureau satisfied the water needs of in-basin users and higher priority out-of-basin users.

In early 1988, the California State Water Resources Control Board (State Water Board) approved the Bureau’s application to divert water at New Melones and downstream on the Stanislaus River for diversion by SEWD. As a condition of approving the Bureau’s water contracts, the State Water Board required the Bureau to maintain in-stream flow needs to protect fisheries and instructed the Bureau to conduct instream flow and fisheries studies. The Board retained jurisdiction over the Bureau’s permit in order to revise instream flow requirements for water quality objectives and fishery purposes.

In 1989, SEWD started building its 41-mile conveyance system to divert water from the Stanislaus River. The conveyance system consists of a diversion structure at Goodwin Dam, a 3.3-mile tunnel, a 10-mile Upper Farmington Canal, improvements in Shirley, [472]*472Hoods, and Rock creeks to utilize their 16 miles of natural watercourses, a rediversion structure at Rock Creek, the 8.6-mile Lower Farmington Canal, and a 3.2-mile buried pipeline. Prior to commencing construction, SEWD issued an Environmental Impact Report for the “Farmington Canal Project,” as required by California state law, which encompassed the Farmington Canal, as well as other features of the project.

In 1990, SEWD applied to the Corps for a permit under section 404 of the Clean Water Act to discharge fill material into water of the United States (wetlands), in connection with building one of the conveyance system components — the rediversion structure within Rock Creek, just below the Farmington Dam. No other portion of the project required federal approval. The Corps determined that 4.18 acres of wetlands within the Corps’s jurisdiction would be affected by the construction of the Rock Creek facility.

Pursuant to NEPA, the Corps prepared an Environmental Assessment (EA), granting the permit to SEWD and responding to concerns from third parties. The Corps’s sister agencies, including FWS, the Environmental Protection Agency (EPA), and the National Marine Fisheries Service (NMFS), were initially concerned about the impact the water diversion might have on the fisheries in the Stanislaus River. The Corps explained that SEWD’s permit application was not the appropriate forum for resolving the fishery issues, based on (1) the Bureau’s control over the allocation of water; (2) the separate contracts between the Bureau and SEWD governing water allocation; (3) and the environmental impact statements and other studies the Bureau had performed in the past, and currently was performing, concerning the fisheries. The Corps concluded that “[sjuffi-cient guarantees are in place to ensure that if studies indicate that additional flows are needed in the Stanislaus River, the Bureau will operate the New Melones reservoir accordingly.”

On October 26, 1992, CalTrout filed this lawsuit claiming that the Corps violated NEPA and the Clean Water Act when it issued the section 404 permit to SEWD. The Corps and SEWD’ moved for summary judgment, which the district court granted on August 27, 1993. This appeal followed.

In the meantime, construction of the entire project, including the Rock Creek facility, has been completed.1 However, to date, the Bureau has denied SEWD’s requests for water, in order to preserve supplies for higher-priority users, and no water has been diverted from the Stanislaus River to East Stockton. The 41-mile conveyance system, although completely built, remains dry.

DISCUSSION

1. Did the Corps arbitrarily and capriciously limit the scope of its NEPA analysis?

“The purpose of NEPA is to assure that federal agencies are fully aware of the impact of their decisions on the environment.” Friends of the Earth v. Hintz, 800 F.2d 822, 836 (9th Cir.1986) (citing Friends of Endangered Species, Inc. v. Jantzen, 760 F.2d 976, 985 (9th Cir.1985)).

Free access — add to your briefcase to read the full text and ask questions with AI

California Trout v. Schaefer, 58 F.3d 469, 1995 WL 374254 (9th Cir. 1995).

58 F.3d 469 (California Trout v. Schaefer) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Wong v. Bush
542 F.3d 732 (Ninth Circuit, 2008)
Sierra Club v. Babbitt
69 F. Supp. 2d 1202 (E.D. California, 1999)
United States v. Century Clinic, Inc.
75 F. Supp. 2d 1127 (D. Nevada, 1998)
Northcoast Environmental Center v. Glickman
136 F.3d 660 (Ninth Circuit, 1998)
Northwest Environmental Defense Center Northwest Resource Information Center, Inc. Oregon Trout, Inc. Idaho Steelhead and Salmon Unlimited Salmon for All v. Bonneville Power Administration U.S. Department of Energy, Direct Service Industrial Customers (Aluminum Co. Of America, Atochem North America, Columbia Falls Aluminum Company, Georgia-Pacific Corp., Kaiser Aluminum & Chemical Corp., Intalco Aluminum Corp.) Puget Sound Power & Light Company, a Maine Corporation City of Seattle, City Light Department ("City") Public Utility Dist. No. 2 of Grant County, Washington ("Grant") Washington Water Power Company Public Utility Dist. No. 1 of Chelan County, Washington, a Washington Municipal Corporation ("Chelan") Public Power Council Canby Utility Board ("Canby") Tillamook Peoples' Utility District Public Utility District 1 of Benton County, Washington Public District 1of Franklin County, Washington Public Utility 1 of Skamaia County Washington and Western Montana Generating & Transmission Cooperative, Inc. Portland General Electric Company Pacific Power & Light Company Public Utility District No. 1 of Douglas County, Respondents-Intervenors. Northwest Environmental Defense Center Northwest Resource Information Center, Inc. Idaho Steelhead and Salmon Unlimited Public Power Council, Petitioner-Intervenor v. Bonneville Power Administration U.S. Department of Energy, Direct Service Industrial Customers (Aluminum Co. Of America, Atochem North America, Columbia Falls Aluminum Company, Georgia-Pacific Corp., Kaiser Aluminum & Chemical Corp., Intalco Aluminum Corp.) Puget Sound Power & Light Company, a Maine Corporation City of Seattle, City Light Department ("City") Public Utility Dist. No. 2 of Grant County, Washington ("Grant") Washington Water Power Company Public Utility Dist. No. 1 of Chelan County, Washington, a Washington Municipal Corporation ("Chelan") Public Power Council Canby Utility Board ("Canby") Tillamook Peoples' Utility District Public Utility District 1 of Benton County, Washington Public District 1of Franklin County, Washington Public Utility 1 of Skamaia County Washington and Western Montana Generating & Transmission Cooperative, Inc. Portland General Electric Company Pacific Power & Light Company Public Utility District No. 1 of Douglas County, Respondents-Intervenors
117 F.3d 1520 (Ninth Circuit, 1997)
Oregon Natural Resources Council v. John Lowe
109 F.3d 521 (Ninth Circuit, 1997)
Ramsey v. Kantor
96 F.3d 434 (Ninth Circuit, 1996)
Environmental Coalition Of Ojai v. Brown
72 F.3d 1411 (Ninth Circuit, 1995)
California Trout v. Schaefer
58 F.3d 469 (Ninth Circuit, 1995)