State of Ohio Ex Rel. Brown v. Callaway

364 F. Supp. 296, 6 ERC 1629, 3 Envtl. L. Rep. (Envtl. Law Inst.) 20892, 6 ERC (BNA) 1629, 1973 U.S. Dist. LEXIS 12162
CourtDistrict Court, S.D. Ohio
DecidedAugust 24, 1973
DocketCiv. 8892 and 8893
StatusPublished
Cited by5 cases

This text of 364 F. Supp. 296 (State of Ohio Ex Rel. Brown v. Callaway) is published on Counsel Stack Legal Research, covering District Court, S.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State of Ohio Ex Rel. Brown v. Callaway, 364 F. Supp. 296, 6 ERC 1629, 3 Envtl. L. Rep. (Envtl. Law Inst.) 20892, 6 ERC (BNA) 1629, 1973 U.S. Dist. LEXIS 12162 (S.D. Ohio 1973).

Opinion

OPINION AND ORDER

CARL B. RUBIN, District Judge.

This matter is before the Court upon plaintiff’s motion for a preliminary injunction. Comprehensive memoranda, briefs, affidavits, and exhibits have been filed; oral arguments have been heard and testimony received. In accordance with Rule 52 of the Federal Rules of Civil Procedure, the Court makes the following findings of fact and conclusions of law.

I

FINDINGS OF FACT

1. As part of the Flood Control Act of June 28, 1938, 52 Stat. 1215 (33 U.S. C. § 701 et seq.), seventy-four reservoirs were authorized for the Ohio Valley. These reservoirs were constructed at various times and on various rivers. Included among such reservoirs are those to be located on Caesar’s Creek and the East Fork, each a tributary of the Little Miami River, itself a tributary of the Ohio River. Funding for the above projects commenced in 1962 with a Congressional appropriation of approximately twelve thousand dollars ($12,000.00) for each. These appropriations have increased year by year in approximately the same amount. Significant amounts of appropriation began in 1969 with $1,550,000.00 appropriated for Caesar’s Creek and $1,600,000.00 appropriated for East Fork. During fiscal 1973, $5,800,000.00 was appropriated for Caesar’s Creek and $4,200,000.00 for East Fork. For fiscal 1974, $8,000,000.00 has been budgeted for Caesar’s Creek and $2,600,000.00 for East Fork. 1

2. Each project is intended to help control floods, provide a more desirable water supply, improve water quality, and create new recreational features. Land acquisition began in 1967 and each will require approximately 11,000 acres of land. As of June 30, 1973, 88.7% of the necessary land had been acquired for East Fork and 77.7% for Caesar’s Creek. 2

*298 3. Three contracts are presently in force for construction at these two projects. 3 For Caesar’s Creek, a contract for the construction of outlet works, dam, and spillway, No. DACW 27-72-C-0086 in the face amount of $7,853,737.55 was awarded to Butt & Head, Inc., 3858 New Germany Road, Dayton, Ohio, on March 1, 1972.

For the same project, contract No. DACW 27-73-C-0022 was entered into on August 31, 1972 for the construction of an office and shop building. This contract was awarded to the Small Business Administration, Midwest Regional Office, and was subcontracted in full to Francis & Washington, Inc., 125 South Infirmary Road, Dayton, Ohio. This contract is in the face amount of $216,551.45.

For the East Fork Lake project, contract No. DACW 27-73-C-0068 was entered into on December 29, 1972, with S. J. Groves & Sons Company, Minneapolis, Minnesota, for the construction of a dam and spillway in the face amount of $12,257,839.30.

4. On January 1, 1970, the National Environmental Policy Act (NEPA), 42 U.S.C. § 4321 et seq. (1970), became effective. In accordance with § 102 of NEPA, 42 U.S.C. § 4332 (1970), an Environmental Impact Statement (EIS) was filed for the East Fork project on February 25, 1971, and an Environmental Impact Statement for Caesar’s Creek was filed on April 16, 1971. There is also an undated document entitled “Draft Environmental Statement” for each project consisting of three pages. In addition, on August 11, 1972, a supplement to the East Fork EIS was filed. These five documents comprise the sole evidence of compliance with § 102 of NEPA.

Each project is intended to convert a free-flowing stream into an impounding lake behind a dam and spillway. Each will involve the removal of trees and groundcover, and the excavation of topsoil and subsoil from approximately 11,000 acres of land.

Recreational opportunities inherent in a free-flowing stream will be lost and those incident to a stillwater lake will be gained. Biosystems that flourish in the former environment will be replaced by those that flourish in a stillwater lake.

Each of the projects will contribute water to the Little Miami River, particularly during periods of low water in suifamer. No evidence of excessive adverse environmental effects appears in either Environmental Impact Statement. No evidence has been presented to the Court as to environmental advantages of flow regulation of the Little Miami River.

5. The situation in August of 1973 as to each of these projects is as follows:

(a) Environmental Impact Statements have been filed which are admittedly below 1973 standards for such statements.

(b) Environmental damage incident to the contracts, i. e., site clearing, excavation to bedrock, construction of service roadways, has already occurred. No further significant environmental damage from such contracts appears likely. Future contracts will have substantial environmental impact.

(c) Only the months of August, September and October remain during which outdoor construction may feasibly *299 continue in the present construction season.

II

OPINION

There are four customary conditions precedent to the granting of a preliminary injunction. The plaintiff must establish that a substantial question is at issue; that there is probability of success on the merits; that a balancing of injuries to the parties requires preliminary relief; and that the public interest would be served by such preliminary relief. Environmental Defense Fund v. Tennessee Valley Authority, 339 F.Supp. 806 (E.D.Tenn.1972), aff’d, 468 F.2d 1164 (6th Cir. 1972); Sierra Club v. Hickel, 433 F.2d 24 (9th Cir. 1970), aff’d sub nom., Sierra Club v. Morton, 405 U.S. 727, 92 S.Ct. 1361, 31 L.Ed.2d 636 (1972), Garlock, Inc. v. United Seal, Inc., 404 F.2d 256 (6th Cir. 1968).

There is no doubt that this is a matter of substantial importance to all the parties involved. Since defendants have conceded that complete Environmental Impact Statements have not beén filed, there is probability of success for plaintiff upon that limited issue.

Implicit in any construction project of this magnitude may be substantial and irreparable injury to the public at large. Without seeking to catalogue the damages that might result, the Court observes merely that flooding thousands of acres of land and conversion of free-flowing streams into impounding reservoirs are, for all practical purposes, irreversible.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State of Ohio v. United States
Federal Claims, 2022
National Audubon Society v. Andrus
442 F. Supp. 42 (District of Columbia, 1977)
City of Romulus v. County of Wayne
392 F. Supp. 578 (E.D. Michigan, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
364 F. Supp. 296, 6 ERC 1629, 3 Envtl. L. Rep. (Envtl. Law Inst.) 20892, 6 ERC (BNA) 1629, 1973 U.S. Dist. LEXIS 12162, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-of-ohio-ex-rel-brown-v-callaway-ohsd-1973.