Entech Corp. v. City of Newark

798 A.2d 681, 351 N.J. Super. 440, 2002 N.J. Super. LEXIS 271
CourtNew Jersey Superior Court Appellate Division
DecidedJanuary 9, 2002
StatusPublished
Cited by5 cases

This text of 798 A.2d 681 (Entech Corp. v. City of Newark) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Entech Corp. v. City of Newark, 798 A.2d 681, 351 N.J. Super. 440, 2002 N.J. Super. LEXIS 271 (N.J. Ct. App. 2002).

Opinion

798 A.2d 681 (2002)
351 N.J. Super. 440

ENTECH CORPORATION, a New York Corporation, Plaintiff,
v.
CITY OF NEWARK, Defendant.

Superior Court of New Jersey, Law Division.

Decided January 9, 2002.

*684 Edward S. Kiel, Hackensack, for plaintiff, (Cole Schotz, Meisel, Forman & Leonard, attorneys).

William J. Schwartz, First Assistant Corporation Counsel, for defendant, City of Newark.

Mark L. Fleder and Damon McDougal, Roseland, for Spiniello, intervenor-defendant, (Connell Foley, LLP, attorneys). *682

*683 JACOBSON, J.S.C.

INTRODUCTION

On November 16, 2001, Entech Corporation filed an Order To Show Cause and a Verified Complaint in Lieu of Prerogative Writs against the City of Newark, growing out of the City's selection of Spiniello as the low bidder on Brick Sewer Rehabilitation, Phase III/IV (G) Sewer Rehabilitation Contract No. 08-WS2000. The City notified Entech on October 12, 2001, that Entech's bid—although apparently the lowest received—had not been accepted because it was non-conforming. Entech admittedly had submitted a bid for the in-place rehabilitation of approximately 5800 linear feet of brick combined sanitary/storm sewers using shotcrete or gunite when the bid specifications called for the use of cured-in-place pipe lining or *685 Fiberglass Reinforced Plastic segmental sewer lining, also known as "channeline". Shotcrete had been used on other sewer rehabilitation projects in Newark and is less expensive than the two other methods selected by Newark for this bid. Although Entech had challenged the bid specification that excluded shotcrete as an alternative method of sewer rehabilitation for the project under N.J.S.A. 40A:11-13(e) prior to the bid opening, Newark had rejected the challenge without explanation. After the bid award, Entech filed this Order to Show Cause seeking to enjoin Newark from entering into a contract with the winning bidder, Spiniello, which had bid more than $1,000,000 more than Entech using the cured-in-place technology.

STATEMENT OF FACTS

The City of Newark is in the process of implementing a major sewer rehabilitation project funded in part by the federal government. Newark's engineer for Phase III/IV of the Brick Sewer Rehabilitation project is Camp Dresser & McKee. Entech had successfully bid on at least one sewer rehabilitation contract for Newark using shotcrete, which is a mortar or concrete coating that is sprayed onto the inside surface of sewer pipes. Shotcrete is also referred to as gunite. Among the issues involved in this case is whether Newark properly excluded shotcrete as an acceptable method of sewer rehabilitation for contract 08.

In February 2001, Entech became concerned that bid openings on contracts 03, 04, 05 and 06 of Phase III/IV of Newark's Brick Sewer Rehabilitation project excluded shotcrete as a rehabilitation method, and wrote to Camp Dresser & McKee (CDM) to request that shotcrete be considered as an alternate method to the technologies specified in the bid documents. CDM responded on February 19, 2001, stating that while shotcrete had been considered as a rehabilitation technique for some of the sewer rehabilitation contracts in the past, it would not be used for contracts 03, 04, 05 and 06, but might be used for contract 09. No explanation for this statement was provided. On February 23, 2001, Entech wrote again to CDM, this time to request the procedures for filing a bid protest with Newark concerning the bid specifications for the four contracts under discussion. Entech sent a second letter on the same date, asking again for an explanation from CDM for the exclusion of shotcrete from the rehabilitation methods acceptable for the four contracts. Entech sounded what has become its recurring theme in that letter, arguing that shotcrete had historically been accepted by Newark for sewer rehabilitation projects, was more cost effective than the other methods chosen for those contracts, and should be reconsidered as a rehabilitation method for the brick sewer rehabilitation work in Newark. There is no written response from CDM to Entech's letter in the record. Nor does the record address the award of bids for contracts 03, 04, 05 and 06.

In September 2001, Newark solicited bids for contract 08 of the Phase III/IV Sewer Rehabilitation Program and limited the rehabilitation techniques to cured-in-place piping and a fiberglass lining system known as channeline. Prior to this solicitation, the plans and specifications for contract 08 had been reviewed and approved by the United States Environmental Protection Agency as being in conformance with applicable federal regulations. Bids were to be submitted by September 26, 2001. Entech reviewed the bid documents and wrote to CDM on September 11, 2001, proposing to respond to the bid request utilizing the shotcrete method. Entech noted in the September 11 letter that *686 CDM had led Entech to believe that the earlier referenced contracts excluded shotcrete because of the smaller size of the sewers involved and that shotcrete would be acceptable for larger sewers, such as the ones included in contract 08. A follow-up letter from Entech to CDM of September 14, 2001, requested the design basis and method of analysis used to design the project.

On September 18, 2001, CDM responded to Entech, stating merely that a bid proposing gunite (or shotcrete) would be deemed unresponsive. No explanation was given as to why shotcrete had been excluded as a rehabilitation technique for the large sewers included in contract 08. In a letter of September 21, 2001, CDM reiterated that a bid utilizing gunite would be non-responsive given the bid specifications for contract 08. CDM also refused to provide Entech with the design basis for the contract, claiming that this material was not necessary for Entech to bid on the contract. Also on September 21, 2001, counsel for Entech challenged the exclusion of gunite or shotcrete from the bidding specifications for contract 08 under N.J.S.A. 40A:11-13(e). By letter dated September 24, 2001, CDM acknowledged receipt of the challenge and stated simply that "Please be advised that the City intends to receive bids on the project as designed on September 26, 2001." No explanation for the exclusion of shotcrete as a rehabilitation method for contract 08 was provided.

Entech then proceeded to submit a bid for contract 08 using shotcrete or gunite, totalling $1,590,999.00. By letter dated October 12, 2001, Philip A. LiVecchi, Director of the Newark Department of Water and Sewer Utilities, notified Entech that Entech's "alternate bid proposal ... cannot be accepted." Apparently, Newark awarded the bid to Spiniello, one of three responsive bidders, with a bid utilizing cured-in-place piping at a total cost of $2,687,920.00. Entech did not file a bid protest with Newark at this time, despite having preserved its right to challenge the bid specifications after the receipt of bids by filing a bid specification challenge under N.J.S.A. 40A:11-13(e) at least three days prior to the opening of bids. Rather, approximately one month later, on November 16, 2001, Entech filed an Order to Show Cause and Verified Complaint in Lieu of Prerogative Writs, naming only the City as defendant, and seeking an injunction against the award of the 08 contract to any entity other than Entech.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
798 A.2d 681, 351 N.J. Super. 440, 2002 N.J. Super. LEXIS 271, Counsel Stack Legal Research, https://law.counselstack.com/opinion/entech-corp-v-city-of-newark-njsuperctappdiv-2002.