Engineering & Construction Innovations, Inc. v. Bradshaw Construction Corp.

CourtDistrict Court, D. Minnesota
DecidedSeptember 3, 2020
Docket0:20-cv-00808
StatusUnknown

This text of Engineering & Construction Innovations, Inc. v. Bradshaw Construction Corp. (Engineering & Construction Innovations, Inc. v. Bradshaw Construction Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Engineering & Construction Innovations, Inc. v. Bradshaw Construction Corp., (mnd 2020).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF MINNESOTA

Engineering & Construction Innovations, Case No. 20-cv-808 (WMW/TNL) Inc.,

Plaintiff, ORDER v.

Bradshaw Construction Corporation and Travelers Casualty & Surety Company of America,

Defendants.

Ernest F. Peake, Patrick J. Lindman, and Paul Shapiro, Taft Stettinius & Hollister LLP, 80 South Eighth Street, Suite 2200, Minneapolis, MN 55402 (for Engineering & Construction Innovations, Inc.); and

Dean B. Thomson and Julia J. Douglass, Fabyanske Westra Hart & Thomson, PA, 333 South Seventh Street, Suite 2600, Minneapolis, MN 55402 and Rachael L. Russo and Thomas Louis Rosenberg, Roetzel & Andress, LPA, 41 South High Street, Huntington Center, Columbus, OH 43215 (for Bradshaw Construction Corporation and Travelers Casualty & Surety Company of America).

This matter is before the Court on Plaintiff Engineering & Construction Innovations, Inc.’s Motion to Amend Complaint. (ECF No. 55). The Court has reviewed and considered all papers filed in connection with the motion. For the reasons that follow, the Court will grant the motion. I. FACTUAL BACKGROUND AND PROCEDURAL HISTORY Plaintiff Engineering & Construction Innovations, Inc. (“ECI”) is a general contractor that entered into a contract with the City of Minneapolis to install a water main under the Mississippi River near the 10th Avenue Bridge (ECF No. 61, p. 3). ECI hired Defendant Bradshaw Construction Corporation (“Bradshaw”) as a subcontractor to provide

microtunneling work. (ECF No. 61, p. 7). The contract between Bradshaw and ECI requires Bradshaw to indemnify, defend, and save harmless ECI and Minneapolis from all claims, damages, and expenses that result from Bradshaw’s intentional or reckless misconduct, omissions, or negligent acts. (ECF No. 61, p. 22). Bradshaw also obtained a performance bond from Travelers to guaranty Bradshaw’s performance of the worked required under the contract. (ECF No. 61, p. 8).

ECI alleges that Bradshaw’s work was defective, causing two flood events and substantial delay to the project. (ECF No. 61, pp. 9-10). ECI further alleges that Bradshaw failed to complete the work called for under its contract because Bradshaw tunneled only 70 of 896 feet (ECF No. 61, p. 12) and that Bradshaw later entered the work site without permission, causing another flooding event. (ECF No. 61, p. 15). After the parties were

unable to resolve disputes related to Bradshaw’s performance, Minneapolis required ECI to terminate Bradshaw and remove it from the project. (ECF No. 61, p. 15). ECI did so and requested that Travelers perform under the bond. (ECF No. 61, p. 16). Travelers refused. (ECF No. 61, p. 16). On March 16, 2020, ECI served Travelers and Bradshaw with a summons and

complaint, which it intended to file in state court. (ECF No. 1-1, p. 1). In response, Travelers filed a lawsuit against ECI in federal court. Travelers sought declaratory relief as to its rights and obligations under the bond. (ECF No. 1, 20-cv-795 & ECF No. 83, 20-cv- 808). ECI then filed suit in state court against Travelers and Bradshaw, who removed it to federal court. The cases have since been consolidated into this matter for further proceedings.

ECI then requested that Bradshaw defend, indemnify, and save harmless ECI in the Travelers lawsuit, pursuant to the indemnification clause in the contract between Bradshaw and ECI. ECI alleges that Bradshaw has failed or declined to do so. It now seeks to amend its complaint to add a breach of contract claim against Bradshaw for its alleged failure to indemnify ECI.

II. ANALYSIS Once 21 days have passed after service of a responsive pleading, a party “may amend its pleading only with the opposing party’s written consent or the court’s leave.” Fed. R. Civ. P. 15(a)(2). “Although leave to amend ‘shall be freely given when justice so requires,’ see Fed. R. Civ. P. 15(a), plaintiffs do not have an absolute or automatic right to amend.” United States ex rel. Lee v. Fairview Health Sys., 413 F.3d 748, 749 (8th Cir.

2005) (citing Meehan v. United Consumers Club Franchising Corp., 312 F.3d 909, 913 (8th Cir. 2002)). The Court may deny a party’s request for leave to amend only “if there are compelling reasons such as undue delay, bad faith, or dilatory motive, repeated failure to cure deficiencies by amendments previously allowed, undue prejudice to the non- moving party, or futility of the amendment.” Reuter v. Jax Ltd., Inc., 711 F.3d 918, 922

(8th Cir. 2013) (quoting Sherman v. Winco Fireworks, Inc., 532 F.3d 709, 715 (8th Cir. 2008)). “[A] motion to amend should be denied on the merits ‘only if it asserts clearly frivolous claims or defenses.’” Becker v. Univ. of Nebraska at Omaha, 191 F.3d 904, 908 (8th Cir. 1999) (quoting Gamma–10 Plastics, Inc. v. American President Lines, Ltd., 32 F.3d 1244, 1255 (8th Cir. 1994)). In general, motions for leave to amend under Rule 15 may only be denied in “limited circumstances.” Roberson v. Hayti Police Dept., 241 F.3d

992, 995 (8th Cir. 2001). Bradshaw argues only the proposed amendment is futile.1 A motion for leave to amend a pleading is futile when the amended pleading would not be able to withstand a motion to dismiss under Federal Rule of Civil Procedure 12(b)(6). Zutz v. Nelson, 601 F.3d 842, 850 (8th Cir. 2010). In deciding a Rule 12(b)(6) motion, a court accepts as true all well-pleaded factual allegations and then determines “whether they plausibly give rise to

an entitlement to relief.” Ashcroft v. Iqbal, 556 U.S. 662, 680 (2009). In doing so, the court must draw reasonable inferences in the plaintiff’s favor. Zink v. Lombardi, 783 F.3d 1089, 1098 (8th Cir. 2015) (citation omitted). “To survive a motion to dismiss, a complaint must contain sufficient factual matter, accepted as true, to state a claim to relief that is plausible on its face.” Sletten & Brettin Orthodontics v. Cont’l Cas. Co., 782 F.3d 931, 934 (8th Cir.

2015) (citation and internal quotations omitted). Facial plausibility of a claim exists “when the plaintiff pleads factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Iqbal, 556 U.S. at 678 (citing Twombly, 550 U.S. at 555). Although a sufficient complaint need not be detailed, it must contain “[f]actual allegations . . . enough to raise a right to relief above the speculative

level.” Twombly, 550 U.S. at 555 (citation omitted). Complaints are insufficient if they

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zutz v. Nelson
601 F.3d 842 (Eighth Circuit, 2010)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Gordon M. Becker v. University of Nebraska, at Omaha
191 F.3d 904 (Eighth Circuit, 1999)
Douglas Reuter v. Jax Ltd., Inc.
711 F.3d 918 (Eighth Circuit, 2013)
Sherman v. Winco Fireworks, Inc.
532 F.3d 709 (Eighth Circuit, 2008)
Employers Mutual Casualty Co. v. A.C.C.T., Inc.
580 N.W.2d 490 (Supreme Court of Minnesota, 1998)
David Zink v. George Lombardi
783 F.3d 1089 (Eighth Circuit, 2015)
Meehan v. United Consumers Club Franchising Corp.
312 F.3d 909 (Eighth Circuit, 2002)
Mono Adver., LLC v. Vera Bradley Designs, Inc.
285 F. Supp. 3d 1087 (D. Maine, 2018)
Engineering & Construction Innovations, Inc. v. L.H. Bolduc Co.
825 N.W.2d 695 (Supreme Court of Minnesota, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Engineering & Construction Innovations, Inc. v. Bradshaw Construction Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/engineering-construction-innovations-inc-v-bradshaw-construction-corp-mnd-2020.