Emery v. Leavesly McCollum

725 A.2d 807, 1999 Pa. Super. 26, 1999 CCH OSHD 31,774, 1999 Pa. Super. LEXIS 124
CourtSuperior Court of Pennsylvania
DecidedFebruary 17, 1999
StatusPublished
Cited by29 cases

This text of 725 A.2d 807 (Emery v. Leavesly McCollum) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Emery v. Leavesly McCollum, 725 A.2d 807, 1999 Pa. Super. 26, 1999 CCH OSHD 31,774, 1999 Pa. Super. LEXIS 124 (Pa. Ct. App. 1999).

Opinion

LALLY-GREEN, J.:

¶ 1 Appellants, Stephen H. Emery and Star Emery, appeal from an order granting summary judgment in favor of Appellees, Bechtel Construction, Inc. (“Bechtel”) and Gilberton Power Company (“Gilberton”). We affirm.

¶2 The Emerys filed negligence actions against Bechtel and Gilberton, among others. 1 The trial court granted summary judgment in favor of Bechtel on the ground that Bechtel was Stephen Emery’s statutory employer. The court held that Gilberton was not hable for the acts or omissions of its general contractor, Bechtel, and granted summary judgment in favor of Gilberton on that basis.

¶ 3 The injury underlying these lawsuits occurred when Stephen Emery, a forklift operator employed by Leavesly-MeCollum, was working overtime at a construction site owned by Gilberton. It was dark when Emery completed his work. He ascended a staircase in order to shut off the air compressors at the site. Upon entering the first floor, Emery fell through an opening in the floor and landed on top of the storage tank below. He suffered permanent disabling lower back injuries.

*810 ¶ 4 Gilberton, a general partnership, was formed to finance, construct and operate a cogeneration plant and drying facility in West Mahanoy Township, Schuylkill County. Gilberton entered into a contract with Bechtel for construction of the facility. Bechtel contracted with Pyro Power, Inc. (“Pyro Power”) for certain work. Pyro Power in turn contracted with Leavesly-McCollum, Emery’s employer, to insulate the inside of the boilers at the facility. Gilberton is the owner of the facility and Bechtel is the general contractor.

¶ 5 On appeal, the Emerys raise four issues:

1. Whether a general contractor is liable for injuries suffered by the employee of a sub-subcontractor where the general contractor did not have actual control over the work; and when there was no contractual relationship between the general contractor and the sub-subcontractor?
2. Whether a general contractor is liable for injuries suffered by the employee of a sub-subcontractor when the sub-subcontractor provided workers’ compensation benefits?
3. Whether the owner of a construction site is liable for injuries suffered by the employee of a subcontractor when the owner retains control of the job site, is obligated to inspect and supervise all work performed on site, promulgate a safety program for the project and ensure compliance with safety procedures and employs a site manager to supervise and inspect the work, to ensure all contractors comply with safety procedures and to correct hazardous conditions on site.
4. Whether an employer is liable for injuries suffered by the employee of a subcontractor when the employee was working overtime on the job site after dark; the job site was not equipped •with artificial lighting; and the employee fell through a floor opening which was unlit, railless and uncovered in contravention of OSHA regulations and the employer’s safety program?

¶ 6 In reviewing the grant of summary judgment:

we must view the record in the light most favorable to the non-moving party and determine whether the moving party has established that there exists no genuine issue of material fact and that it is therefore entitled to judgment as a matter of law. Skipworth v. Lead Industries Assoc., 547 Pa. 224, 230, 690 A.2d 169, 171 (1997). The non-moving party is entitled to all reasonable inferences. Any doubts as to the existence of a factual dispute must be resolved in the non-moving party’s favor and summary judgment is appropriate only in the clearest of eases. Kingston Coal Co. v. Felton Mining Co., Inc., 456 Pa.Super. 270, 690 A.2d 284, 287 (1997).

Roman Mosaic & Tile v. Aetna Cas. & Sur., 704 A.2d 665, 668 (Pa.Super.1997).

¶ 7 The Emerys first contend that Bechtel is not a statutory employer and, thus, is not immune from liability for negligence. This argument is premised on the definition of statutory employer found in § 203 of the Workers’ Compensation Act. 2 A general contractor can only be deemed a statutory employer where the following elements are demonstrated: ■

1. An employer who is under contract with an owner or one in the position of an owner. 1
2. Premises occupied by- or under the control of such employer.
3. A subcontract made by such employer.
4. Part of the employer’s regular business entrusted to such subcontractor.
5. An employee of such subcontractor.

McDonald v. Levinson Steel Co., 302 Pa. 287, 294, 153 A. 424, 426 (1930). The Emerys do *811 not challenge the first, fourth, and fifth elements of this test but argue that Bechtel does not meet either the second or the third element.

¶ 8 The Emerys first' argue that Bechtel cannot be a statutory employer because it fails the second McDonald element, i.e. Bechtel did not have actual control over the work at the construction site. An employer will satisfy this element of the McDonald test either if he occupies the premises or if he is in control of the premises. Dougherty v. Conduit & Foundation Corp., 449 Pa.Super. 405, 674 A.2d 262, 266 (1996). Although actual control must be demonstrated, id., the statutory employer’s control of the premises need not be exclusive of the owner’s possession of the premises. Colloi v. Philadelphia Elec. Co., 332 Pa.Super. 284, 481 A.2d 616, 623 (1984). Moreover, the fact that the subcontractor used its own supervisors to directly oversee the subcontractor’s employees does not mean the general contractor did not retain actual control over the project and premises in general. Pastore v. Anjo Construction Co., 396 Pa.Super. 58, 578 A.2d 21, 26 (1990).

¶ 9 The record shows that Bechtel, as general contractor, occupied the property for the purpose of constructing the cogeneration plant and had actual control over the premises. Bechtel had an on-site project superintendent who coordinated the work of the various subcontractors. The deposition testimony of the project superintendent clearly set forth that, while each subcontractor was responsible in its limited area, Bechtel was responsible for overseeing the entire project. 3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M. Edie v. George Junior Republic in PA
Commonwealth Court of Pennsylvania, 2026
Yoder, J. v. McCarthy Const., Inc
2023 Pa. Super. 13 (Superior Court of Pennsylvania, 2023)
Dobransky, E. v. EQT Production
2022 Pa. Super. 61 (Superior Court of Pennsylvania, 2022)
Uzho, M. v. Top Gun Construction, Inc.
Superior Court of Pennsylvania, 2021
Main, R. v. The Columbia Gas Company
Superior Court of Pennsylvania, 2019
Doman v. Atlas America, Inc.
150 A.3d 103 (Superior Court of Pennsylvania, 2016)
Maghakian v. Cabot Oil & Gas Corp.
171 F. Supp. 3d 353 (M.D. Pennsylvania, 2016)
Keffer v. Bob Nolan's Auto Service, Inc.
59 A.3d 621 (Superior Court of Pennsylvania, 2012)
Beil v. Telesis Construction, Inc.
11 A.3d 456 (Supreme Court of Pennsylvania, 2011)
Six L'S Packing Co. v. Workers' Compensation Appeal Board
2 A.3d 1268 (Commonwealth Court of Pennsylvania, 2010)
Braun v. Target Corp.
983 A.2d 752 (Superior Court of Pennsylvania, 2009)
Warnick v. Home Depot U.S.A., Inc.
516 F. Supp. 2d 459 (E.D. Pennsylvania, 2007)
Farabaugh v. Pennsylvania Turnpike Commission
911 A.2d 1264 (Supreme Court of Pennsylvania, 2006)
Kelly v. Thackray Crane Rental, Inc.
874 A.2d 649 (Superior Court of Pennsylvania, 2005)
Stokes v. I.B. Dickinson & Sons Inc.
70 Pa. D. & C.4th 484 (Northampton County Court of Common Pleas, 2004)
Thomas v. Aethos Construction Co.
66 Pa. D. & C.4th 187 (Alleghany County Court of Common Pleas, 2004)
Matchulat v. Powlus Construction Inc.
67 Pa. D. & C.4th 183 (Monroe County Court of Common Pleas, 2004)
Fulgham v. Daniel J. Keating Co.
285 F. Supp. 2d 525 (D. New Jersey, 2003)
Hepps v. LaBrum & Doak
57 Pa. D. & C.4th 124 (Philadelphia County Court of Common Pleas, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
725 A.2d 807, 1999 Pa. Super. 26, 1999 CCH OSHD 31,774, 1999 Pa. Super. LEXIS 124, Counsel Stack Legal Research, https://law.counselstack.com/opinion/emery-v-leavesly-mccollum-pasuperct-1999.