Emanuel v. Sheridan Transportation Corp.

10 A.D.3d 46, 779 N.Y.S.2d 168, 2004 N.Y. App. Div. LEXIS 6500
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 4, 2004
StatusPublished
Cited by14 cases

This text of 10 A.D.3d 46 (Emanuel v. Sheridan Transportation Corp.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Emanuel v. Sheridan Transportation Corp., 10 A.D.3d 46, 779 N.Y.S.2d 168, 2004 N.Y. App. Div. LEXIS 6500 (N.Y. Ct. App. 2004).

Opinion

OPINION OF THE COURT

Tom, J.

On December 3, 1992, the barge ST 114, a merchant vessel allegedly owned by defendant Hygrade Operators Inc. (Hygrade) and operated by defendant-appellant-respondent Spentonbush/ Red Star Companies, Inc. (Spentonbush), was transporting oil off the northeast coast of the United States when it was grounded in an area known as “stepping stones” and suffered damage to its hull. The Coast Guard conducted an investigation and directed the barge to discharge its cargo and make permanent repairs before being allowed to operate or load cargo again. On December 16, 1992, the barge entered the shipyard of third-party defendant G. Marine Diesel Corp. (G. Marine) in the Brooklyn Navy Yard for dry-docking. G. Marine quoted Spentonbush prices for dry-docking and repairs, and, more particularly, G. Marine quoted a price to hook up and disconnect a gangway. On December 17, 1992, the barge was placed in a dry-dock space, all the water pumped out, and the barge was resting on cement blocks that had timbers placed on top of those blocks.

Plaintiffs decedent, James Emanuel, was a rigger employed by G. Marine. After the barge was placed in dry dock, G. Marine’s rigging foreman instructed Emanuel to place the gangway, provided by G. Marine, between the barge and dry dock. According to the foreman, he told Emanuel to walk around the dry dock while a crane swung the gangway over into place [48]*48and did not assign anyone to ride the gangway. However, G. Marine’s marine engineer, Thomas Gibson, who was on board the barge and discussing repair work with the captain of the barge when the accident occurred, saw Emanuel standing in the center of the gangway, holding on to its side rails, as the crane attempted to land it on the barge.

According to Gibson, the only eyewitness, the gangway, which had rope at both ends, was being placed in position when Emanuel yelled to the captain to “tie up the gangway.” The captain, whose back was facing Emanuel, kept talking to Gibson. The gangway touched the barge deck for a few seconds and then suddenly shot out, and Emanuel plummeted approximately 45 feet to the bottom of the dock, sustaining massive injuries that rendered him a quadriplegic and ultimately led to his death on August 30, 1994.

Plaintiff, individually and as administratrix of Emanuel’s estate, brought this action against, inter alia, Hygrade, its agent, Spentonbush, and defendant-appellant-respondent Amerada Hess (Hess). Hess and Spentonbush, inter alia, commenced a third-party action against Emanuel’s employer G. Marine and its successor in interest, FCE Industries Ltd. After plaintiff’s causes of action pursuant to the Jones Act and Labor Law § 240 and the third-party complaint against G. Marine were dismissed, a bifurcated jury trial ensued. The trial court found that Hess owned the barge and dismissed the action against defendant Hygrade.

At the liability trial, Emanuel’s foreman, Roger Jones, the supervisor who instructed the rigging crew that day, testified that he put tag lines on each end of the gangway for the purpose of securing each end and that a vessel’s captain or first mate would grab the lines on the end that went on the vessel and would lash them off before the lines on the dock were secured. That was their job. Consistent with this practice, Jones told Emanuel, a novice at rigging, that after the crane swung the gangway over, he should yell to the barge’s captain and tell him to lash the gangway off, and Emanuel complied with this instruction.

Plaintiffs maritime expert witness, John Gartner, maintained that the barge, though emptied of its cargo and dry-docked for repair, remained in navigation and should have been manned by at least two crew members in accordance with the certificate of inspection issued by the Coast Guard. He further testified that while the shipyard provided the crane, according to customary [49]*49maritime practice, the obligation of securing the gangway to a vessel remained the vessel’s responsibility. Gartner explained that the gangway in question has one end that has rollers, and customarily it is that end that lands on the dock. The lashing is done on the vessel’s end. When the gangway is secured, the vessel’s crew member customarily supervises the release of the wiring from the gangway to the crane, which is done by a shipyard person. The vessel should have two crew members to secure the lashing on its end, which should just take 15 to 20 seconds.

The defense presented the testimony of G. Marine’s general manager, Joseph Ekhardt, as to the practices and procedures employed by the shipyard at the time of the accident. Ekhardt testified that once a vessel enters the graving dock it becomes the responsibility of the shipyard. The shipyard’s procedure for rigging a gangway was that the gangway would be hooked to the crane on the pier and the crane operator would lift it to the vessel. The roller end would land on the vessel and the gangway would be secured on the pier. When this was complete, the rigger would release the wires attaching the gangway to the crane. The guidelines on the ends of the gangway have nothing to do with lashing. The vessel crew has nothing to do with the placement of the gangway, which is the responsibility of the shipyard. However, the general manager was not present on the accident date and did not know how the gangway was rigged that date. He did not know if the roller end was placed on the barge or dock, and he never discussed with the riggers what they did that day.

At the liability trial, the jury found the barge unseaworthy and Hess and Spentonbush negligent. At the damages trial, the jury awarded plaintiff the principal amount of $24,967,660, which the trial court reduced to $7,613,566. Plaintiff consented to the remittitur under protest.

Hess and Spentonbush appeal and plaintiff cross-appeals from the judgment. The judgment brings up for review an order of the same court and Justice which dismissed plaintiff’s Jones Act and Labor Law § 240 claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schnapp v. Miller's Launch, Inc.
2017 NY Slip Op 2172 (Appellate Division of the Supreme Court of New York, 2017)
Heller v. Emanuel (In Re Emanuel)
450 B.R. 1 (S.D. New York, 2011)
In Re Emanuel
422 B.R. 443 (S.D. New York, 2009)
Emanuel v. Sheridan Transportation Corp.
58 A.D.3d 583 (Appellate Division of the Supreme Court of New York, 2009)
Lee v. Astoria Generating Co.
55 A.D.3d 124 (Appellate Division of the Supreme Court of New York, 2008)
Olsen v. James Miller Marine Service, Inc.
16 A.D.3d 169 (Appellate Division of the Supreme Court of New York, 2005)
McConville v. Reinauer Transportation Companies, L.P.
16 A.D.3d 387 (Appellate Division of the Supreme Court of New York, 2005)
Sweeney v. City of New York
2004 NY Slip Op 24196 (New York Supreme Court, Kings County, 2004)
Sweeney v. City of New York
4 Misc. 3d 834 (New York Supreme Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
10 A.D.3d 46, 779 N.Y.S.2d 168, 2004 N.Y. App. Div. LEXIS 6500, Counsel Stack Legal Research, https://law.counselstack.com/opinion/emanuel-v-sheridan-transportation-corp-nyappdiv-2004.