Ellison v. R & B CONTRACTING, INC.

32 S.W.3d 66, 2000 Ky. LEXIS 103, 2000 WL 1210973
CourtKentucky Supreme Court
DecidedAugust 24, 2000
Docket1998-SC-0535-DG, 1999-SC-0296-DG and 1999-SC-0302-DG
StatusPublished
Cited by49 cases

This text of 32 S.W.3d 66 (Ellison v. R & B CONTRACTING, INC.) is published on Counsel Stack Legal Research, covering Kentucky Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ellison v. R & B CONTRACTING, INC., 32 S.W.3d 66, 2000 Ky. LEXIS 103, 2000 WL 1210973 (Ky. 2000).

Opinions

KELLER, Justice.

ISSUE

This injury-to-property case between landowners and construction companies presents one primary issue and several lesser issues.

Landowners proved the cost of removing construction debris deposited on their property by the construction companies, but did not otherwise show a diminution in their property’s value. The construction companies’s expert witness, however, testified that the debris did not affect the property’s value. The Court of Appeals set aside the jury’s damage award and held that the trial court should have granted a directed verdict in favor of the companies as to the issue of damages when the plaintiffs failed to introduce direct evidence that the fair market value of the property had decreased. Were the construction companies entitled to a directed verdict on damages? Because we hold that the cost of removing the construction debris was sufficient evidence of diminution in property value, the trial court properly submitted the damages issue to the jury. Accordingly, we reverse the Court of Appeals and reinstate the jury’s verdict and damage award.

FACTUAL BACKGROUND

In 1991, the Kentucky Department of Transportation accepted a bid by Lawrence Construction and Leasing, Inc. (hereinafter “Lawrence Construction”) to perform contracting services on a multi-year construction project to widen and rebuild Kentucky Highway 17 in Northern Kentucky. Lawrence Construction subcontracted with R & B Contracting, Inc. (hereinafter “R & B Contracting”) for excavation work which included the disposal of waste materials (gravel, dirt, sand, and some paving) from Highway 17. R & B Contracting performed this work from approximately March of 1991 through December of 1992.

Gilbert and Bonnie Ellison and Howard and Agnes Sullivan (hereinafter, “the Elli-sons/Sullivans”), the plaintiffs below, owned a piece of property fronting the reconstructed Kentucky Highway 17. The Ellisons/Sullivans sued Lawrence Construction and R & B Construction for trespass and alleged that the two companies, without the Ellisons’/Sullivans’ consent, stored and serviced heavy equipment and deposited debris from the highway construction project on the Ellisons’/Sullivans’ property.

At trial, the Ellisons/Sullivans introduced testimony that large pieces of concrete and blacktop, culvert pipe, dirt and [69]*69gravel were deposited on the property. An expert witness who had examined topographical survey maps estimated on the basis of changes in the property contours between 1985 and 1995 that approximately 14,500 cubic yards of material had been added to the property. Other testimony established that R & B Construction employees drained oil onto the property from some of the heavy equipment and that Lawrence Construction left behind paint removed during sandblasting of construction equipment. Based on testimony suggesting it would cost the Ellisons/Sullivans ten cents (10$) per cubic yard to remove the material from their property, they asked for $145,000 in damages for the cost to return the property to its prior state.

Lawrence Construction and R & B Construction introduced testimony that the Ellison/Sullivans had given their permission both for the companies to store equipment on the property and for R <& B to deposit materials from the highway excavation as fill upon the property. An R & B representative testified that, while his company deposited highway waste material on the Ellisons’/Sullivans’ property, the volume of highway waste material involved was no more than 4,000 cubic yards.

The defendant construction companies also introduced the testimony of a real estate appraiser indicating that depositing waste material on the Ellisons’/Sullivans’ property resulted in no diminution in the value of the property and that its fair market value, therefore, did not change between the time immediately before and after the alleged trespass. Lawrence Construction and R & B Construction also disputed the Elhsons’/Sullivans’ figures regarding the cost of removing the material from the property and introduced testimony suggesting that the Ellisons/Sullivans could contract for the removal of the property at a price substantially less than ten cents (10$) per cubic yard.

The jury found for the Ellisons/Sullivans on the trespass issue by deciding that both Lawrence Construction and R & B Construction had, “without the express or implied consent of the Plaintiffs, deposited landfill material on Plaintiffs’ land.” The next question on the special verdict form asked the jury:

What sum of money do you find from the evidence is the cost of restoring Plaintiffs’ land to substantially the same condition as immediately before the dumping of the landfill material by the defendants, as described in the evidence, not to exceed the sum of $145,000.00?

The jury answered $72,500 and apportioned ninety-five percent (95%) of the fault to R & B Contracting and five percent (5%) of the fault to Lawrence Construction. The trial court entered judgment in accordance with the jury verdict and adjudged R & B Contracting hable to the Ehisons/Suhivans for $68,875 and Lawrence Construction hable to the Elli-sons/Sullivans in the amount of $3,625.

Before we address the specific legal issues before this Court in their current procedural posture, we feel it would be of benefit to the bench and bar to review the types of damages available to a claimant for injury to real estate. In cases such as the one before us, we have upheld two distinct types of damages: (1) if the injury to the property is permanent, the amount by which the fair market value of the property decreased immediately prior to and after the trespass;1 but (2) if the injury to the property is temporary, the cost to return it to its original state.2 We [70]*70have distinguished between “permanent” and “temporary” injuries on the basis of the cost of restoration and have held that injuries to real estate are “permanent” where the cost to restore the property to substantially its original state exceeds the amount by which the injury decreased the property’s value.3 Reasonable restoration costs are an available remedy only in “temporary” injury cases where the property may be restored to its original state at a cost less than the amount by which the market value of the property decreased as a result of the trespass.

As a practical matter, therefore, the amount by which the injury to the property diminishes its total value operates as an upper limit on any damage recovery. Claimants may receive restoration cost damages in injury-to-property cases only when compensation in the form of restoration costs is the least expensive way to make those claimants whole.4 This Court’s most recent opinions addressing the issue of the damages available in injury-to-property cases have sidestepped the “permanent” versus “temporary” distinction and focused on the way in which the amount by which the decrease in property value operates as a practical limit on the amount of recovery.5 We reiterate today, however, that cost to repair damages are available only where the factfinder determines that the injury to the property may properly be characterized as “temporary” by finding that the property may be restored at an expense less than the total amount by which the injury decreased the property’s value.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dennis Carlton v. James M. Poynter
Court of Appeals of Kentucky, 2026
David Vorherr v. Brett Coldiron
Court of Appeals of Kentucky, 2026
Albert Marshall v. Commonwealth of Kentucky
Court of Appeals of Kentucky, 2025
Lewis Logan v. Ralph Jeffrey Collins
Court of Appeals of Kentucky, 2023
Joyce Turner v. Norton Healthcare, Inc.
Kentucky Supreme Court, 2023
Rhonda Beinlein v. Kidz University, Inc.
Court of Appeals of Kentucky, 2023
Haley Belt v. Cincinnati Insurance Company
Kentucky Supreme Court, 2022
Cincinnati Insurance Company V Haley Belt
Kentucky Supreme Court, 2022
Robert Hill v. Christian County Quail Club, Inc.
Court of Appeals of Kentucky, 2021
Maria Chalk v. Robert Houp
Court of Appeals of Kentucky, 2021
Andrew McMichael v. Commonwealth of Kentucky
Court of Appeals of Kentucky, 2021
Rebecca Cardwell v. Commonwealth of Kentucky
Court of Appeals of Kentucky, 2021

Cite This Page — Counsel Stack

Bluebook (online)
32 S.W.3d 66, 2000 Ky. LEXIS 103, 2000 WL 1210973, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ellison-v-r-b-contracting-inc-ky-2000.