Ellefson Plumbing Co. v. Holmes & Narver Constructors, Inc.

143 F. Supp. 2d 652, 2000 WL 33324183
CourtDistrict Court, N.D. Mississippi
DecidedSeptember 26, 2000
Docket100CV149-D-D
StatusPublished

This text of 143 F. Supp. 2d 652 (Ellefson Plumbing Co. v. Holmes & Narver Constructors, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ellefson Plumbing Co. v. Holmes & Narver Constructors, Inc., 143 F. Supp. 2d 652, 2000 WL 33324183 (N.D. Miss. 2000).

Opinion

OPINION

DAVIDSON, District Judge.

Presently before the court is the Defendants’ motion to dismiss or, in the alternative, motion to compel arbitration and stay proceedings. Upon due consideration, the court finds that the motion should be granted. In accordance with the parties’ contract, the Plaintiffs claims shall be submitted to arbitration in Orange County, California, and this cause shall be dismissed without prejudice.

*654 A. Factual Background,

The Defendant Holmes & Narver Constructors, Inc. (Holmes) is the prime contractor on a federal construction project involving the replacement of several family housing units at Columbus Air Force Base in Columbus, Mississippi (the Project). In early 1999, Holmes entered into a subcontract with the Plaintiff, Ellefson Plumbing Co. (Ellefson), whereby Ellefson became the subcontractor for some of the plumbing work required on the Project.

Ellefson then commenced doing some preliminary work required on the Project and, on July 22,1999, and August 13, 1999, submitted invoices totaling $26,001.00 to Holmes for payment. Holmes did not pay Ellefson for the work. Later, on August 24, 1999, and August 26, 1999, Holmes and Ellefson entered into two separate “Temporary Agreements” that specified additional Project-related preliminary work that Holmes believed was necessary. El-lefson completed the work called for by the temporary agreements and, on September 7, 1999, submitted invoices totaling $8667.00 to Holmes for payment. Holmes did not pay Ellefson for the work.

On April 27, 2000, Ellefson filed the current suit contending that it is owed a total of $34,668.00 for the preliminary work it performed related to the Project. On June 2, 2000, Holmes filed a motion seeking to compel arbitration of Ellefson’s claims according to the terms of the Subcontract between the parties, and to have these proceedings dismissed or stayed.

B. Discussion

1. Validity of the Subcontract

Before the court can compel arbitration of Ellefson’s claims according to the terms of the Subcontract, the Subcontract itself must be valid and enforceable. Relying upon Attachment A to the Subcontract, 1 Ellefson contends that it merely conditionally signed the Subcontract and conditioned its acceptance and signature upon Holmes obtaining Air Force approval of certain proposed design changes to the plumbing structure. Thus, goes Ellefson’s argument, because the Air Force eventually declined to approve the proposed design changes, the Subcontract was never formed and is therefore unenforceable.

Ellefson’s argument, however, overstates the significance of Attachment A. A cursory review of Attachment A reveals that it merely conditioned the value or price of the Subcontract — not Ellefson’s execution of the Subcontract — on the Air Force accepting the proposed design changes to the plumbing structure. As such, the court holds that, although Attachment A was intended to allow Ellefson to change its price if the Air Force rejected the proposed design changes, it was not intended to invalidate the Subcontract or otherwise cause any of the additional terms of the Subcontract (such as the arbitration clause) to become unenforceable. The court holds, therefore, that the Subcontract is valid, enforceable and binding on the parties.

2. The Temporary Agreements

Ellefson’s next argument against its claims being arbitrable revolve around the fact that, after the Subcontract was entered into, Ellefson and Holmes entered into two Temporary Agreements that called for Ellefson to perform work not specifically called for by the Subcontract. *655 Ellefson argues that the present dispute is not governed by the Subcontract’s mandatory arbitration clause because its claims supposedly arise from Holmes’ alleged breach of these Temporary Agreements, as opposed to arising from Holmes’ breach of the Subcontract itself.

It is undoubtedly clear that all of the preliminary work Ellefson performed prior to the enactment of the Temporary Agreements was performed pursuant to the original Subcontract, because there was no other agreement in place at the time for the parties to perform under. Ellefson argues, however, that the work it performed pursuant to the Temporary Agreements is not covered by the Subcontract and is thus not subject to the Subcontract’s mandatory arbitration clause.

While it is undisputed that the Temporary Agreements expanded the scope of Ellefson’s work on the Project, the court declines to find that these Agreements constituted entirely new and separate subcontracts. The barebones nature of the Agreements, compared to the original Subcontract, and the Agreements’ lack of material terms commonly found in construction subcontracts, lead the court to hold that the Temporary Agreements related to and were a part of the underlying Subcontract, and were not entire new subcontracts in and of themselves. As such, the court finds that all of Ellefson’s work that is part of this claim was performed pursuant to the parties’ original Subcontract.

3. The Subcontract’s Arbitration Clause

The Federal Arbitration Act, 9 U.S.C. §§ 1 — 16 (1999), provides that, in a contract evidencing a transaction involving commerce, a written provision to settle by arbitration a controversy arising out of such contract is valid, irrevocable, and enforceable. 9 U.S.C. § 2 (1999). The Federal Arbitration Act expresses a strong national policy in favor of arbitration. Southland Corp. v. Keating, 465 U.S. 1, 10, 104 S.Ct. 852, 857, 79 L.Ed.2d 1 (1983). As such, any doubts concerning the scope of arbitrable issues should be resolved in favor of arbitration. Mouton v. Metropolitan Life Ins. Co., 147 F.3d 453, 456 (5th Cir.1998).

The Fifth Circuit has directed that courts are to perform a two-step inquiry to determine whether parties should be compelled to arbitrate a dispute. R.M. Perez & Assocs., Inc. v. Welch, 960 F.2d 534, 538 (5th Cir.1992). First, the court must determine whether the parties agreed to arbitrate the dispute. Once the court finds that the parties agreed to arbitrate, it must consider whether any federal statute or policy renders the claims nonarbitrable. R.M. Perez, 960 F.2d at 538. A party seeking to avoid arbitration must allege and prove that the arbitration clause itself was a product of fraud, coercion, o£ another ground allowing contract revocation that exists at law or in equity. Reisfeld & Son Import Co. v. S.A. Eteco, 530 F.2d 679, 680-81 (5th Cir.1976).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
143 F. Supp. 2d 652, 2000 WL 33324183, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ellefson-plumbing-co-v-holmes-narver-constructors-inc-msnd-2000.