Elizabeth H. Dole, Secretary of Labor v. Williams Enterprises, Inc., and Occupational Safety and Health Review Commission

876 F.2d 186, 278 U.S. App. D.C. 1
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 6, 1989
Docket88-1658
StatusPublished
Cited by19 cases

This text of 876 F.2d 186 (Elizabeth H. Dole, Secretary of Labor v. Williams Enterprises, Inc., and Occupational Safety and Health Review Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Elizabeth H. Dole, Secretary of Labor v. Williams Enterprises, Inc., and Occupational Safety and Health Review Commission, 876 F.2d 186, 278 U.S. App. D.C. 1 (D.C. Cir. 1989).

Opinion

Opinion for the Court filed by Chief Judge WALD.

WALD, Chief Judge:

The Secretary of Labor (“Secretary”) petitions for review of an order issued by the Occupational Safety and Health Review Commission (“OSHRC” or “Commission”) *187 under the Occupational Safety and Health Act (“OSHA”), 29 U.S.C. §§ 651-78, which vacated an abatement order issued by the Secretary against Williams Enterprises, Inc., for a violation of 29 C.F.R. § 1926.750(b)(l)(iii). We conclude that the Commission’s order was not in accordance with governing law, and we therefore remand this case with directions to reinstate and enforce the citation against Williams.

I. Background

Williams Enterprises, Inc. (“Williams”) was the steel erection subcontractor at the Intelsat building construction site located at 4000 Connecticut Avenue, N.W., in Washington, D.C. On May 6 and 7, 1987, OSHA Compliance Officer Wilfred C. Epps conducted an inspection at the Williams worksite to determine whether the working conditions conformed to governing safety regulations. Epps discovered, inter alia, that Williams had failed to install a perimeter cable along two exposed edges of the second tier of the building structure, despite the fact that a large portion of the floor of the second tier was covered with temporary metal decking. This failure placed Williams in violation of 29 C.F.R. § 1926.750(b)(l)(iii), which requires installation of a safety railing around the periphery of all temporary metal-decked floors in tier buildings. 1 Williams’ failure to install this protective measure left workers exposed to á fall hazard of 20 feet (at the southern exposure) to 30 feet (at the eastern exposure). Epps instructed Williams to abate the violation by installing a protective cable, and Williams did so. Epps proceeded to issue Williams a citation for violating the regulation, classifying the violation as “serious” as defined in section 17(k) of OSHA, 29 U.S.C. § 666(k).

Williams appealed. At the hearing before the OSHRC’s administrative law judge (“ALJ”), Williams targeted its questioning at two basic contentions. First, it sought to show that the tier at issue was not “fully decked” — i.e., that the temporary floor sheets had not all been put in place on the third level — in an effort to support its argument that § 1926.750(b)(l)(iii) by its own terms did not apply to Williams’ work-site. Second, it sought to elicit testimony that installation of the allegedly required safety cable in fact presented hazards to the workers responsible for doing the installation work.

The ALJ issued a brief opinion, Secretary of Labor v. Williams Enterprises, Inc., Docket No. 87-960, decision and order (O.S.H.R.C. (ALJ) July 11, 1988) (“ALJ op.”) (reprinted in the Joint Appendix (“J.A.”) at 35-42), in which he made the following relevant factual findings:

“3. The metal decking on the second tier was substantially complete. (Both Mr. Epps and [former Williams employee] Mr. Moore testified that the tier was 90% decked.... Mr. Graham [job foreman] testified that decking was 75% complete. ...) On the south and east sides of the second tier, decking was complete to the perimeter except for small triangular sections.” AU op. at 2 (J.A. at 36).
“5. There was no perimeter cable at the edges of the south and east sides of the second tier.... The fall distance from the south side of the tier was 20 feet to the mechanical room roof. From the east side, the fall distance was 30 feet to the ground.” AU op. at 3 (J.A. at 37).
“6. Respondent’s employees were exposed to a fall hazard when pulling up welding lead and using the ladder.” AU op. at 3 (J.A. at 37).
“7. Respondent’s employees were exposed to. a fall hazard when they installed cable on the south and east perimeters.” AU op. at 3 (J.A. at 37).
*188 “8. Respondent’s employees received a longer exposure to the fall hazard during installation of the guardrails than during the work that made the guardrails necessary. That part of the installation requiring Respondent’s employees to ‘coon’ across four- to eight-inch wide steel beams exposed Respondent’s employees to a more serious fall hazard than pulling up welding lead and using the ladder.” AU op. at 3-4 (J.A. at 37-38) (emphasis added).

Based on these factual findings, the AU determined that the regulation did apply to Williams’ worksite, AU op. at 5 (J.A. at 39), but nevertheless concluded that “entry of an abatement order requiring the installation of perimeter cable would not provide Respondent’s employees with ‘appropriate’ relief.” AU op. at 6 (J.A. at 40) (citing 29 U.S.C. § 659(c)).

The Secretary of Labor petitioned the full Commission for discretionary review of the AU’s decision, but no Commissioner directed review, and the AU’s order therefore became the final order of the Commission pursuant to 29 U.S.C. § 661(j).

II. Analysis

The Secretary argues that the Commission’s order effectively vacated the citation against Williams under a theory of “greater hazard,” but that the Commission did so without any regard whatsoever for the substantial body of law that has grown up around the “greater hazard” defense — law that, had it been observed, would have plainly precluded the doctrine’s application in this case. We agree.

“Greater hazard” refers to a well-established Commission doctrine that, in brief, allows employers to escape sanctions for violations of otherwise applicable safety regulations if they can establish that the act of abating a violation would itself pose an even greater threat to the safety and health of their employees. “Greater hazard” is an affirmative defense that is subject to certain specific pleading requirements under the Commission’s procedures. See 29 C.F.R. § 2200.36(b). Moreover, Commission precedent clearly requires that to prevail on the “greater hazard” defense, an employer must establish the three substantive elements of the defense: “(1) the hazards of compliance with a standard are greater than the hazards of noncompliance, (2) alternative means of protection are unavailable, and (3) a variance was unavailable or inappropriate.” Lauhoff Grain Co., 1986-1987 O.S.H. Dec. (CCH) II 27,814, at 26,397-98 (Rev. Comm’n 1987) (citations omitted). See also M.J. Lee Constr. Co., 1979 O.S.H. Dec. (CCH) 1J 23,330, at 28,227 (Rev. Comm’n 1979).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brackett v. Kelly
District of Columbia, 2021
Halbig v. Sebelius
27 F. Supp. 3d 1 (District of Columbia, 2014)
Abdul Al Qader Hussain v. Barack Obama
718 F.3d 964 (D.C. Circuit, 2013)
Sierra Club v. Jackson
District of Columbia, 2011
Walker v. England
590 F. Supp. 2d 113 (District of Columbia, 2008)
Lerner v. District of Columbia
362 F. Supp. 2d 149 (District of Columbia, 2005)
A.J. McNulty & Co. v. Secretary of Labor
283 F.3d 328 (D.C. Circuit, 2002)
Deer v. Cherokee County
183 F.R.D. 642 (N.D. Iowa, 1999)
Federal Election Commission v. Legi-Tech, Inc.
75 F.3d 704 (D.C. Circuit, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
876 F.2d 186, 278 U.S. App. D.C. 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/elizabeth-h-dole-secretary-of-labor-v-williams-enterprises-inc-and-cadc-1989.