Electricity Consumers Resource Council v. Federal Energy Regulatory Commission

747 F.2d 1511, 241 U.S. App. D.C. 397
CourtCourt of Appeals for the D.C. Circuit
DecidedNovember 20, 1984
DocketNos. 84-1006, 84-1007
StatusPublished
Cited by3 cases

This text of 747 F.2d 1511 (Electricity Consumers Resource Council v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Electricity Consumers Resource Council v. Federal Energy Regulatory Commission, 747 F.2d 1511, 241 U.S. App. D.C. 397 (D.C. Cir. 1984).

Opinions

Opinion for the Court PER CURIAM.

Separate concurring opinion filed by Senior Circuit Judge MacKINNON.

PER CURIAM:

Petitioners, the Electricity Consumers Resource Council (“ELCON”), an organization of large industrial users of electricity, and the Cities, Villages and Towns of Cedarburg, et al. (“the Cities”), a group of wholesale customers, challenge two orders of the Federal Energy Regulatory Commission (“FERC”). The first order, Opinion No. 186,1 accepted and adopted in full a new rate design proposed by the Wisconsin Electric Power Company (“WEPCO”), reversing the initial decision of the Administrative Law Judge (“AU”) on all issues.2 The second order, Opinion No. 186-A,3 denied rehearing on the ground that the rehearing applications raised no new issues. The principal issue presented by these consolidated appeals is whether FERC's finding — that WEPCO’s proposed new rate design .adopting two new pricing methods is just, reasonable, non-preferential and nonprejudicial — is based upon substantial evidence in the record and is within a zone of reasonableness.

This case arises under the Federal Power Act, 16 U.S.C. § 791a, et seq. (1982), (“the Act”), and associated regulations. Section 205(a) of the Act4 requires that all rates subject to the Commission’s jurisdiction be “just and reasonable,” and declares rates that do not meet these standards to be unlawful. In addition, section 205(b) mandates that rates not be unduly preferential [399]*399or prejudicial. Section 205(e) imposes on the public utility the burden of proving that any proposed rate is just and reasonable.

For the reasons set forth below, we affirm FERC’s implementation of the time-of-day pricing component of the new rate design but reverse FERC’s adoption of the marginal pricing component. We find that, with regard to the marginal pricing component, the Commission failed to comply with its statutory mandate to ensure that rates are just, reasonable, non-discriminatory and non-preferential. Moreover, we find that FERC both failed to offer a reasoned explanation for its decision and failed to develop record support, based on the facts of this case, for the adoption of the new marginal pricing ratemaking methodology. Accordingly, we remand this case for further proceedings consistent with this opinion.

I. BACKGROUND

On July 30, 1980, WEPCO filed a wholesale electric rate increase which was made the subject of a FERC investigation under section 205(e). All aspects of WEPCO’s rate proposal were satisfactorily resolved by settlement negotiations prior to hearing except for the two new concepts in the rate design that are at issue here: the substitution of time-of-day energy charges for unitary energy charges, and the use of marginal cost pricing concepts 5 instead of the traditional embedded or average cost pricing. The new rate design still recognizes two discrete types of costs: (1) demand or fixed costs, i.e., building and maintenance expenses, and (2) energy or variable costs, i.e., the cost of generating electricity.

Petitioners do not challenge the adoption of time-of-day rates in principle. Brief of ELCON, 32-33; Brief of the Cities, 59-60. They argue only that WEPCO has not offered sufficient evidence to support cost differentials in the periods chosen, and that neither Exhibit 5 nor Exhibit 32, offered as record support for the choice of peaking periods, suggests that a 12-hour peak period is justified. Id., J.A. 60-61. FERC, on the other hand, found the selection of peak periods to be reasonable and to be supported by substantial evidence on the record. J.A. 45. We agree and affirm this portion of FERC’s order.

Petitioners challenge the adoption of marginal cost pricing in this case on several grounds, the most important of which is that substantial adjustments to the theory were made in order to apply it to this case. These adjustments were necessary because of the “revenue constraint,” representing the maximum revenue collectable by the utility in a given period. In this case, the revenue constraint was determined according to the traditional ratemaking method of average costs. Consequently, if WEPCO collects the fixed costs allocated to wholesale customers by a demand charge and the variable costs by an energy charge under marginal cost pricing instead of average pricing, the total revenues generated will exceed the revenue constraint. Therefore, FERC approved the following reconciliation methodology: WEPCO would collect the entire marginal cost of energy and would consider any residual revenue collectable under the revenue constraint to be the demand charge. J.A. 22, 76. The resulting charges are not pegged to the demand or energy costs assigned to the customers in WEPCO’s cost-of-service study, and there are no demand charges for off-peak customers. J.A. 22-23.

II. DISCUSSION

A. Standard of Review

The scope of our review in this case is limited. We defer to the agency’s expertise, particularly where the statute prescribes few specific standards for the agency to follow, so long as its decision is supported by “substantial evidence” in the record and reached by “reasoned decision-making,” including an examination of the relevant data and a reasoned explanation supported by a stated connection between the facts found and the choice made. Burlington Truck Lines v. United States, 371 U.S. 156, 168, 83 S.Ct. 239, 245, 9 L.Ed.2d [400]*400207 (1962); Memphis Light, Gas and Water Division v. FPC, 504 F.2d 225, 230 (D.C.Cir.1974); 16 U.S.C. § 825l (1982). As this court recently stated in a case arising under the Natural Gas Act, which prescribes a similar “just and reasonable” standard:

This paucity of statutory guidance has resulted in judicial deference to administrative ratesetting. However deferential the judiciary may be, courts have never given regulators carte blanche ____ [T]he judiciary has inferred certain requirements from the “just and reasonable” standard [and] ... “[w]hat is basic is the requirement that there be support in the public record for what was done” ____ In reviewing the record, this Court engages in an inquiry akin to the “substantial evidence” inquiry mandated by the Administrative Procedure Act, 5 U.S.C. § 706(2)(E) (1976) .... Indeed, this Court has required the Commission to specify the evidence on which it relied and to explain how that evidence supports the conclusion it reached.

City of Charlottesville v. FERC, 661 F.2d 945, 949-50 (D.C.Cir.1981) (citations omitted).

B. FERC’s Order Fails to Comply With the Statutory Mandate to Determine Whether Rates are Just, Reasonable, Non-Discriminatory and Non-Preferential

The Commission relied exclusively on economic theory to justify the adoption of a rate design based on marginal costs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
747 F.2d 1511, 241 U.S. App. D.C. 397, Counsel Stack Legal Research, https://law.counselstack.com/opinion/electricity-consumers-resource-council-v-federal-energy-regulatory-cadc-1984.