Electri-Tech, Inc. v. H F Campbell Co.

445 N.W.2d 61, 433 Mich. 57
CourtMichigan Supreme Court
DecidedAugust 1, 1989
Docket81866, (Calendar No. 10)
StatusPublished
Cited by51 cases

This text of 445 N.W.2d 61 (Electri-Tech, Inc. v. H F Campbell Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Electri-Tech, Inc. v. H F Campbell Co., 445 N.W.2d 61, 433 Mich. 57 (Mich. 1989).

Opinions

Riley, C.J.

Plaintiff-appellant applied to the City of Westland for permission to construct a manufacturing plant on its property. In exchange for site-plan approval and a subsequent building permit, the city council demanded the dedication of a strip of land adjacent to Newburgh Road for an unrelated road-widening project. Although the plaintiff repeatedly requested that the council remove the restriction, it did not appeal the council’s decision to a higher city authority. Nor did the plaintiff attempt to have the restriction lifted by way of a circuit court injunction or declaration.

At a council meeting on June 11, 1979, the council approved the plaintiff’s site plan subject to five stated conditions, one being the dedication of land. The plaintiff refused to give away its property and submitted no revised site plan. Thus, the [61]*61proposed building was never erected. However, the City of Westland, through formal condemnation proceedings, eventually acquired the strip of land abutting Newburgh Road.

Later, the plaintiff brought an action against the city under 42 USC 1983, alleging that the city "took” its property without just compensation and without due process of law in violation of the Fifth and Fourteenth Amendments. We are asked, in this case, to determine whether this property owner is entitled to recover damages under 42 USC 1983 for the alleged taking caused by the "wrongful” denial of a building permit. Accordingly, we must first determine the procedural prerequisites for such an action and whether this plaintiff has met them.

We hold that before proceeding under 42 USC 1983, a property owner must first obtain a final decision from the particular governmental entity that is alleged to have unconstitutionally taken his property and also attempt to obtain just compensation through inverse condemnation. In the instant case, because the conditional approval of the plaintiff’s site plan was not the city’s final disposition of the matter, we hold that the plaintiff’s § 1983 claim was not ripe for adjudication. We need not reach, therefore, the question whether the council’s actions actually constituted a "taking” within the meaning of the Fifth and Fourteenth Amendments. We affirm the decision of the Court of Appeals that the trial court erred in permitting the plaintiff to proceed to trial on its § 1983 claim.

I. FACTS AND PROCEEDINGS

Plaintiff-appellant, Electro-Tech, Inc., manufactures electrical and electronic products. Much of [62]*62Electro-Tech’s business involves contracts with the United States military. The company’s manufacturing facility is located on Newburgh Road in the City of Westland.

Mr. Jack Beauchamp is the president and sole shareholder of Electro-Tech. In anticipation of securing additional contracts with the government and in order to more efficiently complete existing contracts, Mr. Beauchamp decided to build another manufacturing plant directly behind the existing facility. On October 26, 1978, Electro-Tech contracted with defendant, H. F. Campbell Company, to construct the new building. Pursuant to the agreement, Campbell was obligated to obtain a building permit and to complete construction by February 13,1979.

On or about March 3, 1979, Mr. Beauchamp approved Campbell’s site plan. However, before obtaining a building permit and actually beginning construction, Campbell was required to submit its plan for review by various city departments. The recommendations of these departments are then submitted to the planning commission for initial site-plan approval. The planning commission thereafter makes its recommendation to the city council for approval. After a site plan passes the council, the matter is finally submitted to the building department. The building department then examines the final site and building plans and, if approved, issues a building permit.1

On February 21, 1979, representatives of the various departments met to discuss Campbell’s proposed site plan. At that meeting, the representatives compiled a list of thirteen items which were required to be included in the site plan before submission to the planning commission and [63]*63city council. This list was forwarded by letter to Mr. Richard Wagner, the project director for Campbell. Although not included in the list, a recommendation was apparently made at this meeting to require, in exchange for site-plan approval and a subsequent building permit, the dedication of a twenty-seven-foot strip along the front of Electro-Tech’s property for the widening of Newburgh Road.2 The instant lawsuit concerns this dedication requirement.

On March 22, 1979, Mr. Wagner received a letter stating that the planning commission would recommend that the city council approve the site plan contingent upon, among other things, ElectroTech’s dedication of the strip adjacent to New-burgh Road. At trial, Mr. Beauchamp testified that, during the spring of 1979, he attended four or five council meetings protesting the city’s demand.

Nonetheless, at a meeting on June 11, 1979, with Mr. Beauchamp in attendance, the city council approved the site plan, subject to five stated contingencies:

1) Loading area should be clearly designated as such by striping and signage.
2) A second access door in the new addition is required along the north side of the building for fire protection.
3) Fire and Engineering requirements must be met on final engineering and building plans.
4) Dedication of 27 feet wide, approximately 210 feet in front of K2da for future Newburgh Road right-of-way.
5) The front greenbelt area is to be graded and sodded. [Emphasis added.]_

[64]*64Neither Campbell nor Electro-Tech attempted to appeal3 the decision of the city council or to take the matter directly to the building department. It is also established that Electro-Tech did not attempt to have the dedication condition removed by way of a circuit court injunction or declaration.

Soon after the meeting of June 11, however, Campbell began making revisions to the site plan to comply with the requests of the city council. Plaintiff claims that all of the contingencies except for the dedication were met. However, evidence adduced at trial suggests that Campbell never submitted a final site plan to the council or to the building department (which is ultimately responsible for issuing the building permit) and was, in fact, still revising through September of 1979.

Because of its failure to procure site-plan approval and a subsequent building permit, Campbell could not proceed with the construction of Electro-Tech’s new plant. Without the additional work space, Electro-Tech alleged it could not bid on several upcoming contracts and was forced to subcontract work on existing contracts in order to meet government deadlines.

On October 15, 1979, the City of Westland sent Electro-Tech a letter offering to purchase the strip of land abutting Newburgh Road. Mr. Beauchamp rejected the initial offer, maintaining that the proposed purchase price was too low. In January of 1980, the city filed a condemnation action in Wayne Circuit Court.4

On May 21, 1982, Electro-Tech brought this [65]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dennis O'Connor v. Rachael Eubanks
83 F.4th 1018 (Sixth Circuit, 2023)
Melissa Mays v. Governor Rick Snyder
Michigan Supreme Court, 2020
Gaspare Grimaldi v. Ohm
Michigan Court of Appeals, 2020
McCausland v. Canton
E.D. Michigan, 2019
Derek Campbell v. City of Hudson
Michigan Court of Appeals, 2017
Lakeside Resort LLC v. Crystal Township
Michigan Court of Appeals, 2016
Tini Bikinis-Saginaw, LLC v. Saginaw Charter Township
836 F. Supp. 2d 504 (E.D. Michigan, 2011)
Wiggins v. City of Burton
805 N.W.2d 517 (Michigan Court of Appeals, 2011)
Hendee v. Putnam Township
786 N.W.2d 521 (Michigan Supreme Court, 2010)
Blue Harvest, Inc. v. Department of Transportation
792 N.W.2d 798 (Michigan Court of Appeals, 2010)
Cummins v. Robinson Township
770 N.W.2d 421 (Michigan Court of Appeals, 2009)
Department of Transportation v. Tomkins
749 N.W.2d 716 (Michigan Supreme Court, 2008)
Ligon v. City of Detroit
739 N.W.2d 900 (Michigan Court of Appeals, 2007)
Dorman v. Township of Clinton
723 N.W.2d 905 (Michigan Supreme Court, 2006)
Department of Transportation v. Tomkins
715 N.W.2d 363 (Michigan Court of Appeals, 2006)
Cramer v. Vitale
359 F. Supp. 2d 621 (E.D. Michigan, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
445 N.W.2d 61, 433 Mich. 57, Counsel Stack Legal Research, https://law.counselstack.com/opinion/electri-tech-inc-v-h-f-campbell-co-mich-1989.