Eisenhart v. Puffer

2008 MT 58, 178 P.3d 139, 341 Mont. 508, 2008 Mont. LEXIS 59
CourtMontana Supreme Court
DecidedFebruary 20, 2008
Docket05-505
StatusPublished
Cited by6 cases

This text of 2008 MT 58 (Eisenhart v. Puffer) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eisenhart v. Puffer, 2008 MT 58, 178 P.3d 139, 341 Mont. 508, 2008 Mont. LEXIS 59 (Mo. 2008).

Opinion

JUSTICE MORRIS

delivered the Opinion of the Court.

¶1 John and Blanche Puffer (Puffers) appeal from several orders of the Eleventh Judicial District, Flathead County, denying a motion for substitution of judge filed by the Puffers’ surety, enforcing an arbitration award against the Puffers, awarding George Eisenhart (Eisenhart) attorney fees, and dismissing the Puffers’ counterclaims. We affirm.

¶2 The Puffers raise ten issues on appeal that we consolidate into the following issues:

¶3 Whether the District Court properly denied the request for substitution of judge filed by the Puffers’ surety.

¶4 Whether the District Court properly enforced the arbitration award against the Puffers and their surety.

¶5 Whether the District Court properly awarded attorney fees and costs to Eisenhart.

¶6 Whether the District Court properly dismissed the Puffers’ counterclaims.

PROCEDURAL AND FACTUAL BACKGROUND

¶7 The Puffers contracted with Eisenhart to build a house in Flathead County. The contract contained an arbitration provision. *510 Disagreement on the contract price prompted Eisenhart to file a construction lien on the property on August 22,2002. The Puffers filed a bond through their surety, Fidelity and Deposit Company of Maryland (F&D), on September 18, 2002, to release the construction lien. The dispute proceeded to arbitration. The arbitrator issued an award for Eisenhart.

¶8 Eisenhart filed a new action in District Court in August 2004, two years after receiving the arbitration award. In this new action, Eisenhart sought to foreclose the construction lien and sued for breach of contract, recovery pursuant to unjust enrichment, and for recovery in quantum meruit. The court consolidated this action with the original construction lien action Eisenhart filed in 2002. The District Court issued a final judgment on the arbitration award in favor of Eisenhart. The Puffers responded by moving to alter or amend the judgment and stay the proceedings. The Puffers also filed a counterclaim.

¶9 Eisenhart sought to enforce the judgment on the arbitration award against the Puffers and F&D. Eisenhart moved on May 31, 2005, for an order to show cause why F&D should not be liable for the amount awarded to Eisenhart. The court issued the order to show cause on June 17, 2005, and set a hearing date. Eisenhart alleges that the Puffers’ counsel refused to accept service on behalf of F&D, however, despite his representations that he also represented F&D. Eisenhart moved to continue the show cause hearing based on the Puffers’ counsel’s refusal to accept service. The District Court issued an amended order to show cause on June 28, 2005. The Puffers’ counsel finally appeared on behalf of F&D on July 12, 2005. The Puffers’ counsel filed a motion for substitution of judge on behalf of F&D three days later.

¶10 The District Court denied F&D’s motion for substitution of judge based on its determination that the Puffers’ right to file such a motion had expired. The court concluded that F&D, as the Puffers’ surety, possessed no independent right to file the motion under § 3-1-804, MCA. The District Court confirmed the arbitration award against the Puffers and F&D. The District Court confirmed Eisenhart’s attorney fees and costs associated with arbitration and enforcing the arbitration award. The District Court also dismissed the Puffers’ counterclaims after the Puffers had failed to respond to Eisenhart’s motion to dismiss.

*511 DISCUSSION

¶11 Whether the District Court properly denied the request for substitution of judge filed by the Puffers’ surety.

¶12 The Puffers argue that the District Court wrongly determined that F&D’s time for filing a motion for substitution of judge expired when the Puffers’ right to file this same motion expired. The Puffers maintain that F&D had an independent right to file the motion free from the Puffers’ time constraints. The Puffers point to the fact that F&D was not a named party to the action and had entered the action only by virtue of the order to show cause filed by Eisenhart. The Puffers contend that F&D’s timely exercise of its independent right to substitution pursuant to § 3-1-804, MCA, voided all orders entered after its filing.

¶13 A district court’s ruling on a motion to substitute a district court judge presents a question of law: We review a district court’s conclusions of law to determine whether they are correct. Mattson v. Montana Power Co., 2002 MT 113, ¶ 7, 309 Mont. 506, ¶ 7, 48 P.3d 34, ¶ 7.

¶14 Section 3-1-804, MCA, sets forth the procedure for substituting a presiding district court judge. A party must file a motion for substitution within thirty days after service of a summons or ten days after service of an order to show cause. Section 3-l-804(c), MCA. Subsequently joined parties generally are barred from filing a motion for substitution once the original party’s time has expired. Mattson, ¶¶ 13-14. An exception exists, however, when a subsequently joined party can demonstrate adversity with its co-party to the action. Goldman Sachs Group v. Mont. Second Dist. Court, 2002 MT 83, ¶ 17, 309 Mont. 289, ¶ 17, 46 P.3d 606, ¶ 17.

¶15 The District Court determined that no adversity existed between the Puffers and F&D. This absence of adversity rendered F&D’s motion -untimely in light of the fact that F&D filed its motion nearly a year after service of summons on the Puffers. The Puffers and F&D maintain, however, that they need not demonstrate adversity in order to establish an independent right to move for substitution of judge. They attempt to distinguish Goldman on the grounds that F&D was not a named party to the action and had entered the case pursuant to an order to show cause rather than by service of summons.

¶16 The Puffers’ attempt to distinguish Goldman proves unavailing. We refused in Mattson to consider the manner in which the moving party entered the action. We held instead that § 3-1-804(1) states on its face that “[o]nce the time expires for the original parties to move for *512 substitution, subsequently joined parties may not do so.” Mattson, ¶¶ 13-14. The fact that F&D was not a named party to the action and entered the case pursuant to an order to show cause is irrelevant.

¶17 Moreover, we agree with the District Court that F&D cannot demonstrate adversity. The construction lien statute, § 71-3-551(3), MCA, entitles a successful lien claimant to recover either from the principal or directly from the surety. Section 71-3-551(3), MCA, makes no distinction between the Puffers and F&D regarding liability for Eisenhart’s claim. F&D cannot demonstrate adversity with the Puffers under these circumstances.

¶18 F&D’s motion would have been untimely regardless of F&D’s ability to demonstrate adversity to the Puffers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marriage of Roadarmel
2025 MT 157N (Montana Supreme Court, 2025)
Ratliff v. Pearson
2011 MT 241 (Montana Supreme Court, 2011)
Patrick v. State
2011 MT 169 (Montana Supreme Court, 2011)
Blue Ridge Homes, Inc. v. Thein
2008 MT 264 (Montana Supreme Court, 2008)
Carvalho v. Thein
2008 MT 264 (Montana Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2008 MT 58, 178 P.3d 139, 341 Mont. 508, 2008 Mont. LEXIS 59, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eisenhart-v-puffer-mont-2008.