Eischeid v. Dover Construction, Inc.

265 F. Supp. 2d 1047, 2003 U.S. Dist. LEXIS 9328, 2003 WL 21272258
CourtDistrict Court, N.D. Iowa
DecidedJune 2, 2003
DocketC 00-4100-MWB
StatusPublished
Cited by1 cases

This text of 265 F. Supp. 2d 1047 (Eischeid v. Dover Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eischeid v. Dover Construction, Inc., 265 F. Supp. 2d 1047, 2003 U.S. Dist. LEXIS 9328, 2003 WL 21272258 (N.D. Iowa 2003).

Opinion

MEMORANDUM OPINION AND ORDER REGARDING SUMMARY JUDGMENT MOTIONS INVOLVING CLAIMS BY AND AGAINST WOODS MASONRY

BENNETT, Chief Judge.

TABLE OF CONTENTS

I. INTRODUCTION 1049

*1049 A. General Factual Background 05 O

B. Procedural Background. 05 rtf O

II. STANDARDS FOR SUMMARY JUDGMENT.1050

III. WOODS’S MOTION FOR SUMMARY JUDGMENT.1051

A. Eischeid’s “Direct” Claim Against Woods .1051

B. Dover’s Third-Party Claims Against Woods .1052

1. Pertinent factual context.1052

2. Arguments of the parties . 1053

3. Analysis .1054

a. Negligence and contribution claims.1054

b. Breach-of-contract claims.1054

c. Indemnity claims.1055

i. Scope and interpretation of indemnity agreements .1055

ii. The indemnity provision at issue .1056

iii. Is Dover’s indemnity claim “unenforceable”?.1056

iv. Procedure to determine extent of indemnity.1058

TV. DELOSS’S MOTION FOR SUMMARY JUDGMENT 05 LO O tH

A. Pertinent Factual Background. 05 DD O tH

B. Arguments Of The Parties. 05 LO O tH

C. Analysis. CD SO O t — I

V. CONCLUSION. .1061

I.INTRODUCTION

A. General Factual Background

In this lawsuit, plaintiff James Eischeid asserts claims arising from an accident at a construction site on March 17, 1999. Eischeid was working at the site as an employee of Woods Masonry, Inc. (Woods), which was, in turn, a subcontractor for masonry work on the construction project for the general contractor, Dover Construction, Inc. (Dover). Apparently because the construction project was behind schedule, Dover had also hired De-Loss Construction, Inc., to grout masonry walls as Woods completed the block work. Eischeid was seriously injured when an unbraced, ungrouted wall under construction on the project collapsed, apparently under the force of gusty winds.

B. Procedural Background

Eischeid filed this lawsuit on September 15, 2000, asserting claims of negligence and failure to maintain a safe workplace against Dover. Dover filed a third-party complaint against Woods on November 3, 2000, then an amended third-party complaint on December 20, 2000, asserting that Woods’s negligence caused Eischeid’s injuries; that Woods breached the subcontract, by failing to obtain workers’ compensation insurance, failing to comply with the plans and specifications, and failing to comply with OSHA safety regulations; and that Woods was required by the subcontract to indemnify Dover for any recovery Eischeid might receive against Dover. Eischeid eventually amended his complaint on March 19, 2001, to assert his own “direct” negligence claim against Woods, as well as a negligent design claim against the architects for the construction project, Otis, Koglin, Wilson Architects, Inc. On January 22, 2008, Eischeid dismissed his claims against the architects, leaving Dover and Woods as the only “direct” defendants. On August 7, 2002, Woods filed its own third-party complaint against DeLoss Construction, Inc., in which Woods alleges that DeLoss’s negligence caused all or part of Eischeid’s damages. *1050 This matter is now before the court on two motions for summary judgment. First, on March 25, 2003, Woods moved for summary judgment on Eischeid’s “direct” negligence claim against Woods and on Dover’s third-party claims of negligence, breach of contract, and indemnity against Woods asserting, in essence, that the “exclusive remedy” provisions of the Iowa Workers’ Compensation Act, IOWA CODE CH. 668, bar both Eischeid’s and Dover’s claims. Dover resisted Woods’s motion for summary judgment on April 11, 2003, but Eischeid has never responded to the motion. The second motion for summary judgment now before the court is third-party defendant DeLoss’s April 25, 2003, motion, in which DeLoss contends that Woods has conceded that DeLoss did nothing wrong and is not at fault for the injuries to Eischeid. Woods resisted De-Loss’s motion for summary judgment on May 15, 2003. These matters are now fully submitted and the court will consider them in turn. However, the court must first consider the standards applicable to these summary judgment motions.

II. STANDARDS FOR SUMMARY JUDGMENT

As this court has explained on a number of occasions, applying the standards of Rule 56 of the Federal Rules of Civil Procedure providing for summary judgment, the trial judge’s function at the summary judgment stage of the proceedings is not to weigh the evidence and determine the truth of the matter, but to determine whether there are genuine issues for trial. Quick v. Donaldson Co., 90 F.3d 1372, 1376-77 (8th Cir.1996); Johnson v. Enron Corp., 906 F.2d 1234, 1237 (8th Cir.1990). In reviewing the record, the court must view all the facts in the light most favorable to the nonmoving party and give that party the benefit of all reasonable inferences that can be drawn from the facts. See Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986); Quick, 90 F.3d at 1377 (same). Procedurally, the moving party bears “the initial responsibility of informing the district court of the basis for its motion and identifying those portions of the record which show lack of a genuine issue.” Hartnagel v. Norman, 953 F.2d 394, 395 (8th Cir.1992) (citing Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986)); see also Rose~Maston v. NME Hosps., Inc., 133 F.3d 1104, 1107 (8th Cir.1998); Reed v. Woodruff County, Ark., 7 F.3d 808, 810 (8th Cir.1993).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Auto Mutual Insurance v. Dover Construction, Inc.
273 F. Supp. 2d 1023 (N.D. Iowa, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
265 F. Supp. 2d 1047, 2003 U.S. Dist. LEXIS 9328, 2003 WL 21272258, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eischeid-v-dover-construction-inc-iand-2003.