Eischeid v. Dover Construction, Inc.

217 F.R.D. 448, 2003 U.S. Dist. LEXIS 14763, 2003 WL 22001192
District Court, N.D. Iowa·Decided August 25, 2003·No. No. C 00-4100-MWB·Published·Cited by 18 cases

Opinion

EXPEDITED MEMORANDUM OPINION AND ORDER REGARDING PLAINTIFF’S MOTIONS TO EXTEND DIS-POSITIVE MOTION DEADLINE, FOR SUMMARY JUDGMENT, TO SEVER, AND TO INTERVENE

BENNETT, Chief Judge.

TABLE OF CONTENTS

I. PROCEDURAL BACKGROUND............................................452

II. LEGAL ANALYSIS........................................................453

A. Motion To Extend Dispositive Motion Deadline ..........................453

1. Arguments of the parties.................................. 453

2. Analysis:..........................................................454

B. Motion For Summary Judgment ........................................456

1. Arguments of the parties............................................456

2. Analysis...........................................................457

a. Standards for summary judgment................................457

b. Factual background............................................458

c. Theories of liability ............................................459

i. “Control of the job” liability................................460

ii. “Contractual” liability.....................................463

C. Motions To Sever And To Intervene .....................................465

1. Arguments of the parties............................................465

2. Analysis...........................................................465

a. . Bifurcation or severance........................................465

b. Intervention...................................................467

III. CONCLUSION............................................................468

In this lawsuit, plaintiff James Eischeid asserts claims arising from an accident at a .construction site on March 17, 1999. Eis-[452]*452cheid was working at the site as an employee of Woods Masonry, Inc., which was, in turn, a subcontractor for masonry work on the construction project for the general contractor, Dover Construction, Inc. Apparently because the construction project was behind schedule, Dover had also hired DeLoss Construction, Inc., to grout masonry walls as Woods Masonry completed the block work. Eischeid was seriously injured when an unbraced, ungrouted wall under construction on the project collapsed, apparently under the force of gusty winds. Following this court’s June 2, 2003, ruling on motions for summary judgment regarding claims by and against Woods Masonry, the claims remaining in this action are Eischeid’s “direct” negligence action against defendant Dover, and the third-party indemnity claims by and between Dover, Woods Masonry, and DeLoss. Trial in this matter is set to begin on September 8, 2003. However, this matter comes before the court on four motions filed by Eischeid on July 29, 2003, which, if granted, would radically alter the issues and procedures for trial.

J. PROCEDURAL BACKGROUND

The four motions filed by Eischeid on July 29, 2003, are both “substantive” and “procedural” in nature. In light of the short time remaining before trial, the court entered an order on August 1, 2003, accelerating the deadline for resistances to Eischeid’s motions to August 11, 2003, and the deadline for any reply from Eischeid to August 15, 2003. The court also set oral arguments on the pending motions for August 21, 2003. The motions now before the court,1 and the parties’ various responses, are as follows:

The first motion now before the court— logically, if not by docket number—is Eis-cheid’s Motion For Extension Of Dispositive Motion Deadline (docket no. 106), in which he seeks an extension of the dispositive motion deadline from May 2, 2003, to July 29, 2003, so that his motion for summary judgment on the liability of defendant Dover can be considered by the court before trial. Dover resisted this motion on August 4, 2003. Third-party defendant Woods Masonry also filed a response to this motion, on August 11, 2003, stating that it neither resists nor joins in Eischeid’s request. Eischeid filed a reply to Dover’s resistance on August 15, 2003.

The second motion now before the court is Eischeid’s Motion For Summary Judgment (docket no. 105), which seeks summary judgment on the issue of liability on Eischeid’s “direct” negligence claim against Dover. If this motion is granted, it would leave for trial only the damages portion of Eischeid’s “direct” claim against Dover. Dover resisted this motion on August 11, 2003, and Eischeid filed a reply on August 15, 2003. Obviously, whether or not the court entertains Eis-cheid’s belated Motion For Summary Judgment depends upon whether or not the court grants his Motion For Extension Of Disposi-tive Motion Deadline.

The third motion now before the court— again, logically, if not by docket number—is Eischeid’s Motion To Sever Third-Party Claims (docket no. 108), and the last motion now before the court is Eischeid’s related Motion To Intervene In Third-Party Actions (docket no. 107), in which he seeks leave to intervene in the third-party action if that action is severed for a separate trial. Eis-cheid asserts that both of these motions are premised primarily on the assumption that the court will grant his motion for summary judgment on Dover’s liability. Third-party defendant DeLoss resisted both Eischeid’s Motion To Intervene and his Motion To Sever on August 8, 2003, as did defendant Dover on August 11, 2003. However, on August 11, 2003, third-party defendant Woods Masonry joined in Eischeid’s Motion To Sever and stated that, assuming the court grants Eis-cheid’s Motion To Sever, Woods Masonry has no objection to Eischeid’s intervention in the third-party actions, provided that a jury verdict in excess of one million dollars has been obtained against defendant Dover.

The court did, indeed, hear oral arguments on these four motions on August 21, 2003, as scheduled. At the oral arguments, plaintiff Eischeid was represented by N. Richard Wil-[453]*453lia and Steven J. Andreasen of Willia, Stable & Andreason, L.L.P., in Sioux City, Iowa. Defendant and third-party plaintiff Dover Construction, Inc., was represented by Paul D. Lundberg of the Lundberg Law Firm, P.L.C., in Sioux City, Iowa, and John C. Gray of Heidman, Redmond, Fredregill, Patterson, Plaza, Dykstra & Prahl, L.L.P., also in Sioux City, Iowa. Third-party defendant and third-party plaintiff Woods Masonry, Inc, was represented by Matthew T.E. Early of Rawlings, Nieland, Probasco, Killinger, Ellwanger, Jacobs & Mohrhauser in Sioux City, Iowa. Third-party defendant DeLoss Construction, Inc., was represented by Stephen F. Avery of Cornwall, Avery, Bjoms-tadt & Scott in Spencer, Iowa.

II. LEGAL ANALYSIS

Free access — add to your briefcase to read the full text and ask questions with AI

Eischeid v. Dover Construction, Inc., 217 F.R.D. 448, 2003 U.S. Dist. LEXIS 14763, 2003 WL 22001192 (N.D. Iowa 2003).

217 F.R.D. 448 (Eischeid v. Dover Construction, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Koffler v. Brown
S.D. Georgia, 2024
BUTLER v. PINERIO
S.D. Georgia, 2024
Kelly v. Ethicon, Inc.
N.D. Iowa, 2020
Langenbau v. Med-Trans Corp.
167 F. Supp. 3d 983 (N.D. Iowa, 2016)
Daniels ex rel. Y.A. v. City of Sioux City
294 F.R.D. 509 (N.D. Iowa, 2013)
Shannon v. Koehler
673 F. Supp. 2d 758 (N.D. Iowa, 2009)
Dayton Valley Investors, LLC v. Union Pacific Railroad
664 F. Supp. 2d 1174 (D. Nevada, 2009)
Kuiper v. Givaudan, Inc.
602 F. Supp. 2d 1036 (N.D. Iowa, 2009)
Animal Protection Institute v. Merriam
242 F.R.D. 524 (D. Minnesota, 2006)
Doctor John's, Inc. v. City of Sioux City, IA
438 F. Supp. 2d 1005 (N.D. Iowa, 2006)
Niver v. TRAVELERS INDEMNITY CO OF IL
430 F. Supp. 2d 852 (N.D. Iowa, 2006)
DP Wagner Manufacturing Inc. v. Pro Patch Systems, Inc.
434 F. Supp. 2d 445 (S.D. Texas, 2006)
Cochran v. Gehrke, Inc.
293 F. Supp. 2d 986 (N.D. Iowa, 2003)