E&I Global Energy Services v. Liberty Mutual Insurance Co.

134 F.4th 504
CourtCourt of Appeals for the Eighth Circuit
DecidedApril 4, 2025
Docket23-3739
StatusPublished
Cited by5 cases

This text of 134 F.4th 504 (E&I Global Energy Services v. Liberty Mutual Insurance Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E&I Global Energy Services v. Liberty Mutual Insurance Co., 134 F.4th 504 (8th Cir. 2025).

Opinion

United States Court of Appeals For the Eighth Circuit ___________________________

No. 23-3739 ___________________________

E&I Global Energy Services, Inc.; E&C Global, LLC

Plaintiffs - Appellants

v.

Liberty Mutual Insurance Company

Defendant - Appellee ____________

Appeal from United States District Court for the District of South Dakota - Southern ____________

Submitted: October 22, 2024 Filed: April 4, 2025 ____________

Before LOKEN, SMITH, and GRASZ, Circuit Judges. ____________

SMITH, Circuit Judge.

E&I Global Energy Services, Inc. and E&C Global, LCC (collectively, “Plaintiffs”) sued Liberty Mutual Insurance Company (Liberty), alleging several breach-of-contract and tort claims arising from Liberty’s promise to pay E&C for the completion of a construction project from which Plaintiffs were eventually terminated. The district court1 granted summary judgment for Liberty on Plaintiffs’ unjust enrichment claim, and after a bench trial, the district court found in Liberty’s favor on all remaining claims. On appeal, Plaintiffs argue that the district court erred in (1) denying Plaintiffs’ untimely request for a jury trial; (2) excluding an expert witness report filed after the expert report deadline; (3) finding that there was no evidence of an assignment of rights between E&C and E&I under the completion contract; (4) holding for Liberty on their fraud, deceit, and negligent misrepresentation claims; and (5) granting summary judgment for Liberty on their unjust enrichment claim. We affirm.

I. Background The United States, through the Western Area Power Administration (WAPA), contracted with Isolux to build the VT Hanlon Substation in Montrose, South Dakota. Liberty and the Insurance Company of the State of Pennsylvania (ISOP) (collectively, “Sureties”) issued a performance bond that guaranteed Isolux’s performance and a payment bond that guaranteed Isolux’s payment to its subcontractors and suppliers.

Jeff Bruce owns E&I and E&C, two distinct legal entities with different business operations. Isolux approached Bruce for help on the substation project. Upon agreement, E&I became a subcontractor of Isolux. In June 2016, E&I arrived onsite with supplies and equipment. Bruce testified that he found the project in disarray; he arrived on site with no plans, disks, drawings, or specifications. He viewed the project’s viability as uncertain.

In December 2016, WAPA terminated Isolux for failure to complete the project by the completion date. This termination triggered Liberty’s performance bond. Liberty, in search of a new completion contractor, hired Professional Construction Consulting (PC2) to investigate the project. David Mattingly, the PC2

1 The Honorable Karen E. Schreier, United States District Judge for the District of South Dakota. -2- vice president, visited the project site. Bruce introduced Mattingly to the project, gave Mattingly a tour, and showed Mattingly construction issues. Mattingly also met with WAPA representatives, including Jonathan Dittmer, WAPA’s contracting officer. Dittmer gave Mattingly four CDs with project information. The first CD contained drawings, specifications, and solicitations, which were then available online. The second CD contained aerial pictures of the site that lacked information about the materials onsite. The third and fourth CDs contained project submittals.2

After the visit, Mattingly, Bruce, and the PC2 president negotiated a completion contract in which the Sureties tendered E&C as the completion contractor to WAPA. During these negotiations, Bruce received documents and information, including a bill of materials that Bruce used to prepare his initial bid. Before the parties signed the completion contract but after E&C submitted some bids, Mattingly sent Bruce an email that said, “Jeff, [t]hese are the drawings that Jonathan [Dittmer] provided to me. Jonathan indicated they include all of the revisions to date.” R. Doc. 108-1, at 1. However, Mattingly did not give Bruce the four CDs. Mattingly testified that he believed Bruce had the submittals and that the contents of the first CD were available online. He also thought that Bruce had other documents and a good understanding of the project.

Bruce testified that he knew he was missing documents when negotiating the completion contract but bid anyway at WAPA’s direction. Bruce also testified that when he signed the completion contract, he noticed that the agreement listed E&C, his other company, as the completion contractor and asked Dittmer to change it to E&I, the correct company. Dittmer told him “not to worry” and that he would print a new document. R. Doc. 112, at 536. The agreement language was never corrected.

On March 28, 2017, the Sureties, E&C, and WAPA signed a tender agreement in which the Sureties tendered E&C to WAPA. This agreement fulfilled the Sureties’

2 “[S]ubmittals are documents that a contractor submits to an engineer or architect to confirm the contractor fully and accurately understands the various aspects of a project.” R. Doc. 118, at 10. -3- obligation under the performance bond but not the payment bond. The next day, the Sureties and Plaintiffs executed the completion contract that listed E&C as the completion contractor and E&I as a subcontractor. Under the agreement, E&C would finish the project, and Liberty promised to pay E&C the completion price. Liberty also promised to pay E&C for certain items excluded from the completion price. The completion contract had a non-assignment clause that said E&C had “no right to assign any of its rights or obligations hereunder without the prior written consent of [WAPA] and Sureties.” R. Doc. 108, at 149. On April 23, 2017, WAPA and E&I executed a follow-on contract in which E&I promised to complete the project.

Ultimately, E&I acted as the completion contractor because E&C could not obtain a bond required by the contract. In July 2017, Bruce sent Liberty a letter stating that Liberty owed E&I money under the completion contract for items excluded from the completion price. Carolyn Banks, a senior claims specialist at Liberty, responded in September 2017 and denied that Liberty owed E&I money. In this letter, Banks noted that the Sureties “tendered E&I, as completion contractor, to WAPA.” R. Doc. 109-1, at 769. Banks wrote on behalf of Liberty and ISOP, but ISOP did not sign the letter. In May 2018, WAPA terminated E&I for failure to complete the project by the completion date.

In February 2020, Plaintiffs sued Liberty for (1) breach of the completion contract, (2) breach of the implied covenant of good faith and fair dealing, (3) unjust enrichment, (4) fraud and deceit, and (5) negligent misrepresentation.

A. Jury Trial Demand The original complaint did not include a jury trial demand. In May 2020, Plaintiffs filed a discovery report with the district court. The discovery report acknowledged that the Plaintiffs failed to request a jury trial, said that they would file a motion under Federal Rule of Civil Procedure 39(b) to request a jury trial, and represented that Liberty would not oppose that motion. Plaintiffs, however, never

-4- filed a Rule 39(b) motion. They did file a second amended complaint in late 2021, but that complaint also did not include a jury demand.

In September 2022, the district court entered a scheduling order that set a jury trial date. In December 2022, Liberty, the defendant, filed a motion requesting that the court correct the scheduling order to reflect a bench trial because neither the original nor amended complaint included a jury trial request.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
134 F.4th 504, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ei-global-energy-services-v-liberty-mutual-insurance-co-ca8-2025.