E&I Global Energy Services, Inc. v. United States

CourtCourt of Appeals for the Federal Circuit
DecidedOctober 17, 2025
Docket24-1286
StatusUnpublished

This text of E&I Global Energy Services, Inc. v. United States (E&I Global Energy Services, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E&I Global Energy Services, Inc. v. United States, (Fed. Cir. 2025).

Opinion

Case: 24-1286 Document: 38 Page: 1 Filed: 10/17/2025

NOTE: This disposition is nonprecedential.

United States Court of Appeals for the Federal Circuit ______________________

E&I GLOBAL ENERGY SERVICES, INC., Plaintiff-Appellant

v.

UNITED STATES, Defendant-Appellee ______________________

2024-1286 ______________________

Appeal from the United States Court of Federal Claims in No. 1:19-cv-00244-DAT, Judge David A. Tapp. ______________________

Decided: October 17, 2025 ______________________

JOSEPH WHITCOMB, Whitcomb, Selinsky, PC, Lake- wood, CO, argued for plaintiff-appellant.

DAVID MICHAEL KERR, Commercial Litigation Branch, Civil Division, United States Department of Justice, Wash- ington, DC, argued for defendant-appellee. Also repre- sented by BRIAN M. BOYNTON, DEBORAH ANN BYNUM, PATRICIA M. MCCARTHY. ______________________

Before DYK, PROST, and STOLL, Circuit Judges. Case: 24-1286 Document: 38 Page: 2 Filed: 10/17/2025

2 E&I GLOBAL ENERGY SERVICES, INC. v. US

DYK, Circuit Judge. E&I Global Energy Services, Inc. (“E&I Global”) ap- peals from a decision of the United States Court of Federal Claims (“Claims Court”) granting the government’s motion for summary judgment. E&I Glob. Energy Servs., Inc. v. United States, 168 Fed. Cl. 206, 209 (2023) (“Claims Court Decision”). The case arose from an E&I Global con- tract with the United States Department of Energy’s West- ern Area Power Administration (“WAPA”) to construct a high-voltage electricity substation. WAPA terminated the contract for default for failure to complete construction in a timely manner. E&I Global brought suit in the Claims Court, claiming excusable delay and seeking conversion of the termination for default into termination for conven- ience. The Claims Court sustained WAPA’s decision to ter- minate the contract for default, finding that E&I Global’s contract performance failures were not caused by excusa- ble delays. Id. at 209. For the reasons explained below, we affirm in part, vacate in part, and remand for further pro- ceedings. BACKGROUND We have recounted many of the relevant facts in this case in a previous decision, E&I Glob. Energy Servs., Inc. v. United States, No. 2022-1472, 2022 WL 17998224 (Fed. Cir. Dec. 30, 2022) (nonprecedential) (“Federal Cir- cuit Remand”). Briefly stated, the facts are that in June 2015, WAPA solicited bids to construct a high-voltage elec- tricity substation in South Dakota. In September 2015, WAPA awarded the contract to Isolux Corsan, LLC (“Isolux”). The contract required Isolux to provide all labor, materials, and equipment necessary to construct the sub- station. Liberty Mutual Insurance Company and the In- surance Company of the State of Pennsylvania (collectively, the “Sureties”) issued bonds guaranteeing that the project would be completed and that Isolux’s un- fulfilled labor and materials obligations to third parties Case: 24-1286 Document: 38 Page: 3 Filed: 10/17/2025

E&I GLOBAL ENERGY SERVICES, INC. v. US 3

incurred in the performance of the project would be paid. WAPA terminated the contract with Isolux for default in December 2016. The Sureties assumed responsibility for performance and outstanding Isolux debts. In March 2017, the Sureties employed E&C Global, LLC to complete the project, entering into a “Completion Agreement” under which E&C Global, LLC was named as the “Completion Contractor” and agreed to complete the project, and the Sureties agreed to pay a firm- fixed price of $5,428,625.69 (the “completion price”). 1 J.A. 434–36. The appellant in this case, E&I Global (a dif- ferent entity than E&C Global, LLC), was named as a sub- contractor in the Completion Agreement. WAPA subsequently executed a new contract (the “E&I Global contract”) with E&I Global as the prime con- tractor. 2 On September 12, 2017, WAPA formally author- ized E&I Global to start work on the substation under the E&I Global contract. This authorization provided that E&I Global was required to complete construction of the substation by April 3, 2018. E&I Global alleges that it immediately ran into delays with the project. According to E&I Global, Isolux owed money to the subcontractors and suppliers on the project, and those subcontractors and suppliers refused to continue

1 Our previous decision in this case did not turn on any difference between E&I Global and E&C Global, LLC. We noted that “[t]he parties treat[ed] E&I [Global] and E&C [Global, LLC] . . . as identical” and so “we d[id] as well.” Federal Circuit Remand at *1 n.1. We did not decide whether the entities were the same. 2 The Sureties remained responsible for paying Isolux’s subcontractors and suppliers for work performed, or supplies purchased, before E&I Global took over the pro- ject. Case: 24-1286 Document: 38 Page: 4 Filed: 10/17/2025

4 E&I GLOBAL ENERGY SERVICES, INC. v. US

to work on the project until they were paid past due amounts. Though the Sureties were required to pay Isolux’s project-related debts, they allegedly failed to fulfill those obligations. To complete the project, E&I Global al- leged that it was required to pay the former Isolux suppli- ers and subcontractors what they claimed to be owed by Isolux. E&I Global asserts that these payments strained its finances and that as a result of these difficulties it missed the contract deadline. On April 3, 2018, the sched- uled completion date, construction was incomplete. In May 2018, WAPA terminated the E&I Global con- tract for default for failure to complete construction in a timely manner. On October 1, 2018, E&I Global submitted a certified Contracts Disputes Act claim seeking $3.6 mil- lion in damages and reversal of its default termination. The WAPA contracting officer denied E&I Global’s claim. E&I Global then brought suit in the Claims Court, seeking damages and conversion of the termination for default into termination for convenience. The Claims Court rejected E&I Global’s claims. The Claims Court granted the government’s motion to dismiss several claims, granted the government’s motion for sum- mary judgment as to others, and granted the government's motion for judgment on the pleadings as to E&I Global’s claim that the government improperly terminated the con- tract for default. Federal Circuit Remand at *2. Those rul- ings were appealed to this court. We affirmed many aspects of the Claims Court’s decision, but we reversed its dismissal of E&I Global’s claim that the government im- properly terminated the contract for default because the actions of other government contractors (i.e., the Sureties) caused the delay and remanded for further proceedings. Id. at *1. On remand, E&I Global continued to argue that the Sureties’ failure to pay Isolux’s debts to subcontractors and equipment suppliers led to excusable delay, because Case: 24-1286 Document: 38 Page: 5 Filed: 10/17/2025

E&I GLOBAL ENERGY SERVICES, INC. v. US 5

E&I Global instead paid those debts and, as a result, was financially unable to complete the project in a timely fash- ion. E&I Global also argued its delay was excusable be- cause the government allegedly failed to timely deliver wiring schematics for the construction project. The govern- ment moved for summary judgment, arguing that the un- disputed facts demonstrated that E&I Global’s performance failures were not caused by excusable delay because E&I Global was not the “Completion Contractor” in the agreement with the Sureties, E&I Global was not forced to pay Isolux’s debts, any delays caused by the sub- contractors or the absence of equipment were foreseeable and controllable, and E&I Global’s missing schematic ar- gument was not properly raised. The government provided no declarations to support its motion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dairyland Power Cooperative v. United States
16 F.3d 1197 (Federal Circuit, 1994)
Frankel v. United States
842 F.3d 1246 (Federal Circuit, 2016)
International Electronics Corp. v. United States
646 F.2d 496 (Court of Claims, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
E&I Global Energy Services, Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ei-global-energy-services-inc-v-united-states-cafc-2025.