Edward McLundie & Co. v. Mount

123 S.W. 966, 145 Mo. App. 660, 1909 Mo. App. LEXIS 335
CourtMissouri Court of Appeals
DecidedNovember 30, 1909
StatusPublished
Cited by10 cases

This text of 123 S.W. 966 (Edward McLundie & Co. v. Mount) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edward McLundie & Co. v. Mount, 123 S.W. 966, 145 Mo. App. 660, 1909 Mo. App. LEXIS 335 (Mo. Ct. App. 1909).

Opinion

GOODE, J.

Respondent does plumbing work and installs plumbing apparatus in buildings. In the year 1906, T. L. Houser, one of the original defendants [663]*663in the case, and respondent entered into a contract by ., which respondent undertook to do the plumbing work and furnish plumbing materials for a building on Arco avenue in the city of St. Louis between the Kingshighway and Taylor avenues. Houser was the contractor to erect the entire building. His contract was in writing, dated April 25,1906, and was executed by himself on one side and by Ida Mount, wife of J oseph Mount, appellant, and Gussie and Mamie Mount, sisters of appellant, on the other. The course of the title was shown by the deeds put in evidence and ran thus: On January 5, 1903, Joseph L. Mount and Ida Mount conveyed the lots to Joseph M. Grifdn; on July 5, 1906, Joseph M. Griffin conveyed them to Ida, Gussie and Mamie Mount; on August 3, 1906, Ida, Gussie and Mamie Mount conveyed them again to Joseph M. Griffin and on the same day Griffin conveyed them to appellant J oseph L. Mount. It will be perceived that when Houser contracted with the three Mount women to erect the building, the title to the premises stood in Jos. M. Griffin, but it was transferred by him to said women on July 5, 1906, during the progress of the work. Appellant negotiated the contract with Houser, but the latter testified he did not know the women were the owners of the property before the contract was signed, or know they were the parties named in the contract. In fact Mount acted for the women throughout the work and does yet, he says. Respondent’s contract with Houser was entered into May 1, 1906, and the plumbing work began pretty soon and continued through July, August and perhaps into October. Regarding Griffin’s title he (Griffin) testified he had had money transactions with Mount and the deed to him (Griffin) dated January 5, 1903, was executed by Mount and wife to pay a debt Mount owed him. He testified the property was his own and he could do with it as he chose. As we gather from Griffin’s testimony, he conveyed the property to Ida Mount, wife of appellant, and appellant’s two sisters, on [664]*664^July 5, 1906, by appellants direction and upon payment by them of five thousand dollars. Regarding the two subsequent conveyances of August 3, 1906, he said he did not remember the reasons for which the property was conveyed to him by the three Mount women and then conveyed by him to appellant. Appellant testified that when the contract for the erection of the house and the sub-contract for the plumbing were made, he had no financial interest in the property; that he originally conveyed the property to Griffin in payment of a debt and when it was conveyed by Griffin to the three Mount women, they furnished the consideration, having received it from their father’s estate; that it was also their money which went into the house. Plaintiff’s bill for work and material not having been paid in full, he filed a lien for the balance due, $300.65. The demand fell due December 8, 1906, and the lien was filed within four months, or on April 2, 1907. In the lien statement respondent described T. L. Houser as the contractor under whom he had done the work and Joseph L. Mount as owner of the property. On March 2, 1907, more than ten days prior to the filing of the lien account, respondent gave Joseph, L. Mount notice in writing of his claim against the premises, stating the amount claimed and that it was due from Houser. These facts are all alleged in the petition in the present case, and the lien account and notice of intention to file the lien, were put in evidence but are not set forth at large in the record, which recites the lien account was in proper form, contained the items described in the petition, was duly verified by affidavit and named Joseph L. Mount “as the contracting owner of the premises.” No declarations of law were given at the instance, of respondent and those requested by appellant were refused. Judgment was rendered in plaintiff’s favor for three hundred dollars, with interest at six per cent from April 2, 1907, a lien on the premises, for said amount was declared; and after appropriate [665]*665motions Mount appealed, but Houser submitted to a personal judgment against him. The court refused to declare, at appellant’s instance, that if plaintiff furnished the material and installed the same as stated in the petition, under contract with T. L. Houser and said Houser became indebted to plaintiff for the contract price thereof at any time on or about December 8. 1906, the verdict and finding should be in favor of Mount; that the indebtedness from Houser to plaintiff accrued when the work and material called for in the agreement between them was completed and when Houser accepted said work as completed, and if the court found the agreement for furnishing and installing the plumbing material was completed, and the last work done and the last materials furnished by December 8, 1906, then plaintiff was not entitled to a mechanic’s lien against the property of Mount even if Houser had failed to pay respondent in full.

Two defenses are insisted on: First, that notice of the lien claim was given only to appellant, whereas it should have been given to the three women who had contracted with Houser for the erection of the building' and owned an equitable estate in it at the date of that contract, and also at the date respondent sub-contracted with Houser; second, omitting to make those women defendants and instituting the action only against Houser, the main contractor, and appellant. The record owner of the premises at the date of the contract for the entire building, and also at the date of the sub-contract for the plumbing, was Joseph M. Griffin, and, and as we have seen, he testified he was absolute owner. It looks like there must have been some understanding between him and the women that he would convey the title to them upon payment of what Mount owed him, though this fact was not clearly proved. The first question for decision is whether the lien must fail because notice of the lien demand was not given to the women who -had contracted with Houser. The statutes [666]*666say every person, except the original contractor, who wishes to avail himself of the benefit of the lien law, shall give ten days’ notice, before the filing of his lien account and statement, to the owners of the building or improvement, or the owner’s agent, setting forth the amount he claims and from whom the same is due. [R. S. 1899, sec. 4221.] In Kuhleman v. Schuler, 35 Mo. 142, a local statute applicable to the city of St. Louis, but in its requirements about notice like the general statute in force to-day, was construed to require notice of the lien claim to be given to the person who owned the property at the time the contract for the improvement was made, and not to one who became owner during the progress of the work. The like construction was put upon the general mechanic’s lien law in Hewitt v. Truitt, 23 Mo. App. 443. Hence it was incumbent on respondent to give notice of his claim to the Mount women, as the owners of the property when both the original contract and his own contract were made, or to their agent. But appellants own testimony is that he was their agent throughout and there is nothing to the contrary in the record. Hence the notice to him fell within the very words of the statute, and the assignment of error regarding it must be overruled.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weyerhaeuser Co. v. Walters
707 P.2d 733 (Wyoming Supreme Court, 1985)
Structo Corp. v. Leverage Investment Enterprises, Ltd.
613 S.W.2d 197 (Missouri Court of Appeals, 1981)
Hertel Electric Company v. Gabriel
292 S.W.2d 95 (Missouri Court of Appeals, 1956)
Brace v. Gauger-Korsmo Const. Co.
36 F.2d 661 (Eighth Circuit, 1929)
R. D. Kurtz, Inc. v. Field
14 S.W.2d 9 (Missouri Court of Appeals, 1929)
American Radiator Co. v. Conner Plumbing & Heating Co.
211 S.W. 56 (Supreme Court of Missouri, 1919)
Hiller v. Schulte
167 S.W. 461 (Missouri Court of Appeals, 1913)
Hughes Bros. Paint & Hardware Co. v. Prewitt
157 S.W. 120 (Missouri Court of Appeals, 1913)
Eberle v. Drennan
1912 OK 795 (Supreme Court of Oklahoma, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
123 S.W. 966, 145 Mo. App. 660, 1909 Mo. App. LEXIS 335, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edward-mclundie-co-v-mount-moctapp-1909.