Hiller v. Schulte

167 S.W. 461, 184 Mo. App. 42, 1913 Mo. App. LEXIS 294
CourtMissouri Court of Appeals
DecidedDecember 31, 1913
StatusPublished
Cited by9 cases

This text of 167 S.W. 461 (Hiller v. Schulte) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hiller v. Schulte, 167 S.W. 461, 184 Mo. App. 42, 1913 Mo. App. LEXIS 294 (Mo. Ct. App. 1913).

Opinion

ALEEN, J.

This is an action to enforce a mechanic’s lien for work and labor done and materials furnished for and upon thirteen two-story brick buildings, and the lots of ground upon which they are situated, located in the city of St. Louis. The lien statement was filed on June 16, 1906, and states that the work and labor done and materials furnished, as shown by the account therein set forth, were furnished by the said lienor under contract with defendant Louis C. Schulte. The account itself runs against “Louis C. Schulte (M. P. Hynson, agent),” and is for certain furnaces and pipes and other accessories pertaining thereto, and for certain work and labor done in and about installing all of the same.

[44]*44Eleven of the buildings in question are upon contiguous lots fronting on Etzel avenue in the city of St. Louis, and two thereof upon adjacent lots fronting upon Clara avenue, and separated from the others by a private alley.

On September 13, 1906, plaintiff instituted this action to enforce the lien. In his petition filed at said time plaintiff named as defendants Louis O. Schulte, Montrose P. Hynson, W. M. McDade, F. W. Lovett, Chas. O. Nichols, trustee, and Frank C. Burdett. The original petition does not appear in the record. Subsequent to the institution of the suit, Hynson was adjudged a bankrupt, and on February 19, 1909, plaintiff filed what is designated as a“ statement of parties in interest,” and asked leave to make certain other persons defendants. The court granted this request, and on March 17, 19091, plaintiff filed an amended petition naming, in addition to the original defendants, the other parties as defendants in the cause, viz.: Wm, R. Orthwein, trustee in bankruptcy of M. P. Hynson, and certain other persons who were described in the amended petition as persons to whom' portions of the property had been conveyed, or who held deeds of trust thereon. The amended petition avers that, at the dates of furnishing the materials and labor in question, defendant Schulte held title to the property, but held it in fact in trust for Hynson, to whom it in reality belonged.

On behalf of all the parties who were made defendants on March 17, 1909, excepting défendaní Florence M. D'ale, demurrers were filed, upon the ground that they were not made parties within ninety days after the filing of the lien, and also, as to a part of them, that they were neither necessary nor proper parties defendant, having purchased after the filing of the lien. These demurrers were overruled. Florence M. Dale, who was made a party defendant by the amendment, filed a motion to dismiss as to her, [45]*45for the reason that it appeared from the record that the suit had not been instituted against her within the time required by law. This motion was also overruled. And as to the parties made defendant on March 17, 1909, the answers filed set up that the suit was not instituted against these defendants within the period allowed by the statute in which to institute an action for the enforcement of a mechanic’s lien after the filing of the same.

The cause was referred to Benj. J. Klene, of the St. Louis bar, to try all of the issues. The referee duly heard the testimony and filed his report in the cause, wherein he made a very complete finding of facts, and recommended a judgment sustaining the lien. The court overruled the exceptions filed to the referee’s report, and the case is here upon defendants’ appeal.

In the view which we take of the case, it is unnecessary for us to set out the rather lengthy findings of the referee; but we shall confine ourselves to such of the facts as are essential to the determination of the case as we view it.

On October 12, 1904, Schulte, who then held the title to the property, conveyed the various lots, described in plaintiff’s petition, by separate deeds of trust, to Ohas. C. Nichols, as trustee for Fred W. Lovett, to secure certain promissory notes. Thereafter the said buildings were erected on the various lots, and on June 2, 1905, defendant Schulte conveyed to Florence M. Dale one of these lots, with the house and other improvements thereon, subject to one of the aforesaid deeds of trust. At the time that defendant Florence M. Dale acquired this house, no furnace had been installed therein, and it appears that Hynson, for whom Schulte held the title, and who really owned the property, agreed with Mrs. Dale that a furnace would be provided and installed in it. Later this was done, at or about the time when the furnaces [46]*46were installed in the other buildings, to-wit, about November, 1905.

It is perfectly clear that the suit was not begun as to Florence M. Dale within ninety days after the filing of the lien as required by section 8228, Revised Statutes 1909. The action was instituted within the prescribed ninety days, to-wit, on September 13, 1906; but Florence M. Dale was not made a party thereto until March 17, 1909, about two and one-half years thereafter. And it is well settled that, where parties are thus brought in by an amendment, the suit as to them is begun at the time of such amendment making them parties. The amended petition as to them is the filing of a new suit. And, as an action to enforce a mechanic’s lien must be brought within ninety days after the filing of the lien, after the lapse of that time new parties cannot be brought in by amendment and be thus affected by'the proceeding. [See Lumber Co. v. Staley, 141 Mo. App. 295, 125 S. W. 779; Rumsey v. Pieffer, 108 Mo. App. 486, 83 S. W. 1027; Bombeck v. Devorss, 19 Mo. App. 38; Fury v. Boeckler, 6 Mo. App. 24; 27 Cyc. 344; Watson v. Gardner, 119 Ill. 312, 10 N. E. 192. See, also, Riverside Lumber Co. v. Schafer, 251 Mo. 539, 158 S. W. 340; Smith v. Barrett, 41 Mo. App. 460; Forrey v. Holmes, 65 Mo. App. 114; St. Joseph v. Baker, 86 Mo. App. 310; Jaicks v. Sullivan, 128 Mo. 177, 30 S. W. 890.]

In Fury v. Boeckler, supra, this court said:

“The proceeding is special, and the person who claims under it must bring himself within its special provisions. The ninety days after which no lien is to continue to exist, unless the conditions of the law are complied with, are not provided as a period of repose to bar actions; on the contrary, they are a limit to the existence of the lien.”

And as to the same effect is Lumber Co. v. Staley, supra, where the immediately foregoing excerpt is quoted approvingly. And such is likewise the [47]*47rule with respect to the existence of the lien of a special taxbill. [See Smith v. Barrett; Forrey v. Holmes; St. Joseph v. Baker; Jaicks v. Sullivan, supra.]

Though it is well established that the filing of the petition is the commencement of an action, and that the general rule is that subsequent amendments properly made to the petition relate back to the institution of the suit, nevertheless this is applicable only to the defendants originally sued, and not to new parties brought in by any such amendment. [See Jaicks v. Sullivan, supra, 128 Mo. 186, 30 S. W. 890.]

In the instant case it is beyond dispute that defendant Florence M. Dale, the owner of one of the thirteen lots, with the improvements thereon, described in plaintiff’s petition, and against which the lien is sought to be enforced, acquired her title thereto prior to the time when the lien, if any, attached to the same. She was not made a party to the suit within the prescribed time, and therefore is not affected by the proceeding; and, as to her property, the lien must fail.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.H. Berra Paving Co. v. City of Eureka
50 S.W.3d 358 (Missouri Court of Appeals, 2001)
Diamond Hill Investment Co v. Shelden
767 P.2d 1005 (Wyoming Supreme Court, 1989)
Seafirst Mortgage Corp. v. Specialty Concrete Construction
708 P.2d 1245 (Wyoming Supreme Court, 1985)
Advance Concrete & Asphalt Co. v. Ingels
556 S.W.2d 955 (Missouri Court of Appeals, 1977)
Daiprai v. Moberly Fuel & Transfer Co.
223 S.W.2d 474 (Supreme Court of Missouri, 1949)
Haney v. Thomson
98 S.W.2d 639 (Supreme Court of Missouri, 1936)
Peters v. Dona
54 P.2d 817 (Wyoming Supreme Court, 1936)
Gordon v. Hannaman
234 S.W. 569 (Court of Appeals of Texas, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
167 S.W. 461, 184 Mo. App. 42, 1913 Mo. App. LEXIS 294, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hiller-v-schulte-moctapp-1913.