EBI-Detroit, Inc. v. City of Detroit

279 F. App'x 340
CourtCourt of Appeals for the Sixth Circuit
DecidedMay 22, 2008
Docket07-1391
StatusUnpublished
Cited by42 cases

This text of 279 F. App'x 340 (EBI-Detroit, Inc. v. City of Detroit) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
EBI-Detroit, Inc. v. City of Detroit, 279 F. App'x 340 (6th Cir. 2008).

Opinion

BOGGS, Chief Judge.

Construction contractor EBI-Detroit appeals the district court’s grant of summary judgment in favor of the City of Detroit, the Detroit Water and Sewer Department (“DWSD”), Gary Fujita and Victor Mercado, two directors of DW SD, and Detroit’s mayor, Kwame Kilpatrick. EBI claims that the defendants breached a contract and committed various intentional torts when they rejected EBI’s bid on a DWSD project. The threshold question in this case is whether federal jurisdiction exists. We conclude that it does. EBI’s allegation that Kilpatrick acted outside the powers granted to him by a federal court requires us to interpret the federal court order and thus presents a federal question. The second, easier question is whether EBI’s claims can survive summary judgment. We conclude that they cannot, and therefore affirm.

I

Our jurisdiction turns on Kilpatrick’s appointment as “Special Administrator” of DWSD under a consent decree between DWSD and the EPA, so we summarize the extended litigation between those two parties. Thirty-one years ago, in 1977, the United States sued DWSD over DWSD’s noncompliance with the Clean Water Act (“EPA Case”). In September 1977, the parties entered a consent decree establishing a compliance schedule for bringing DWSD’s wastewater treatment and pollution discharges in line with the Clean Water Act. District Judge Feikens oversaw the initial consent decree, and he has continued to oversee the litigation surrounding DWSD and the EPA to this day. In 1979, Judge Feikens found that DWSD was not following the compliance schedule and appointed Coleman Young, the mayor of Detroit, as “Special Administrator” of the DWSD. United States v. City of Detroit, 476 F.Supp. 512 (E.D.Mich.1979). *343 This appointment gave the mayor power to “exercise extraordinary remedies in control, management, and operation of the Wastewater Treatment Plant” to ensure DWSD’s compliance, id. at 515, and allowed him “to enter into such contracts as he deems necessary and appropriate under the circumstances, with or without competitive bidding.” Id. at 516.

Since the initial consent decree, DWSD has drifted in and out of compliance with the Clean Water Act. During periods of compliance, Judge Feikens “temporarily suspended the Special Administratorship,” only to “revive” it when “compliance with the Clean Water Act or the Consent Judgments in this case was at risk.” United States v. Michigan, 409 F.Supp.2d 883, 886 (E.D.Mich.2006) (Feikens, J.). In August 1997, DWSD acknowledged that it was once again operating in violation of EPA regulations. Judge Feikens appointed a committee to investigate DWSD’s noncompliance. The committee issued its report in January 2000, and the court again responded by appointing Detroit’s mayor, Dennis Archer, as Special Administrator of DWSD. The court gave Archer the same powers it gave to Mayor Young in 1979. United States v. City of Detroit, No. 77-71100, 2000 WL 371795 (E.D.Mich. Feb. 7, 2000). DWSD’s contracts were “subject to the requirement of competitive bidding,” but the mayor could waive the bidding rules when he deemed it “necessary.” Id. at *5. On December 3, 2001, the court transferred the authority of the Special Administrator to Detroit’s new mayor, Kwame Kilpatrick.

This case arises from DWSD’s rejection of EBI’s bid on Contract PC-753, the Belle Isle Pump Station and Combined Sewer Overflow Control Improvements Project (the “Belle Isle Project”). The parties agree that the Belle Isle Project is required by DWSD’s EPA permit. DWSD’s Assistant Director Gary Fujita stated that the Belle Isle Project needed to be completed on a tight timetable to ensure compliance with the EPA’s consent decree. DWSD solicited bids on the Belle Isle Project, and, after equalization, the two lowest bids came from EBI, at $13,265,009, and from Walsh Construction, at $13,588,680. 1

DWSD made it clear that the Belle Isle Project would be awarded to the lowest bidder who was both responsive and responsible, “responsive” meaning that the bidder submitted a timely bid that conformed to DWSD’s request, and “responsible” meaning that the bidder’s record suggested that it could be expected to complete the project on time and in compliance with all relevant laws. DWSD sent EBI a letter on January 28, 2005, telling EBI that it was the lowest responsive bidder and that it needed to submit certain documents to prove that it was responsible. On February 4, 2005, EBI attended a bid evaluation meeting where EBI and DWSD discussed the items that EBI needed to submit. On March 21, 2005, DWSD’s director, Victor Mercado, sent EBI a letter stating that due to EBI’s deficient performance on an earlier project, the LH-391 Project, DWSD was deeming EBI a non-responsible bidder and awarding the contract to another bidder.

The LH-391 Project was also required by the consent decree, and EBI was the *344 design/build contractor for that project. While the LH-391 Project is not at issue in this case, it is relevant because EBI’s performance on it prompted DWSD to reject EBI’s bid on the Belle Isle Project. Both parties agree that serious problems arose on the LH-391 Project. It was supposed to be substantially completed by June 21, 2004, but was not substantially completed until July 2005. As expected, EBI and the defendants disagree over the source of the problems. EBI devotes three pages of its brief to explaining how the defendants falsely blamed EBI for problems that they created. The Defendants counter by pointing the finger at EBI. They also argue that because EBI has already sued DWSD in state court over the LH-391 Project, it should not be allowed to litigate the LH-391 Project in this case as well.

EBI responded to the rejection of its bid on the Belle Isle Project on March 29, 2005, by sending a letter claiming that the decision was unfair and requesting a protest hearing. Sections 13.2 and 13.3 of the bidding document state that if a bid is rejected, the bidder may file a protest, and DWSD will review the protest and “if necessary” hold a hearing on the matter within ten days. DWSD sent EBI a letter on April 19 pointing out the permissive nature of its hearing obligations and informing EBI that DWSD had determined that a hearing was not necessary. Instead, on June 9 Kilpatrick invoked his powers as Special Administrator of DWSD and awarded the contract to Walsh Construction.

EBI sued the defendants on September 25, 2006, in Wayne County Circuit Court, asserting claims for breach of contract, defamation, tortious interference, and “abuse of power by the Special Administrator” against Kilpatrick. On October 11, 2006, the defendants removed the case to federal court. The case was initially assigned to Judge Paul Gadola, but it was reassigned on November 1, 2006, to Judge Feikens in light of his role in overseeing DWSD. EBI filed a motion to remand the case to state court on October 30, but it was denied on December 6.

The defendants filed a motion for summary judgment on December 27, and on April 25, 2007, the district court granted the motion. Judge Feikens reasoned that EBI was merely a disappointed bidder and lacked standing to assert any of its claims. EBI appealed.

II

A

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
279 F. App'x 340, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ebi-detroit-inc-v-city-of-detroit-ca6-2008.