EBCO Construction Group, LLC v. Garretson (In Re Garretson)

377 B.R. 214, 2007 Bankr. LEXIS 3661, 49 Bankr. Ct. Dec. (CRR) 19, 2007 WL 3181300
CourtUnited States Bankruptcy Court, E.D. Arkansas
DecidedOctober 23, 2007
DocketBankruptcy No. 4:05-bk-25235 E, Adversary No. 4:06-ap-1049
StatusPublished
Cited by2 cases

This text of 377 B.R. 214 (EBCO Construction Group, LLC v. Garretson (In Re Garretson)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
EBCO Construction Group, LLC v. Garretson (In Re Garretson), 377 B.R. 214, 2007 Bankr. LEXIS 3661, 49 Bankr. Ct. Dec. (CRR) 19, 2007 WL 3181300 (Ark. 2007).

Opinion

ORDER DENYING PLAINTIFF’S SECOND MOTION FOR SUMMARY JUDGMENT

AUDREY R. EVANS, Bankruptcy Judge.

Plaintiff, EBCO Construction Group, LLC (hereafter referred to as “EBCO”), filed a Complaint to Determine Discharge-ability of Debt and Objection to Discharge on January 16, 2006. Pro se Defendant Jerry Garretson (hereafter referred to as “DPS” or “Drywall Painting Specialists, Inc.” or “Garretson”) filed an Answer on February 14, 2006. Now before the Court is the Second Motion for Summary Judgment and brief in support, filed by EBCO on August 2, 2007. 1 Garretson filed a Reply to the Second Motion for Summary Judgment and brief in support on October 1, 2007. EBCO filed a Reply to Defendant’s Reply to Second Motion for Summary Judgment and brief in support on October 12, 2007. Garretson filed a Response to Plaintiff’s Reply to Defendant’s Reply to Second Motion for Summary Judgment and brief in support on October 19, 2007. The parties did not request a hearing. The court has reviewed all relevant motions, briefs, responses and applicable law, and for the reasons stated herein, denies EBCO’s Second Motion for Summary Judgment.

FACTS

EBCO filed suit against Garretson on November 5, 2003, for breach of contract, in the Circuit Court of Miller County, Missouri (the “Missouri State Court”) (CV503-524CC). Garretson failed to file a *218 timely answer. On June 15, 2004, EBCO submitted a Request for Admissions and Garretson again failed to file a timely answer. Thereafter, on October 14, 2004, the Court granted an Interlocutory Default Judgment as to liability, and pursuant to Mo.R.Civ.P. 59.01, the submitted requests for admissions were deemed admitted. On February 17, 2005, EBCO moved for summary judgment (the “State Court Summary Judgment Motion”) against Garretson based on the following deemed admissions (as recited in EBCO’s State Court Summary Judgment Motion):

a. Prior to its dissolution, Garretson was a director and/or officer of DPS;
b. From and after the time that DPS was dissolved, Garretson continued to conduct business in the name of DPS;
c. The copy of the contract (“Exhibit A” hereto) is a true and accurate copy of the contract between DPS and EBCO on the Miller County Courthouse project.
d. After the original subcontract between EBCO and DPS was entered into, the three change orders included in Exhibit A hereto were executed and adjusted the amount of the subcontract to $348,098.86.
e. EBCO performed all conditions, covenants and promises required of it in accordance with the terms and conditions of such subcontract;
f. Certain work furnished and installed by DPS was defective and was repaired and/or replaced by EBCO;
g. DPS did not pay its suppliers and sub-subcontractors in full for work and/or materials provided to the Project.
h. DPS did not complete all of the work expected of it pursuant to its contract with EBCO.
i. EBCO informed DPS on several occasions that the manpower supplied by DPS for the Project was insufficient.
j. EBCO formally terminated DPS from the Project by the letter [sic] October 31, 2002 which was attached to the Request for Admissions as “Exhibit C.”
k. EBCO incurred the costs and expenses set forth in EBCO’s Petition in this matter as a result of DPS’ failure to complete and/or correct its deficient work on the Project.

EBCO claimed that based on these admissions, DPS breached the subcontract with EBCO in the following respects (as set forth in EBCO’s State Court Summary Judgment Motion):

a. DPS furnished and installed defective work which had to be repaired and/or replaced;
b. DPS failed to properly pay its suppliers and sub-subcontractors which required EBCO to pay such suppliers and sub-subcontractors in accordance with the payment bond EBCO was required to provide for the Project;
c. DPS failed to timely complete the work required of DPS in accordance with the subcontract; and
d. DPS failed to complete the work required of DPS under the subcontract which required EBCO to engage other subcontractors to complete the work of DPS.

In the State Court Summary Judgment Motion, EBCO alleges in Paragraph 2:

EBCO and DPS entered into that certain subcontract under which DPS agreed, inter alia, to furnish certain framing and drywall work in accordance with applicable plans and specifications for the sum of $350,000. A copy of *219 EBCO’s contract and change orders with DPS are attached hereto as “Exhibit A” and incorporated herein by this reference.

The Exhibit A attached to the copy of EBCO’s State Court Summary Judgment Motion is NOT a subcontract between DPS and EBCO (hereinafter referred to as the “Subcontract”). The attached Subcontract is between Otis Elevator Co. and EBCO, signed by a Gary Zimmerman on behalf of Otis Elevator Co. EBCO has not explained this discrepancy, and it raises serious concerns regarding the validity of the State Court judgment. Further, Garretson maintains in his Reply to the Second Motion for Summary Judgment filed in this adversary proceeding that neither he nor DPS ever had a contract with EBCO.

After Garretson did not appear at a hearing on EBCO’s motion for summary judgment, the Missouri State Court granted summary judgment in favor of EBCO on April 14, 2005, in the amount of $294,743.21.

On October 10, 2005, Garretson filed a voluntary petition for Chapter 7 relief in this Court.

LEGAL STANDARD FOR SUMMARY JUDGMENT

Rule 56 of the Federal Rules of Civil Procedure, as applied to these proceedings through Federal Rule of Bankruptcy Procedure 7056, provides that summary judgment shall be granted where the pleadings, depositions, answers to interrogatories, admissions or affidavits show that there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986); Burnette v. Dow Chemical Company, 849 F.2d 1269, 1273 (10th Cir.1988). “In determining whether a genuine question of material fact exists, this court is required to view the facts in [the] light most favorable to the nonmov-ing

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coleman v. Fields (In re Fields)
544 B.R. 156 (E.D. Arkansas, 2016)
Humes v. LVNV Funding, L.L.C. (In re Humes)
496 B.R. 557 (E.D. Arkansas, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
377 B.R. 214, 2007 Bankr. LEXIS 3661, 49 Bankr. Ct. Dec. (CRR) 19, 2007 WL 3181300, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ebco-construction-group-llc-v-garretson-in-re-garretson-areb-2007.