EB Ludwig Steel Corp. v. CJ Waddell Contractors, Inc.

534 So. 2d 1364, 1968 WL 1589
CourtLouisiana Court of Appeal
DecidedNovember 16, 1988
Docket88-CA-379 to 88-CA-382
StatusPublished
Cited by5 cases

This text of 534 So. 2d 1364 (EB Ludwig Steel Corp. v. CJ Waddell Contractors, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
EB Ludwig Steel Corp. v. CJ Waddell Contractors, Inc., 534 So. 2d 1364, 1968 WL 1589 (La. Ct. App. 1988).

Opinion

534 So.2d 1364 (1988)

E.B. LUDWIG STEEL CORPORATION
v.
C.J. WADDELL CONTRACTORS, INC. and Fidelity & Deposit Company of Maryland.
The NEW ORLEANS CATHOLIC CHURCH OF THE ARCHDIOCESE OF NEW ORLEANS
v.
C.J. WADDELL CONTRACTORS, INC., and Fidelity and Deposit Company of Maryland, et al.
C.J. WADDELL CONTRACTORS, INC.
v.
The ROMAN CATHOLIC CHURCH, ARCHDIOCESE OF NEW ORLEANS, et al.
ALL AMERICAN DECORATING SERVICE, INC.
v.
C.J. WADDELL CONTRACTORS, INC., and Fidelity and Deposit Company of Maryland.

Nos. 88-CA-379 to 88-CA-382.

Court of Appeal of Louisiana, Fifth Circuit.

November 16, 1988.
Writ Denied January 20, 1989.

*1365 Elsie B. Halford, Metairie, for defendant/appellee.

Denechaud and Denechaud, New Orleans, for plaintiff/appellant.

Before BOWES, GRISBAUM, and GOTHARD, JJ.

GOTHARD, Judge.

This consolidated suit arises from a controversy between the owners, the general contractor, and the various subcontractors on a private building project.

The Archdiocese of New Orleans entered into a contract with C.J. Waddell Contractors, Inc., of which C.J. Waddell was owner and principal shareholder, to build additions to and renovate existing buildings at the Our Lady of Divine Providence parish school (hereafter "School") in Kenner. The contract was signed on June 18, 1984 and the job was to be completed by December 8, 1984, later extended to December 14. Completion was delayed and on February 4, 1985 Waddell was terminated as contractor, with notice to the bonding company, Fidelity & Deposit Company of Maryland.

The contract price, including change orders, was $253,008.39. Under the contract the Archdiocese was to make periodic payments for the work completed at the end of each month minus a retainage of 10%, pending final acceptance. At the time Waddell was terminated the Archdiocese had paid him $172,763.68, leaving a balance of $80,244.71 due on the contract. The Archdiocese retained the balance, alleging that it was entitled to the retainage to cover the cost of completion by another contractor and liquidated damages for the delay at the rate of $200 per day as provided in the contract.

After accepting the project, on June 21, 1985 the Archdiocese filed a petition for a concursus and deposited $6,122.88 into the registry of the court for the benefit of the contractor, surety, and subcontractors, etc. The Archdiocese sought by this means to have all liens and privileges on the property cancelled and to be released from liability for any further claims arising from the building contract. The Archdiocese also demanded costs and attorneys' fees. Prior to the concursus petition, E.B. Ludwig Steel Corporation, supplier of the steel components of the buildings, and All American Decorating Service, Inc., the painting contractor, had filed suits against C.J. Waddell Contractors, Inc., and Fidelity & Deposit Corporation of Maryland, seeking payment. Following the Archdiocese's *1366 suit, Waddell sued the Archdiocese for the balance of the contract price.

The suits were ordered consolidated for trial and were heard by a judge in two segments on February 11 through 13, 1987 and June 16 through 19, 1987. An amended judgment was signed on November 18, 1987 in which the court rendered judgment in favor of various subcontractors and suppliers against C.J. Waddell Contractors, Inc. and Fidelity & Deposit Company of Maryland for the stipulated amounts of their claims. An additional award was made to all American Decorating against the Archdiocese in the amount of $5,096.00.

Judgment was rendered also in favor of C.J. Waddell Contractors, Inc. and against the Archdiocese in the amount of $219,644.71 plus legal interest from date of judicial demand. All costs were to be borne by the Archdiocese. In his reasons for judgment the trial judge stated that he found the project was substantially complete when Waddell was terminated. He found that the delays were not caused by Waddell but by the failure of the Archdiocese to appoint another architect to replace the project architect who became gravely ill. He explained that he calculated the award to Waddell as follows: From the balance due on the contract, $80,244.71, he deducted $5,000 which was needed to complete the work and $5,600 to repair and replace a roof, leaving a balance of $69,644.71. He then added $150,000 in damages to Waddell for loss of his construction business because of the breach of contract by the Archdiocese and arrived at a total of $219,644.71. The Archdiocese appealed suspensively and Waddell answered the appeal.

Issues raised by the Archdiocese are as follows: 1) whether a contractor is entitled to an award of "exemplary damages" for loss of future business under Louisiana law; 2) whether the Archdiocese was legally entitled to terminate Waddell's employment and retain an amount from the balance due on the contract sufficient to pay another contractor to complete the job; 3) whether the Archdiocese was entitled to recover liquidated damages; and 4) whether the actions or inactions of the architect or owner were in fact the cause of the delay or whether the delay was caused by factors within the control of the contractor.

In answering the appeal Waddell seeks an increase in the award of the balance due on the contract to $77,744 and an award of attorney's fees of $25,000 for bad faith breach of contract.

RESPONSIBILITY FOR THE DELAY IN COMPLETION.

We consider first the issue of whether the owner or the contractor caused the delay, as that determination of fact has a bearing on all other issues. James D. Carter was the project architect who prepared the plans and specifications and who was responsible for supervision of the job. Work began on July 12, 1984. At some point between that date and mid-September Mr. Carter was found to be gravely ill and on September 17 he asked the School building committee to cancel his contract and replace him. The Archdiocese chose not to honor his request and instead appointed Roy Burst to represent the architect in the field as of September 26, 1988. Burst was not an architect but was a long time employee of the Port of New Orleans who had for many years inspected Port facilities for damage. He testified that he was hired part time to visit the site as needed, to assist Mr. Carter in reviewing shop drawings, writing letters, and making copies and deliveries. He generally visited the job at noon or after work and reported to Mr. Carter at his home. Waddell and his superintendant, Mike King, were instructed not to deal directly with Mr. Carter, only with Burst.

Mr. Carter's deposition was taken on June 21, 1985 and was admitted into evidence in lieu of testimony as he died before trial. In it he stated that he was completely incapacitated during the months of November, December, and January but still made all decisions himself, based on information provided by Burst. He had Burst sign his letters as a convenience so Burst *1367 would not have to make a return trip after they were typed. Burst admitted at trial that during the fall Carter was virtually blind and he not only signed Carter's name but described to him items on E.B. Ludwig's shop drawings submitted for Carter's approval as early as October. We assume that Burst actually reviewed the drawings. He had difficulty in interpreting some items and asked for details to be drawn, apparently unaware that the components were detailed in the steel supplier's standard detail book, which had been delivered to Mr. Carter in September. The deposition of Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pipe Liners, Inc. v. Edenwald Contracting Co.
610 So. 2d 1109 (Louisiana Court of Appeal, 1992)
Usner v. Strobach
591 So. 2d 713 (Louisiana Court of Appeal, 1991)
Brill v. Catfish Shaks of America, Inc.
727 F. Supp. 1035 (E.D. Louisiana, 1989)
E.B. Ludwig Steel Corp. v. C.J. Waddell Contractors, Inc.
536 So. 2d 1239 (Supreme Court of Louisiana, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
534 So. 2d 1364, 1968 WL 1589, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eb-ludwig-steel-corp-v-cj-waddell-contractors-inc-lactapp-1988.