Eatonton Oil & Auto Co. v. Greene County

185 S.E. 296, 53 Ga. App. 145, 1936 Ga. App. LEXIS 28
CourtCourt of Appeals of Georgia
DecidedMarch 14, 1936
Docket23937
StatusPublished
Cited by8 cases

This text of 185 S.E. 296 (Eatonton Oil & Auto Co. v. Greene County) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eatonton Oil & Auto Co. v. Greene County, 185 S.E. 296, 53 Ga. App. 145, 1936 Ga. App. LEXIS 28 (Ga. Ct. App. 1936).

Opinions

Stephens, J.

Eatonton Oil and Auto Company brought suit against Greene County to recover for the cost of gas, oil, etc., which the plaintiff had furnished to E. S. Taylor Incorporated, and which went into the construction of a road which E. S. Taylor Incorporated was building under a contract with Greene County and Oconee County. The plaintiff brought the suit in three counts as will hereinafter be more particularly set out. The undisputed facts were about as follows: Greene County made a contract with the State Highway Board for the construction of a road designated as Project 228-A on Route No. 15. One of its terms required the county to work twenty convicts (with two guards) on the proposed road. The county then contracted with R. S. Taylor Incorporated to do certain excavating, clearing and grubbing, top-soiling and concrete work, according to the plans and specifications of the highway board and under their direction. Taylor further agreed to employ in the "work, on every day that work was done, twenty convicts and two guards, each convict to be paid at the rate of $1.50 per day and each guard at the rate of $2.50 per day; and to furnish a surety bond conditioned on compliance with the terms of the contract, etc., "which bond shall be construed to be a compliance with the acts of the legislature approved August 19th, 1916,” and that the county should have the option to pay each estimate of work done (made by the highway board) on the first of each following month, at a discount of eight per cent.; and that the county should have the option to furnish money to meet pay rolls, pay for material, etc., before estimates were made, such sums to be deducted [147]*147from the amount due on such estimate “before any other payment either to second party or its order is made.” For some reason the Taylor Company was unable to give the bond required. Notwithstanding this, the.county permitted it to go ahead with the work and cooperated by furnishing the convicts, making advances, paying orders, etc. Taylor Company bought from Eatonton Oil and Auto Company large quantities of gasoline, oil, kerosene, and other materials which were used for the operation of the machinery employed in the work. The account for these materials amounted to $3553.96 from October 7, to December 28, 1931. On January 14, 1932, the Eatonton Company presented an order to the county from the Taylor Company requesting payment to the Eatonton Company of $3553.96 out of payments when and as due to the Taylor Company according to estimates of the State Highway Department, “this order subject to such other orders as may have been accepted for pajunent by you,” etc. This order was accepted by the county in the following terms: “accepted and payment promised accordr ing to the terms and conditions of said order, upon the express condition that payment is to be made only from such amounts as may be due the signers of said order under the .terms of employment between such signers and this county, and at such times as payment may be due under such terms; this writing making no original undertaking as to any payment, and not being so construed; and no liability hereunder is intended other than to make pajunents to the said grantee in the above order, if, when, and as such may be due the signers above; and provided expressly, further, that this acceptance is subject to all such orders and acceptances of prior date hereto, and to repayments to Greene County for all advances of money and supplies made to E. S. Taylor Inc., or which may be made from time to time in pursuance with the agreement between E. S. Taylor Inc. and this county, and subject to any other claims which may have precedence by law.”

After this the Eatonton Company continued to supply gasoline, etc., to the Taylor Company. On February 1, 1932, Eatonton Company solicited of the county a part payment on the order of January 14. After considerable discussion between the parties in which some question was raised as to the liability of the county, the county paid $1800 to the Eatonton Company itpon receiving from it a paper acknowledging payment of the $1800 as a credit on the [148]*148order of January 14, and as an advance to E. S. Taylor Inc. and continuing: “The undersigned freely admits and here states that it has no claim or demand for any amount due by E. S. Taylor Inc., for gas and oil used on the Watson Springs project, other'than as set out in the said order; and does hereby in consideration of said payment and the advantages received therefrom, and of $1 further paid, and of the acceptance by said county of said order, expressly relieve and release said Greene County, and the Board of Roads and Revenues thereof, from any and all claim, debt, or liability of any sort other than as represented by said order, and does not hold said county or .said board in any way responsible for the debts of said E. S. Taylor Inc., other than as stated. It is further agreed, in consideration of said payments made, that if any retention payments (held up under estimates and to be later paid Taylor Inc.) pass under any prior orders, such is satisfactory to the undersigned, all orders to speak for themselves."

The Eatonton Company continued to supply gasoline, etc., to the Taylor Company until March 23, 1932, when the total amounted to $5433.81. The Eatonton Company rendered a bill to the county, payment of which was refused, and suit was brought against the county and the county commissioners. The petition was in three counts, the first being predicated on the acceptance of January 14, 1932, on which it was alleged a balance of $1753.96 was due, after crediting the $1800 paid the plaintiff on February 1. The second count sought recovery of this $1753.96 on the ground of the liability under the act of August 19, 1916 (Ga. L. 1916, p. 94, Code of 1933, § 23-1705 et seq.) imposed on any county or other public body which contracts for a public work without taking bond from the contractor. The third count, based on the same statutory liability, alleged that $1879.85 worth of gasoline, etc., was supplied to the Taylor Company between January 1, and March 23, 1932, of which an amount worth $939.92 was used in an Oconee County project, leaving a balance due the plaintiff of $939.93. This count was amended, allegedly to correct an error, so as to claim that the amount of gasoline diverted to Oconee County was $474.42, whereby the amount due the plaintiff under this count was $1405.43. A further amendment of counts 2 and 3 claimed that the $474.42 collected by the plaintiff from Oconee County, if not allowed ás a credit to Greene County against the account sued for in count 3, [149]*149should be credited pro rata against the accounts suéd on in counts 2 and 3.

The county answered count 1, admitting that bond was not given by the contractor, admitting acceptance of the order of January 14th, denying that any sum was due thereunder to the plaintiff, and setting up the receipt of February 1, -as a complete release from liability of any sort on account of materials furnished by the plaintiff to the contractor except such sums as might be due under the original order; alleging that no amount had become due under such order, and denying that gas and oil were such materials as the county would be liable for by reason of failing to take bond from the contractor. Counts 2 and 3 of the petition were answered in substantially the same terms as count 1, with the additional claim that the order and acceptance of January 14, constituted a special contract by which the plaintiff waived the failure of the county to take bond from the contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

U.S. Anchor Mfg., Inc. v. Rule Industries, Inc.
27 F.3d 521 (Eleventh Circuit, 1994)
U. S. Anchor Manufacturing, Inc. v. Rule Industries, Inc.
443 S.E.2d 833 (Supreme Court of Georgia, 1994)
J & a PIPELINE CO. v. DeKalb County
430 S.E.2d 13 (Court of Appeals of Georgia, 1993)
Mta Brokerage Consultants, Inc. v. Finkle
330 S.E.2d 419 (Court of Appeals of Georgia, 1985)
Henry v. Century Finance Co.
139 S.E.2d 123 (Court of Appeals of Georgia, 1964)
Bussell v. Glenn
30 S.E.2d 617 (Supreme Court of Georgia, 1944)
Greble v. Morgan
26 S.E.2d 494 (Court of Appeals of Georgia, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
185 S.E. 296, 53 Ga. App. 145, 1936 Ga. App. LEXIS 28, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eatonton-oil-auto-co-v-greene-county-gactapp-1936.