East Penn Sanitation, Inc. v. Grinnell Haulers, Inc.

682 A.2d 1207, 294 N.J. Super. 158
CourtNew Jersey Superior Court Appellate Division
DecidedSeptember 26, 1996
StatusPublished
Cited by15 cases

This text of 682 A.2d 1207 (East Penn Sanitation, Inc. v. Grinnell Haulers, Inc.) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
East Penn Sanitation, Inc. v. Grinnell Haulers, Inc., 682 A.2d 1207, 294 N.J. Super. 158 (N.J. Ct. App. 1996).

Opinion

294 N.J. Super. 158 (1996)
682 A.2d 1207

EAST PENN SANITATION, INC., PLAINTIFF-RESPONDENT,
v.
GRINNELL HAULERS, INC., SUSSEX COUNTY MUNICIPAL UTILITIES AUTHORITY, AND PETER COFRANCESCO, JR., DEFENDANTS-APPELLANTS.

Superior Court of New Jersey, Appellate Division.

Argued May 6, 1996.
Decided September 26, 1996.

*161 Before Judges PETRELLA, SKILLMAN and P.G. LEVY.

Marc J. Friedman argued the cause for appellants Grinnell Haulers, Inc. and Peter Cofrancesco, Jr. (Rich & Friedman, attorneys; Mr. Friedman, of counsel and on the brief).

Sharon Handrock Moore argued the cause for appellant Sussex County Municipal Utilities Authority (Gebhardt & Kiefer, attorneys; Ms. Moore, of counsel; Patricia S. Colabella, on the brief).

Nicholas I. Filocco argued the cause for respondent (Waters, McPherson, McNeill, attorneys; David A. Waters and Mr. Filocco, of counsel; James J. Seaman and Matthew Malfa, on the brief).

Rachel Boylan, Deputy Attorney General, argued the cause for amicus curiae Department of Environmental Protection (Deborah T. Poritz, Attorney General, attorney; Ms. Boylan, on the brief).

The opinion of the court was delivered by SKILLMAN, J.A.D.

These are consolidated appeals from a judgment memorializing a jury verdict awarding plaintiff $1,875,000 in compensatory damages for tortious interference with contract and breach of contract.

In the spring of 1987 defendant Sussex County Municipal Utilities Authority (SCMUA) entered into a contract with plaintiff *162 East Penn Sanitation, Inc. for the disposal of solid waste collected in Sussex County. This contract was entered into without competitive bidding because of a garbage crisis resulting from the closing of a landfill. The contract provided for separate methods of waste disposal during different "phases" of performance thereunder. In Phase I plaintiff agreed to receive waste collected in Sussex County at a transfer station located in Pennsylvania pending completion of construction of the Sussex County transfer station. Although the parties originally contemplated that Phase I would last no more than twelve weeks, the anticipated commencement of operations of the Sussex County transfer station was delayed for a substantial period of time, which resulted in numerous amendments to the contract that eventually extended the end of Phase I to July 15, 1988. In Phase II, which was scheduled to last for a term of twelve months, plaintiff agreed to transport waste from the Sussex County transfer station to a final disposal site. When plaintiff entered into this contract, it was not licensed by either the Department of Environmental Protection (DEP) or the Board of Public Utilities (BPU).

On November 4, 1987, defendant Peter Cofrancesco, Jr., President of defendant Grinnell Haulers, Inc. (Grinnell), informed the SCMUA's commissioners in a closed executive session that he was interested in transporting waste from the Sussex County transfer station at lower rates than would be charged by plaintiff. By letter dated November 17, 1987, the SCMUA Chairman, John Carroll, informed the County Freeholder Director that, in response to proposals from several trucking and disposal companies, SCMUA counsel Edward Buzak had considered the legal ramifications of negotiating with another hauler and had concluded that the SCMUA's contract with plaintiff was valid. Consequently, the SCMUA could not withdraw from the contract without incurring a risk of suit. Buzak also concluded that, absent an emergency, public bidding would be required before a contract could be awarded to another party.

*163 In late November of 1987, a freeholder sent a memo to Carroll which asserted that plaintiff would have to obtain licenses from both the DEP and BPU in order to perform Phase II of the contract, and that members of the DeLorenzo family, who were plaintiff's principals, were barred from doing business in New Jersey. After receiving this memo, the SCMUA directed Buzak to determine whether plaintiff was licensed by the DEP and BPU, and if not, whether this would prevent plaintiff from performing its obligations under the contract. Based on conversations with representatives of the DEP and BPU, Buzak discovered that although neither plaintiff nor its principals were barred from doing business in New Jersey, they in fact lacked both a BPU certificate of public convenience and necessity and a DEP solid waste registration. Buzak reported these findings to the SCMUA and also expressed the opinion that because of the history of alleged environmental violations at High Point Sanitation, a landfill owned by the DeLorenzos, "it would be very difficult, if not impossible, for [plaintiff] to obtain either of those licenses." Based on his conversations with BPU and DEP representatives, Buzak also advised the SCMUA that plaintiff could complete performance under the contract by subcontracting the hauling part of the work to a licensed hauler.

Thereafter, Grinnell and Cofrancesco continued to communicate with SCMUA and Sussex County officials regarding Grinnell's interest in hauling waste from the Sussex County transfer station to a disposal site. These defendants also questioned plaintiff's qualifications to perform Phase II of the contract in light of its lack of licensure by either the DEP or BPU. In addition, Grinnell sent a letter to the BPU objecting to the SCMUA's application for a solid waste franchise based on plaintiff's lack of a certificate of public convenience and necessity. These communications, which are the basis of plaintiff's tortious interference claims against Grinnell and Cofrancesco, are discussed in section III of this opinion.

*164 At a meeting with Buzak in early March of 1988, the BPU's representatives expressed doubt as to whether plaintiff could perform Phase II by subcontracting with a licensed hauler. Around this same time, the DEP took the position that plaintiff needed an approved registration before it could subcontract or assign the contract.

After learning of these changes in position on the part of the DEP and BPU, the SCMUA authorized the filing of a declaratory judgment action to determine whether plaintiff had the legal authority to perform Phase II and also authorized the solicitation of bids for a new contract for the work plaintiff was scheduled to perform under Phase II. This solicitation notified potential bidders that the SCMUA's acceptance of any bid would be contingent upon the outcome of the declaratory judgment action. Grinnell submitted the low bid in response to this solicitation.

The trial court in the declaratory judgment action concluded that plaintiff did not need to obtain a certificate of public convenience and necessity from the BPU in order to perform Phase II[1] but that it did need to obtain a registration statement and solid waste transporters' license from the DEP. The court also concluded that plaintiff could not circumvent these requirements by subcontracting or assigning the contract to another party. However, the court further determined that plaintiff should be afforded *165 a reasonable opportunity to obtain a registration and license from the DEP. Accordingly, the court ordered plaintiff to submit an application to the DEP no later than May 23, 1988.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D'AMBLY v. EXOO
D. New Jersey, 2021
Ranbaxy Laboratories Inc. v. First Databank, Inc.
826 F.3d 1334 (Eleventh Circuit, 2016)
Ziemkiewicz v. R + L Carriers, Inc.
996 F. Supp. 2d 378 (D. Maryland, 2014)
Brule v. Blue Cross and Blue Shield
455 F. App'x 836 (Tenth Circuit, 2011)
Cargill Global Trading v. APPLIED DEVELOPMENT COMPANY
706 F. Supp. 2d 563 (D. New Jersey, 2010)
Walnut Street Associates, Inc. v. Brokerage Concepts, Inc.
982 A.2d 94 (Superior Court of Pennsylvania, 2009)
Barnes v. St. Joseph's Hospital
1999 ND 204 (North Dakota Supreme Court, 1999)
Seal Tite Corp. v. Bressi
712 A.2d 262 (New Jersey Superior Court App Division, 1998)
United States v. Joint Meeting of Essex & Union Counties
997 F. Supp. 593 (D. New Jersey, 1998)
Ferraro v. Bell Atlantic Co., Inc.
955 F. Supp. 354 (D. New Jersey, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
682 A.2d 1207, 294 N.J. Super. 158, Counsel Stack Legal Research, https://law.counselstack.com/opinion/east-penn-sanitation-inc-v-grinnell-haulers-inc-njsuperctappdiv-1996.