Earth Resources Co. v. Federal Energy Regulatory Commission

617 F.2d 775, 199 U.S. App. D.C. 193, 10 Envtl. L. Rep. (Envtl. Law Inst.) 20091, 1980 U.S. App. LEXIS 21695
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 3, 1980
DocketNos. 79-2191, 79-2193
StatusPublished
Cited by4 cases

This text of 617 F.2d 775 (Earth Resources Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Earth Resources Co. v. Federal Energy Regulatory Commission, 617 F.2d 775, 199 U.S. App. D.C. 193, 10 Envtl. L. Rep. (Envtl. Law Inst.) 20091, 1980 U.S. App. LEXIS 21695 (D.C. Cir. 1980).

Opinion

Opinion for the Court filed by WILKEY, Circuit Judge.

WILKEY, Circuit Judge:

Complainants the State of Alaska and Earth Resources Company of Alaska challenge a Federal Energy Regulatory Commission (FERC) order setting design specifications and initial capacity for the Alaska segment of the Alaska National Gas Transportation System. This system comprises an overland pipeline through Canada to transport natural gas from the Alaska North Slope to the lower forty-eight states. To expedite the approval and construction of the pipeline system Congress established a special procedural framework in the Alaska Natural Gas Transportation Act (ANG-TA).1 Under the ANGTA courts possess only limited jurisdiction to review FERC orders concerning the pipeline system. We find that complainants do not state any claims properly within our limited jurisdiction. We therefore dismiss the petition.

I. FACTS

In September 1977, in accordance with procedures established by the ANGTA, the' President approved a proposal for the nature and route of the Alaska Natural Gas Transportation System.2 The President’s decision, subsequently ratified by Congress,3 left many specifics of the system open for later final decision by FERC and other agencies. Following the President’s decision, FERC granted a conditional certificate of public convenience and necessity for the construction of the Alaskan segment of the system. On 2 March 1979 Alaskan Northwest Natural Gas Transportation Company applied to FERC for a final order approving design specifications for a forty-eight inch diameter pipeline with 1260 psig (pounds per square inch gauge) maximum working pressure. Alaskan Northwest, an intervenor in this case, is the successor to the company designated by the President’s 1977 decision to construct and operate the Alaskan segment of the pipeline system.

[195]*195The FERC gave public notice of Alaskan Northwest’s application and invited comments. Two months later the Commission gave notice of a staff report on issues related to the application,4 and invited comments on the report. Complainants filed comments but did not request a hearing, and none was held. On 6 August 1979 the Commission issued an order approving Alaskan Northwest’s proposed pipeline diameter and pressure. After unsuccessfully petitioning FERC to vacate the order and to rehear the case, complainants appealed to this court to set aside the Commission’s order.

II. ANALYSIS

Our analysis in this case must follow the unique procedures that Congress established in the ANGTA to expedite construction of the Alaska natural gas pipeline. In an earlier decision of this court we described the passage of the ANGTA, the decision by the President subsequently ratified by Congress, and the procedural framework for agency action and judicial review under the ANGTA.5 We limit our exposition here to those factors essential to resolve the issues now before us.

A.

The ANGTA prevents us from reviewing agency decisions on the pipeline system for reasonableness or substantial support on the record. We are strictly limited to reviewing claims of denial of constitutional rights, or action in excess of statutory jurisdiction, authority, or limitations, or action short of statutory right.6 In Midwestern Gas Transmission Company v. FERC7 we acknowledged and followed these strict limitations on judicial review, limitations which were emphasized in the Congress’s very statement of purpose of the ANGTA.8

In the present case there can be no doubt that the Commission had statutory jurisdiction and authority to approve specifications of pipeline diameter and pressure. The Natural Gas Act authorizes the Commission to issue certificates for the transportation of natural gas,9 and the ANGTA specifically authorizes it to certify the Alaska pipeline system.10 We can review the Commission’s order, then,' only if petitioners state a claim of denial of constitutional rights or a claim that the Commission’s actions exceeded specific statutory limitations.

B.

Complainants claim that the Commission violated due process by deciding the pressure issue in isolation from decisions on such related issues as carbon dioxide content and conditioning plant design. By foreclosing options on these related issues, complainants contend, the Commission’s piecemeal decision on the pressure issue has rendered any future hearing on the related issues meaningless, thus denying due process rights regarding those issues.

In order to invoke the due process guarantee of a hearing, one must show that a government action infringes upon a liberty or property interest.11 Further, when the complaint concerns administrative action, due process hearing requirements apply only to adjudicatory proceedings, which concern particular effects on an individual [196]*196or a small group of persons.12 Complainants have met neither prerequisite. Complainants really do not assert any damage here from the FERC action, neither to the environment, nor to existing property interests, nor to any liberty interest. The most complainants have been able to point to is a possible impairment of the concept of Alaskan development which complainants — but not necessarily everyone — favor. The State of Alaska’s desire to develop a petrochemical industry, which it says will be frustrated by the Commission’s order, is far removed from the sort of legitimate claim to entitlement necessary to demonstrate a liberty or property interest.13 Moreover, to put the matter in broader perspective, the Commission’s decision on the pressure issue is a prospective, legislative resolution of a general policy issue, by rulemaking, which in contrast to an adjudication does not ¡give rise to the usual due process rights associated with a hearing.14 Therefore complainants have not stated a valid due process objection to the Commission’s actions.15

Complainants’ contention of “piecemeal adjudication” does not actually state a due process claim, but rather an attack on the Commission’s choice to structure its proceedings on an issue-by-issue basis. The Supreme Court has affirmed in the clearest terms that agencies have broad discretion to fashion their own procedures.16 Since complainants’ argument constitutes an attack on the reasonableness of the Commission’s exercise of its discretion, we have no jurisdiction under ANGTA to review.

c.

Complainants raise a further argument that the Commission has exceeded certain statutory limitations on its actions. First, they observe that the Commission has not acted within the normal framework for certificate applications under section 7(c) of the Natural Gas Act.17 Complainants state that Alaskan Northwest did not apply for a certificate, but only for an order on particular issues; that the FERC did not require the usual detailed supporting exhibits; and that the FERC did not fully consider all factors bearing on public necessity and convenience. These objections fly in the face of the ANGTA.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
617 F.2d 775, 199 U.S. App. D.C. 193, 10 Envtl. L. Rep. (Envtl. Law Inst.) 20091, 1980 U.S. App. LEXIS 21695, Counsel Stack Legal Research, https://law.counselstack.com/opinion/earth-resources-co-v-federal-energy-regulatory-commission-cadc-1980.