Earley Information Science, Inc. v. Omega Engineering, Inc.

CourtDistrict Court, D. Massachusetts
DecidedMay 5, 2021
Docket1:19-cv-10364
StatusUnknown

This text of Earley Information Science, Inc. v. Omega Engineering, Inc. (Earley Information Science, Inc. v. Omega Engineering, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Earley Information Science, Inc. v. Omega Engineering, Inc., (D. Mass. 2021).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF MASSACHUSETTS

_______________________________________ ) EARLEY INFORMATION SCIENCE, ) INC., ) ) Plaintiff, ) ) Civil Action No. v. ) 19-10364-FDS ) OMEGA ENGINEERING, INC., ) ) Defendant. ) _______________________________________)

MEMORANDUM AND ORDER ON DEFENDANT’S MOTION FOR PARTIAL SUMMARY JUDGMENT SAYLOR, C.J. This is a lawsuit arising out of a contract for data-organization services. In 2017, Omega Engineering, Inc., retained Earley Information Science, Inc., to organize and migrate product data to modernize Omega’s e-commerce platform. For reasons disputed by the parties, that effort was largely unsuccessful. Earley has sued Omega for breach of contract and several related claims. Omega has asserted counterclaims arising out of the same contract. Jurisdiction is based on diversity of citizenship. Omega has moved for summary judgment as to Earley’s claims for unfair trade practices under Massachusetts and Connecticut law. For the following reasons, that motion will be granted. I. Background A. Factual Background The following facts are as set forth in the record and are undisputed except as noted. Omega Engineering, Inc., is a Connecticut-based corporation that produces, distributes, and sells engineering products. (Def. SMF ¶¶ 1, 3-4; Vorih Dec. ¶ 3).1 In 2016, Omega asked Earley Information Science, Inc., to assess its external website to determine its suitability as an e- commerce platform. (Def. SMF ¶ 6). Earley made recommendations to modernize and improve

Omega’s e-commerce capabilities. (Id. ¶ 7). Those recommendations included implementing Product Information Management (“PIM”) to collect and manage data related to Omega’s products. (Id. ¶ 8). Omega then retained Earley to perform the PIM-implementation work. (Id. ¶ 10). That work was divided into two phases, each of which was memorialized in a separate Statement of Work. (Id.). Phase 1, which spanned approximately three months, was completed in April 2017. (Id.). Phase 2 was significantly broader in scope, duration, and cost. (Id.; see also Huber Dec. Ex. 1 (“Phase 2 Statement of Work”)). It was scheduled to last approximately one year and to cost more than $2 million. (Def. SMF ¶ 10). In late 2017 or early 2018, Omega began to have concerns about the progress of the work. (Def. SMF ¶ 19; Brolet Dep. 28-29; Wiener 30(b)(6) Dep. at 157).2 Kathleen Wiener,

Director of Global Master Data Management for Omega (and Omega’s 30(b)(6) deponent), testified that she first “came to the conclusion that Earley had not done some or all of what it was supposed to do under the [Statement of Work]” during the “end of February [or] early March.” (Wiener 30(b)(6) Dep. at 157). On March 13, 2018, employees from Omega and Earley met to

1 Earley disputes that “the production, distribution, and sale of engineering products and equipment” represents Omega’s “primary line of business” as that term is used in case law related to the Connecticut Unfair Trade Practices Act. (Pl. Resp. to Def. SMF ¶¶ 3-4). 2 Earley disputes this statement to the extent that it implies that the parties agree about the scope of work required by the Phase 2 Statement of Work. (Pl. Resp. to Def. SMF ¶ 19). Early also contends that the problems and delays executing the Phase 2 work were “attributable to Omega and/or vendors chosen by Omega.” (Pl. Opp. at 3). It does not appear to dispute, however, that Omega was concerned about the work by this time. discuss the progress of the work. (Def. SMF ¶ 21; Schweizer Dep. at 152-55; Schweizer Dep. Ex. 10, at 1). At that meeting, according to Chantal Schweizer, a consultant at Omega, Wiener “was very concerned with gap fill and wanted to know why it [had not] been brought to her attention that gap fill [was not] as near 100% as she was expecting it to be.” (Schweizer Dep.

Ex. 10, at 1). Wiener also indicated that she believed that there might be a “need to start from scratch.” (Id.). About one week later, on March 21, employees from Omega and Earley held another meeting. (Anthony Dec. ¶ 7). At that meeting, according to Earley’s Vice President of Delivery Michael Anthony, “Omega’s representatives expressed dissatisfaction with the status of the Project but also admitted that Omega was at fault for certain problems and delays.” (Id.). The next day, the parties reconvened. (Def. SMF ¶ 25). Earley had prepared a PowerPoint presentation titled “EIS PIM Implementation Phase 2 Close-Out Discussion.” (Ali Dep. Ex. 32 (“Close-Out Meeting Presentation”) at 1). The parties discussed the work completed thus far by Earley. (Anthony Dec. ¶ 10; Close-Out Meeting Presentation at 2). They

further discussed Omega’s concerns and the work remaining for Phase 2. (Anthony Dec. ¶ 10; Close-Out Meeting Presentation at 3). According to Anthony, they “agreed upon a ‘punch list’ of the remaining deliverables that [Earley] would provide to Omega to complete the work that [Earley] would be doing on the Project.” (Anthony Dec. ¶ 10). Anthony further states that Earley “made it 100% clear” to Omega that, upon completion of that work, it would be delivering “33% of the individual product level data,” rather than 100% of that data. (Id.; see also Close-Out Meeting Presentation at 6).3

3 Omega contends that Earley admitted that it “could not complete 100% of the work” required under the Phase 2 Statement of Work. (Def. SMF ¶¶ 28-29). Early disputes that failure to complete 100% of the data- According to Anthony, “Omega’s representatives clearly stated that after [Earley] completed the agreed-upon punch list tasks, Omega would pay [Earley] the remaining amount owed to it under the PIM Phase 2 [Statement of Work].” (Anthony Dec. ¶ 12). By this time, Omega had paid Earley about $1.85 million on the Phase 2 Statement of Work, which had a cap

of approximately $2 million. (Huber Dec. Ex. 6; Ali Dep. 175-77; Phase 2 Statement of Work at 19). Earley subsequently “dedicated significant time and resources to completing those tasks,” which it contends it finished in April 2018. (Anthony Dec. ¶¶ 12, 18). Approximately two weeks after the close-out meeting, on April 4, 2018, Omega issued a purchase order for $150,000. (Anthony Dec. Ex. F (“April 4, 2018 Purchase Order”)). The parties dispute the reason for that order. Omega contends that it was generated “[a]s part of the schedule of purchase orders contemplated in the PIM Phase 2 [Statement of Work].” (Def. SMF ¶ 31). It notes that $150,000 was “the approximate amount remaining” under that Statement of Work. (Id.). Michael Ali, Omega’s Chief Information Officer, testified that he believed that the purchase order “would have . . . been generated as part of [the] schedule” under the Phase 2

Statement of Work. (Ali Dep. at 178; see also id. at 179). He had sent an e-mail shortly before the close-out meeting stating that Omega “owe[d] roughly $150K against the original $2.003M contract” and that Omega “would expect to pay that $150K once [it] receive[d] the final deliverables (still to be agreed [to] . . .).” (Huber Dec. Ex. 6). Likewise, Wiener testified that the $150,000 purchase order was “part of the overarching [Statement of Work]” and “all that was left of the balance of the PO for the entire contract.” (Wiener 30(b)(6) Dep. at 145; see also id. at 146 (“It was just simply the balance that Earley felt they were owed against the original two

migration work is the same as failure to fulfill its obligations under the Phase 2 Statement of Work. (Pl. Resp. to Def. SMF ¶¶ 28-29). million I believe contract.”)). Earley disputes that the purchase order was issued to cover the balance remaining under the Phase 2 Statement of Work. (Pl. Resp. to Def. SMF ¶¶ 31-32, 34). It contends that the order “equaled neither the remaining amount owed to [Earley] (approximately $180,000) nor the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Ahern v. Scholz
85 F.3d 774 (First Circuit, 1996)
Arthur D. Little, Inc. v. Dooyang Corp.
147 F.3d 47 (First Circuit, 1998)
Jasty v. Wright Medical Technology, Inc.
528 F.3d 28 (First Circuit, 2008)
Milissa Garside v. Osco Drug, Inc.
895 F.2d 46 (First Circuit, 1990)
Samuel Mesnick v. General Electric Company
950 F.2d 816 (First Circuit, 1991)
Patrick J. O'COnnOr v. Robert W. Steeves
994 F.2d 905 (First Circuit, 1993)
Naples v. Keystone Building & Development Corp.
990 A.2d 326 (Supreme Court of Connecticut, 2010)
PMP Associates, Inc. v. Globe Newspaper Co.
321 N.E.2d 915 (Massachusetts Supreme Judicial Court, 1975)
Atkinson v. Rosenthal
598 N.E.2d 666 (Massachusetts Appeals Court, 1992)
Southern New England Telephone Co. v. Global Naps, Inc.
482 F. Supp. 2d 216 (D. Connecticut, 2007)
Bamberg v. Goldman, Sachs & Co.
771 F.3d 37 (First Circuit, 2014)
Duclersaint v. Federal National Mortgage Ass'n
696 N.E.2d 536 (Massachusetts Supreme Judicial Court, 1998)
Zabin v. Picciotto
896 N.E.2d 937 (Massachusetts Appeals Court, 2008)
Votto v. American Car Rental, Inc.
871 A.2d 981 (Supreme Court of Connecticut, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Earley Information Science, Inc. v. Omega Engineering, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/earley-information-science-inc-v-omega-engineering-inc-mad-2021.