Eagle Wine & Liquor Co. v. Silverberg Electric Co.

402 A.2d 31, 1979 D.C. App. LEXIS 359
CourtDistrict of Columbia Court of Appeals
DecidedMay 2, 1979
Docket13051
StatusPublished
Cited by26 cases

This text of 402 A.2d 31 (Eagle Wine & Liquor Co. v. Silverberg Electric Co.) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eagle Wine & Liquor Co. v. Silverberg Electric Co., 402 A.2d 31, 1979 D.C. App. LEXIS 359 (D.C. 1979).

Opinion

HARRIS, Associate Judge:

This is an appeal from (1) the trial court’s denial of a motion by plaintiff-appellant Eagle Wine & Liquor Company (and seven subrogated insurance carriers, collectively referred to hereinafter as Eagle) for leave to amend their complaint, (2) the subsequent granting of defendant-appellee Sil-verberg Electric Company’s motion for summary judgment, and (3) the denial of plaintiffs’ motion for reconsideration of the court’s earlier ruling on the proffered amendment. We conclude that the trial court did not err in denying leave to amend, and accordingly affirm. 1

I

The dispute arose out of a fire which occurred on January 5, 1973, on Eagle’s premises. The fire caused substantial property damage. Investigation at the time of, and shortly after, the incident indicated that the cause of the fire was electrical in nature, originating from a short circuit in a length of cable used to supply power to a baling machine. The baler had been sold to Eagle by Maren Engineering Company, and was installed in early June of 1972 by an electrician employed by appellee Silverberg. Eagle collected on its various insurance policies which were in effect at the time of the fire, thereby apparently recouping its property damage. The insurance carriers asserted their subrogation rights against both Maren and Silverberg, and Eagle and its insurers accordingly filed a complaint against those two companies on July 7, 1975.

*33 The original complaint, filed two and one-half years after the fire, included two counts against Maren (breach of warranty for the sale, and negligence in the construction and assembly of the baler) and one count against Silverberg (negligence in failing to properly install the baler). The plaintiffs sought $100,000 in damages against each of the two defendants.

At the time of filing the complaint, the plaintiffs had not pinpointed the cause of the short circuit in the cable. The three counts in the complaint thus reflected the theories of recovery which seemed most plausible after preliminary investigation by fire department officials and appellants’ experts. The underlying assumption was that a current overload had caused the short circuit, and certain theories were propounded. Maren, it was alleged, had breached a warranty that the baler would have built-in protection against current overload, and/or had been negligent in constructing the machine so as to permit an overload. In addition, the complaint alleged that Silverberg’s negligence in installing and wiring the baler caused the overload. More specifically, plaintiffs alleged that Silverberg was negligent in failing to remedy an existing overload in the electrical system and/or in tampering with the electrical system inside the machine.

Interrogatories served by Eagle upon the two defendants reflected those theories. Silverberg’s and Maren’s answers to the complaint were filed on September 5 and December 16,1975, respectively. Maren responded to Eagle’s interrogatories on January 28, 1976, and Silverberg responded on February 23, 1976. From one of Silver-berg’s responses as to the specific size of the cable used in the installation of the machine, Eagle developed the theory that Sil-verberg had been negligent in using cable which was too small for the requisite current flow.

Trial had been set for June 17, 1976. However, during the preceding months, Eagle, upon further reflection and investigation, was abandoning its original theories in favor of several new ones, including the small wire theory. Thus Eagle delayed in responding to interrogatories which had been served by both defendants on February 11,1976. On motion of defendant Mar-en, the court postponed the trial indefinitely while ordering Eagle to respond to the interrogatories.

In responding to Maren’s interrogatories on August 2, 1976, Eagle indicated that it had no evidence to support the original theories of liability on Maren’s part, but it asserted that its expert now believed that the installer — Silverberg—failed properly to affix an exposed portion of the cable to the wall as required by law. In addition, it was suggested for the first time that a defect in the cable itself was the cause of the short circuit and fire. Eagle deposed Silverberg’s installing electrician in early October of 1976. Then, after four more months of consideration, Eagle came forward with a “walking” theory in a response filed February 16, 1977, to Silverberg’s interrogatories. That is, Eagle now contended that the installer had failed to secure the baler properly to the surface on which it was placed, allowing it to move (or “walk”) from vibration while in operation — thus creating tension, and eventually a crimp, in the connecting cable, ultimately causing the resultant short circuit.

Finally, Eagle’s expert, at a deposition still six months later (on August 4, 1977), revealed that Eagle then was embracing the faulty cable theory which had been briefly considered a year before. It now appears that this, in fact, is the correct — or at least the most likely — theory. However, Eagle apparently recognized that under the original complaint recovery could not be had from Silverberg, for the latter had purchased the cable in question from a manufacturer, and the installing electrician could not reasonably have been expected to find the defect in the cable insulation. Thus it could not be said that Silverberg was liable for negligence.

Therefore, Eagle moved on August 6, 1977, for leave to amend its complaint to include a count for breach of express and implied warranties by Silverberg that the *34 wiring materials installed would be of merchantable quality, free from safety defects. The trial judge denied Eagle’s motion after considering memoranda filed both in support and in opposition, and after hearing oral argument. The court cited Eagle’s delays in moving the litigation forward, which it concluded were “substantially prejudicial” to Silverberg.

Following the denial, Eagle filed a prae-cipe dropping Maren as a defendant. Soon thereafter Silverberg filed a motion for summary judgment. In opposing Silver-berg’s motion, Eagle asked the court to reconsider its denial of leave to amend. This the court declined to do, and it granted Silverberg’s motion for summary judgment.

Eagle appealed, claiming that the trial court abused its discretion in denying leave to amend. In its brief, as it had in its memorandum in support of the original motion, Eagle emphasizes that it has not been unduly dilatory, has exhibited no bad faith, and that the amendment was sought pretrial — indeed, before a trial date had even been set. Eagle further contends that Sil-verberg would not suffer any real prejudice were Eagle allowed to amend its complaint.

II

Super.Ct.Civ.R. 15(a), governing amendments, states in pertinent part:

A party may amend his pleading once as a matter of course at any time before a responsive pleading is served or, if the pleading is one to which no responsive pleading is permitted and the action has not been placed upon the trial calendar, he may so amend it at any time within 20 days after it is served. Otherwise a party may amend his pleading only by leave of court or by written consent of the adverse party; and leave shall be freely given when justice so requires.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Andrews v. DCHA
District of Columbia Court of Appeals, 2024
Edwards v. Safeway, Inc.
District of Columbia Court of Appeals, 2019
Mazza v. HOUSECRAFT LLC
18 A.3d 786 (District of Columbia Court of Appeals, 2011)
Pellerin v. 1915 16th Street Cooperative Ass'n
980 A.2d 1234 (District of Columbia Court of Appeals, 2009)
Coulter v. Gerald Family Care, P.C.
964 A.2d 170 (District of Columbia Court of Appeals, 2009)
Taylor v. District of Columbia Water & Sewer Authority
957 A.2d 45 (District of Columbia Court of Appeals, 2008)
Pannell v. District of Columbia
829 A.2d 474 (District of Columbia Court of Appeals, 2003)
Paul v. Bier
758 A.2d 40 (District of Columbia Court of Appeals, 2000)
Sherman v. Adoption Center of Washington, Inc.
741 A.2d 1031 (District of Columbia Court of Appeals, 1999)
Killingham v. Wilshire Investments Corp.
739 A.2d 804 (District of Columbia Court of Appeals, 1999)
Francis v. Recycling Solutions, Inc.
695 A.2d 63 (District of Columbia Court of Appeals, 1997)
District of Columbia v. Tinker
691 A.2d 57 (District of Columbia Court of Appeals, 1997)
Howard University v. Good Food Services, Inc.
608 A.2d 116 (District of Columbia Court of Appeals, 1992)
Adams v. George W. Cochran & Co., Inc.
597 A.2d 28 (District of Columbia Court of Appeals, 1991)
Ching & Sun v. Future Communications, Inc.
23 Va. Cir. 249 (Virginia Circuit Court, 1991)
Professional Answering Service, Inc. v. Chesapeake & Potomac Telephone Co.
565 A.2d 55 (District of Columbia Court of Appeals, 1989)
Joyner v. Jonathan Woodner Co.
479 A.2d 308 (District of Columbia Court of Appeals, 1984)
Goldkind v. Snider Bros., Inc.
467 A.2d 468 (District of Columbia Court of Appeals, 1983)
Gordon v. Raven Systems & Research, Inc.
462 A.2d 10 (District of Columbia Court of Appeals, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
402 A.2d 31, 1979 D.C. App. LEXIS 359, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eagle-wine-liquor-co-v-silverberg-electric-co-dc-1979.