E TX Elec Coop Inc v. FERC

218 F.3d 750
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 25, 2000
Docket99-1222
StatusPublished

This text of 218 F.3d 750 (E TX Elec Coop Inc v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E TX Elec Coop Inc v. FERC, 218 F.3d 750 (D.C. Cir. 2000).

Opinion

218 F.3d 750 (D.C. Cir. 2000)

East Texas Electric Cooperative, Inc., et al.,Petitioners
v.
Federal Energy Regulatory Commission, Respondent
Central Power and Light Company, et al., Intervenors

No. 99-1222

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued April 10, 2000
Decided July 25, 2000

On Petition for Review of Orders of theFederal Energy Regulatory Commission

A. Hewitt Rose, III argued the cause for the petitioners.

David H. Coffman, Attorney, Federal Energy Regulatory Commission, argued the cause for the respondent. John H. Conway, Acting Solicitor, Federal Energy Regulatory Commission, was on brief. Jay L. Witkin, Solicitor, and Susan J. Court, Counsel, Federal Energy Regulatory Commission, entered appearances.

Clark Evans Downs argued the cause for the Intervenors. Martin V. Kirkwood was on brief.

Before: Edwards, Chief Judge, Henderson and Rogers, Circuit Judges.

Opinion for the court filed by Circuit Judge Henderson.

Karen LeCraft Henderson, Circuit Judge:

Petitioners East Texas Electric Cooperative, Inc., Northeast Texas Electric Cooperative, Inc. and Tex-La Electric Cooperative of Texas, Inc. (collectively, Texas Electric) seek review of three orders of the Federal Energy Regulatory Commission (FERC, Commission) ultimately approving the open access transmission tariff the CSW Operating Companies (CSW)1 proposed for their provision of electric power to Texas Electric, inter alia. Texas Electric argues that the Commission, in its Tariff Order, Central Power & Light Co., 81 F.E.R.C. p 61,311 (1997), accepted certain rates included in CSW's proposed rates but rejected and ordered modification of another. CSW not only responded to the Commission's directive regarding modification of the specified rate, they also eliminated a different rate which, Texas Electric argues, had been accepted and was therefore not supposed to be eliminated. The Commission accepted CSW's compliance filing in relevant part in its Compliance Order, Central Power & Light Co., 85 F.E.R.C. p 61,224 (1998), including the alleged rate change resulting from the elimination of the rate earlier accepted. Finally, in its Rehearing Order, Central Power & Light Co., 87 F.E.R.C. p 61,073 (1999), the Commission rejected Texas Electric's arguments and concluded CSW had complied with the Tariff Order directives.

Texas Electric argues, citing 16 U.S.C. § 824d, that CSW failed to justify the rate change as the Federal Power Act (Act) requires and that the Commission's acceptance, without explanation, of CSW's compliance filing and its resulting approval of CSW's elimination of the previously accepted charge (thereby effecting a rate change) also failed to satisfy the Commission's duty under the Administrative Procedure Act, 5 U.S.C. § 706(2). Texas Electric further contends the new rates unduly discriminate against it (and other CSW customers) and that the Commission violated its duty under the Act, 16 U.S.C. § 824e, to assure that rates are not unduly discriminatory.

The Commission on the other hand claims it did not accept the proposed rates in the Tariff Order and that nothing therein prohibited CSW from eliminating the rate at issue. Rather, the Commission claims that its Tariff Order makes clear the decision was left to CSW's discretion. We defer to FERC's interpretation of its Tariff Order as not limiting CSW's revised transmission tariff. We conclude, however, that the Tariff Order did not sufficiently notify Texas Electric of CSW's discretion to modify the original proposal, particularly in light of the Tariff Order's language approving the rates at issue. Hence Texas Electric's failure to seek rehearing does not bar it from raising this issue before us. Moreover, the Commission failed to explain why the revised tariff was lawful, that is, just and reasonable. Given that the revision at issue could not fairly have been anticipated by Texas Electric, the Commission erred in summarily approving that part of the Compliance Tariff without explaining whether the new rates were just and reasonable; accordingly, we remand for FERC to make that determination.

I.

The CSW System operates in two power districts: the Southwest Power Pool (SPP) and the Electric Reliability Council of Texas (ERCOT). Of the four operating companies in the CSW System, two are entirely within SPP and the other two areentirely within ERCOT.2 CSW's facilities are interconnected, however, forming a single, integrated system.

In 1996 FERC addressed the rate systems of public utilities, like those comprising CSW, who are members of registered public utilities holding companies. In Order No. 888 (filed May 10, 1996), Promoting Wholesale Competition Through Open Access Non-discriminatory Transmission Services by Public Utilities, FERC Stats. & Regs. p 31,035, 61 Fed. Reg. 21,540 (1996), codified as revised at 18 C.F.R. Pts. 35 & 385 (1999),3 which resulted from a rule-making proceeding designed to remedy undue discrimination in the transmission of electric power, FERC required all such utilities to file a tariff permitting transmission service across the holding company's entire system at a single price. See Transmission Access Policy Study Group, 2000 WL 762706, at *3, *5 (D.C. Cir. June 30, 2000); see also Tariff Order, 81 F.E.R.C. at 62,430 (discussing Order No. 888). Thus, individual member utilities within a holding company could no longer charge separate, "pancaked" rates4 for what is a single transmission over the holding company's system. Id. at 62,432.Instead, the utilities must provide the transmission under a single rate, resulting in a de facto reduction of the overall charge. FERC addressed the CSW System specifically, directing the utilities therein to file "a system tariff that will provide comparable service to all wholesale users on the CSW System, regardless of whether they take transmission service wholly within ERCOT or the SPP, or take transmission service between the reliability councils over the North and East Interconnections." Order No. 888, 61 Fed. Reg. at 21,595. Furthermore, FERC noted that "[i]t may be appropriate to have different rates for transmission service wholly within ERCOT or the SPP, and for service between [them]."Id. at 21,595 n.422.

CSW filed a proposed transmission tariff that provided separate rates for wholly intra-ERCOT service and wholly intra-SPP service but did not provide a single CSW System wide rate for transmissions through both ERCOT and SPP.Thus, customers requiring service traversing the SPP ERCOT boundary would pay pancaked rates. In its Tariff Order the Commission analyzed CSW's separate rates for the two service areas (ERCOT and SPP) and determined that the rate structures were reasonable.

Assessing different rates for service in the different regions is reasonable....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
218 F.3d 750, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-tx-elec-coop-inc-v-ferc-cadc-2000.