E. Paul Kovacs & Co. v. Alpert

429 A.2d 829, 180 Conn. 120, 1980 Conn. LEXIS 756
CourtSupreme Court of Connecticut
DecidedMarch 18, 1980
StatusPublished
Cited by21 cases

This text of 429 A.2d 829 (E. Paul Kovacs & Co. v. Alpert) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E. Paul Kovacs & Co. v. Alpert, 429 A.2d 829, 180 Conn. 120, 1980 Conn. LEXIS 756 (Colo. 1980).

Opinion

Cotter, C. J.

The plaintiff which is a company engaged in the land development business including excavation work to prepare land for the construction of buildings brought suit to recover an amount due and owing for labor and materials provided in *122 connection with the clearing and excavation of the defendants’ property. From the judgment rendered in favor of the plaintiff the defendants have appealed.

The defendants seek the deletion of twenty-six paragraphs of the finding on the ground that they were found without evidence and the addition to the finding of forty-one paragraphs of their draft finding claiming that the facts stated in those paragraphs are admitted or undisputed. The defendants’ wholesale attack on the finding is to no avail. The facts sought to be deleted are amply supported by the evidence and hence must remain a part of the finding. Bond v. Benning, 175 Conn. 308, 309, 398 A.2d 1158. Also, to secure an addition to the finding, “it is necessary for an appellant to point to some part of the appendix, the pleadings, or an exhibit properly before us which discloses that the appellee admitted that the fact in question was true or that its truth was conceded to be undisputed.” Cohen v. Holloways’, Inc., 158 Conn. 395, 397, 260 A.2d 573; Martin v. Kavanewsky, 157 Conn. 514, 515, 255 A.2d 619. A fact is not admitted or undisputed merely because it has not been contradicted since the credibility of the witness is for the trier; McLaughlin v. Chicken Delight, Inc., 164 Conn. 317, 321 A.2d 456; Morrone v. Jose, 153 Conn. 275, 277, 216 A.2d 196; and with only three witnesses presented at the trial whose testimony was in dispute and contradicted, the determination of what actually transpired between the parties is peculiarly dependent on the credibility of the witnesses. The defendants fail to include any evidence in their appendix which establishes that the plaintiff admitted any of the facts sought to be added or that such facts were undisputed. Accordingly, the *123 only permissible correction to the finding is the addition of seven paragraphs of the defendants’ draft finding to which the plaintiff has stipulated.

The finding, as corrected, discloses the following: The defendants, Norman and Theodora Alpert, engaged Joseph Twardy as their agent with the responsibility of preparing their then vacant property for the construction of their house. In his efforts to obtain price quotations for the excavation portion of the site preparation, in March, 1971, Twardy met on the property with Jerome Kovacs, who was then the construction supervisor and vice-president of the plaintiff E. Paul Kovacs & Co., Inc. At that meeting, without performing any tests to determine the rock composition of the property, Kovacs gave Twardy a copy of the plaintiff’s price list for labor, machine time, and materials and stated that the plaintiff would prepare the site for construction by performing the necessary clearing and excavation work on a time and materials basis. In response to Twardy’s request and based on his estimate that the site to be excavated was 50 percent earth and 50 percent rock, Kovacs, although unaware of the type of rock that was on the property, in a letter dated March 31,1971 and addressed to Twardy, provided an estimate of the total cost of the excavation job based on the price of labor and materials indicated in the price list shown to Twardy. Shortly thereafter, Twardy told Kovacs to commence with clearing and excavation.

Initial earth removal began on April 14, 1971 and was completed in eighteen hours of work. For that work, the plaintiff billed Norman Alpert who paid the amount of the bill on or about May 29, 1971. The plaintiff began drilling and blasting oper *124 ations on May 3, 1971. After five or six days of blasting, little progress was made and Kovacs informed Twardy that the cost of the excavation would be considerably higher than the amount originally estimated in the March 31 letter. Twardy, who was aware of the progress being made and of the hourly rates for the labor and machinery being used on the job, directed Kovacs to continue the excavation.

The blasting and excavation continued until June 21, 1971, when Kovacs was told to cease work. Throughout the entire project the plaintiff’s employees worked diligently under the supervision of Twardy. Of the work to be done listed in the March 31 letter, only three items, with an estimated cost of $3200, were actually performed. In its final bill dated July 1, 1971, the plaintiff requested payment for the outstanding balance of $14,635.81 which was based on the time and materials charges for the plaintiff’s excavation work. The defendants’ refusal to pay that bill precipitated the present lawsuit.

On the basis of the foregoing facts, the trial court concluded that the defendants had entered into a contract with the plaintiff for the clearing and excavation of the defendants’ property on a time and materials basis. It further found that the plaintiff was authorized to continue excavation even though it became apparent that the estimated cost would be exceeded. In accordance with the labor and materials price list shown to Twardy, the court awarded judgment in favor of the plaintiff in the amount of $14,635.81 plus interest.

The defendants claim error in the conclusion of the trial court that a contract to provide labor and *125 equipment on a time and materials basis existed between themselves and the plaintiff. The defendants contend that Twardy, who they concede was their agent with regard to the excavation of their property, lacked authority to enter into a time and materials contract on their behalf and they therefore could not be bound to the contract found to exist by the trial court.

As a general rule, a principal may be bound to contracts executed by an agent if it is within the agent’s authority to contract on behalf of that principal; see Hollywyle Assn., Inc. v. Hollister, 164 Conn. 389, 396, 324 A.2d 247; Cohen v. Holloways’, Inc., supra; Cinque v. Orlando, 140 Conn. 591, 592, 102 A.2d 532; 3 Am. Jur. 2d, Agency § 312; Restatement (Second), Agency §§ 140,186; and the authority to enter into a specified contract includes the authority to make it in the usual form and with usual terms. See Restatement (Second), Agency § 51; 3 Am. Jur. 2d, Agency § 84. The defendants do not claim that Twardy lacked authority to enter into contracts with excavation contractors such as the plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Raftopol v. Ramey
12 A.3d 783 (Supreme Court of Connecticut, 2011)
Royal Insurance Co. of America v. Zygo Corp.
349 F. Supp. 2d 295 (D. Connecticut, 2004)
Updike, Kelly & Spellacy, P.C. v. Beckett
850 A.2d 145 (Supreme Court of Connecticut, 2004)
111 Whitney Avenue, Inc. v. Commissioner of Mental Retardation
802 A.2d 117 (Connecticut Appellate Court, 2002)
Hjarne v. Martin, No. Fa00-0631333 (Apr. 21, 2002)
2002 Conn. Super. Ct. 5521-aa (Connecticut Superior Court, 2002)
Il Giardino, LLC v. Belle Haven Land Co.
757 A.2d 1103 (Supreme Court of Connecticut, 2000)
Doe v. Doe
710 A.2d 1297 (Supreme Court of Connecticut, 1998)
Community Collaborative of Bridgeport, Inc. v. Ganim
698 A.2d 245 (Supreme Court of Connecticut, 1997)
State v. Scott
626 A.2d 817 (Connecticut Appellate Court, 1993)
State v. Crumble
585 A.2d 1245 (Connecticut Appellate Court, 1991)
Dover Court Condo. Assoc. v. Shea Roofing, No. 27 99 20 (Oct. 3, 1990)
1990 Conn. Super. Ct. 2808 (Connecticut Superior Court, 1990)
E. Udolf, Inc. v. Aetna Casualty & Surety Co.
573 A.2d 1211 (Supreme Court of Connecticut, 1990)
Newtown Associates v. Northeast Structures, Inc.
546 A.2d 310 (Connecticut Appellate Court, 1988)
Rascati v. McClinch Crane, Inc.
525 A.2d 133 (Connecticut Appellate Court, 1987)
Bank of Montreal v. Gallo
487 A.2d 1101 (Connecticut Appellate Court, 1985)
Stelco Industries, Inc. v. Bette
475 A.2d 1105 (Connecticut Appellate Court, 1984)
Hartford Division, Emhart Industries, Inc. v. Amalgamated Local Union 376
461 A.2d 422 (Supreme Court of Connecticut, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
429 A.2d 829, 180 Conn. 120, 1980 Conn. LEXIS 756, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-paul-kovacs-co-v-alpert-conn-1980.